PMI CAPM Practice Test 43
Question 420
For an original CAPM project delivery study scenario, consider: A refurbishment reports EV=210 and AC=195 cost units, while the manager describes a fifteen-unit overrun despite delivering more value than was spent. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Check: Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control.
- Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
- Treat every positive planned value as proof actual cost is within the approved budget regardless of what has been spent.
- Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
- Check: Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
Explanation
Correct Answer
B:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. Evidence: Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
E:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. Required intervention: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
Incorrect Answers
A:Check: Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
C:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
D:Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
Question 421
A CAPM project team analyst is reviewing this delivery scenario: A software project reports EV=90 PV=120 AC=100 cost units but its manager states CPI and SPI exceed one because both budgets are large. An unsafe shortcut would be: Set both performance indices equal to actual spending divided by planned spending without using earned value. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Set both performance indices equal to actual spending divided by planned spending without using earned value.
- Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule.
- Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
- Identify the organization's functional, matrix or projectized decision rights and negotiate resource commitments through the recognized management structure.
Explanation
Correct Answer
C:This targeted action addresses the observed delivery, governance or stakeholder-decision gap without discarding necessary controls. Applied case: A software project reports EV=90 PV=120 AC=100 cost units but its manager states CPI and SPI exceed one because both budgets are large.
Incorrect Answers
A:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
B:Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
D:This option addresses a different CAPM project management topic (Organizational matrix authority) rather than the documented CPI and SPI index interpretation decision.
Question 422
CAPM predictive scheduling and earned-value calculation. A software project reports EV=90 PV=120 AC=100 cost units but its manager states CPI and SPI exceed one because both budgets are large. What are the cost performance index CPI and schedule performance index SPI, rounded to two decimals? Select ONE best answer.
- CPI = 0.90; SPI = 0.75
- CPI = 0.75; SPI = 0.90
- CPI = 0.90; SPI = 1.20
- CPI = 1.11; SPI = 1.33
Explanation
Correct Answer
A:CPI = 0.90; SPI = 0.75 This is the correct result. CPI=EV/AC=90/100=0.90; SPI=EV/PV=90/120=0.75; both are below one.
Incorrect Answers
B:CPI = 0.75; SPI = 0.90 This result is inconsistent with the required calculation. This reverses the actual-cost and planned-value denominators. Correct work: CPI=EV/AC=90/100=0.90; SPI=EV/PV=90/120=0.75; both are below one.
C:The SPI does not equal 1.20 when EV is less than PV.
D:This uses reciprocal measures instead of EV divided by cost or planned value.
Question 423
The project team has not approved a broad project-plan change. Available evidence indicates: A software project reports EV=90 PV=120 AC=100 cost units but its manager states CPI and SPI exceed one because both budgets are large. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
- Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances.
- Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.
- Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
Explanation
Correct Answer
D:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
Incorrect Answers
A:Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
B:Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
C:Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
Question 424
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A software project reports EV=90 PV=120 AC=100 cost units but its manager states CPI and SPI exceed one because both budgets are large. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario.
- Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
- The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip.
- CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.
Explanation
Correct Answer
D:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
Incorrect Answers
A:The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
B:Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
C:The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
Question 425
An implementation sign-off request identifies the following problem: A software project reports EV=90 PV=120 AC=100 cost units but its manager states CPI and SPI exceed one because both budgets are large. Which paired project management action and verification should close the review? Select ONE best answer.
- Change: Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified. Verify: Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
- Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately. Verify: Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
- Change: Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule. Verify: Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship.
- Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms. Verify: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
Explanation
Correct Answer
B:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
Incorrect Answers
A:Change: Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified.
C:Change: Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
D:Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
Question 426
A CAPM project team analyst is reviewing this delivery scenario: A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget. An unsafe shortcut would be: Set both performance indices equal to actual spending divided by planned spending without using earned value. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.
- Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.
- Set both performance indices equal to actual spending divided by planned spending without using earned value.
- Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
Explanation
Correct Answer
D:This targeted action addresses the observed delivery, governance or stakeholder-decision gap without discarding necessary controls. Applied case: A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget.
Incorrect Answers
A:This option addresses a different CAPM project management topic (Critical path duration arithmetic) rather than the documented CPI and SPI index interpretation decision.
B:Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
C:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
Question 427
CAPM predictive scheduling and earned-value calculation. A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget. Calculate CPI and SPI, rounded to two decimals, and keep cost distinct from schedule. Select ONE best answer.
- CPI = 0.90; SPI = 0.90
- CPI = 0.90; SPI = 1.20
- CPI = 1.11; SPI = 0.83
- CPI = 1.20; SPI = 0.90
Explanation
Correct Answer
B:CPI = 0.90; SPI = 1.20 This is the correct result. CPI=144/160=0.90 below one; SPI=144/120=1.20 above one, so cost is unfavorable while schedule value is ahead.
Incorrect Answers
A:CPI = 0.90; SPI = 0.90 This result is inconsistent with the required calculation. SPI uses planned value 120, not actual cost 160. Correct work: CPI=144/160=0.90 below one; SPI=144/120=1.20 above one, so cost is unfavorable while schedule value is ahead.
C:CPI = 1.11; SPI = 0.83 This result is inconsistent with the required calculation. These values use reciprocal ratios. Correct work: CPI=144/160=0.90 below one; SPI=144/120=1.20 above one, so cost is unfavorable while schedule value is ahead.
D:CPI = 1.20; SPI = 0.90 This result is inconsistent with the required calculation. The denominators for cost and schedule are swapped. Correct work: CPI=144/160=0.90 below one; SPI=144/120=1.20 above one, so cost is unfavorable while schedule value is ahead.
Question 428
The project team has not approved a broad project-plan change. Available evidence indicates: A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining.
- Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
- Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances.
- Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship.
Explanation
Correct Answer
B:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. Confirm afterward that: CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.
Incorrect Answers
A:Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
C:Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances. A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget.
D:Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
Question 429
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
- The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days.
- CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.
- The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario.
Explanation
Correct Answer
C:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. The approved implementation step was: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
Incorrect Answers
A:This option addresses a different CAPM project management topic (Predictive process groups and transitions) rather than the documented CPI and SPI index interpretation decision.
B:This option addresses a different CAPM project management topic (Cost variance EV versus AC) rather than the documented CPI and SPI index interpretation decision.
D:The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario. A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget.
Question 430
For an original CAPM project delivery study scenario, consider: A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue.
- Check: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
- Check: Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
- Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
- Set both performance indices equal to actual spending divided by planned spending without using earned value.
Explanation
Correct Answer
C:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. Acceptance: CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.
D:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. Evidence: Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
Incorrect Answers
A:Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
B:Check: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
E:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.