PMI CAPM Practice Test 42
Question 410
For an original CAPM project delivery study scenario, consider: A rollout has EV=150 and PV=135 cost units on the status date, yet its dashboard marks a fifteen-unit schedule delay without doing the earned-value subtraction. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Subtract actual cost from planned value and label that number the schedule variance in elapsed days.
- Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
- Check: Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
- Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms.
- Check: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
Explanation
Correct Answer
D:Earned-value schedule variance compares work value accomplished to value planned by the reporting date; it is not a direct measure of calendar days. Evidence: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
E:Earned-value schedule variance compares work value accomplished to value planned by the reporting date; it is not a direct measure of calendar days. Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
Incorrect Answers
A:Earned-value schedule variance compares work value accomplished to value planned by the reporting date; it is not a direct measure of calendar days.
B:This option addresses a different CAPM project management topic (CPI and SPI index interpretation) rather than the documented Schedule variance EV versus PV decision.
C:This option addresses a different CAPM project management topic (Total float and schedule compression) rather than the documented Schedule variance EV versus PV decision.
Question 411
A CAPM project team analyst is reviewing this delivery scenario: A procurement project has EV=120 and AC=150 cost units at status, but finance describes the work as thirty units under budget because planned value was higher. An unsafe shortcut would be: Treat every positive planned value as proof actual cost is within the approved budget regardless of what has been spent. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
- Identify the organization's functional, matrix or projectized decision rights and negotiate resource commitments through the recognized management structure.
- Treat every positive planned value as proof actual cost is within the approved budget regardless of what has been spent.
- Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
Explanation
Correct Answer
A:This targeted action addresses the observed delivery, governance or stakeholder-decision gap without discarding necessary controls. Applied case: A procurement project has EV=120 and AC=150 cost units at status, but finance describes the work as thirty units under budget because planned value was higher.
Incorrect Answers
B:Identify the organization's functional, matrix or projectized decision rights and negotiate resource commitments through the recognized management structure. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
C:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
D:Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
Question 412
CAPM predictive scheduling and earned-value calculation. A procurement project has EV=120 and AC=150 cost units at status, but finance describes the work as thirty units under budget because planned value was higher. What is the earned-value cost variance CV for work performed? Select ONE best answer.
- CV = +270 units
- CV = +30 units
- CV = 0 units
- CV = -30 units
Explanation
Correct Answer
D:CV = -30 units This is the correct result. CV=EV-AC=120-150=-30 cost units, indicating unfavorable cost performance.
Incorrect Answers
A:Adding earned and actual values cannot yield cost variance.
B:CV = +30 units This result is inconsistent with the required calculation. Using AC-EV incorrectly reverses the cost-variance sign. Correct work: CV=EV-AC=120-150=-30 cost units, indicating unfavorable cost performance.
C:CV = 0 units This result is inconsistent with the required calculation. EV and AC differ by 30 units. Correct work: CV=EV-AC=120-150=-30 cost units, indicating unfavorable cost performance.
Question 413
The project team has not approved a broad project-plan change. Available evidence indicates: A procurement project has EV=120 and AC=150 cost units at status, but finance describes the work as thirty units under budget because planned value was higher. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control.
- Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
- Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
- Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions.
Explanation
Correct Answer
B:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
Incorrect Answers
A:Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
C:Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
D:Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
Question 414
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A procurement project has EV=120 and AC=150 cost units at status, but finance describes the work as thirty units under budget because planned value was higher. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario.
- The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days.
- CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.
- Everyone executes one approved baseline set and reports performance against the same current definitions.
Explanation
Correct Answer
B:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
Incorrect Answers
A:The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
C:CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
D:This option addresses a different CAPM project management topic (Integrated baseline and change control) rather than the documented Cost variance EV versus AC decision.
Question 415
An implementation sign-off request identifies the following problem: A procurement project has EV=120 and AC=150 cost units at status, but finance describes the work as thirty units under budget because planned value was higher. Which paired project management action and verification should close the review? Select ONE best answer.
- Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms. Verify: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
- Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Verify: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
- Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue. Verify: Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining.
- Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. Verify: Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
Explanation
Correct Answer
D:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
Incorrect Answers
A:This option addresses a different CAPM project management topic (Schedule variance EV versus PV) rather than the documented Cost variance EV versus AC decision.
B:Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
C:Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
Question 416
A CAPM project team analyst is reviewing this delivery scenario: A refurbishment reports EV=210 and AC=195 cost units, while the manager describes a fifteen-unit overrun despite delivering more value than was spent. An unsafe shortcut would be: Treat every positive planned value as proof actual cost is within the approved budget regardless of what has been spent. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Treat every positive planned value as proof actual cost is within the approved budget regardless of what has been spent.
- Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
- Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
- Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule.
Explanation
Correct Answer
C:This targeted action addresses the observed delivery, governance or stakeholder-decision gap without discarding necessary controls. Applied case: A refurbishment reports EV=210 and AC=195 cost units, while the manager describes a fifteen-unit overrun despite delivering more value than was spent.
Incorrect Answers
A:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
B:Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
D:This option addresses a different CAPM project management topic (Precedence dependencies and network sequencing) rather than the documented Cost variance EV versus AC decision.
Question 417
CAPM predictive scheduling and earned-value calculation. A refurbishment reports EV=210 and AC=195 cost units, while the manager describes a fifteen-unit overrun despite delivering more value than was spent. What is the earned-value cost variance CV? Select ONE best answer.
- CV = -15 units
- CV = +405 units
- CV = 0 units
- CV = +15 units
Explanation
Correct Answer
D:CV = +15 units This is the correct result. CV=EV-AC=210-195=+15 cost units, indicating favorable cost performance.
Incorrect Answers
A:CV = -15 units This result is inconsistent with the required calculation. Using AC-EV reverses the interpretation. Correct work: CV=EV-AC=210-195=+15 cost units, indicating favorable cost performance.
B:CV = +405 units This result is inconsistent with the required calculation. Adding amounts cannot measure variance. Correct work: CV=EV-AC=210-195=+15 cost units, indicating favorable cost performance.
C:CV = 0 units This result is inconsistent with the required calculation. Actual cost is not equal to earned value. Correct work: CV=EV-AC=210-195=+15 cost units, indicating favorable cost performance.
Question 418
The project team has not approved a broad project-plan change. Available evidence indicates: A refurbishment reports EV=210 and AC=195 cost units, while the manager describes a fifteen-unit overrun despite delivering more value than was spent. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
- Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
- Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
- Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions.
Explanation
Correct Answer
C:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. This check evaluates the actual project, quality or delivery decision before a risky project-wide change.
Incorrect Answers
A:Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
B:Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
D:Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions. A refurbishment reports EV=210 and AC=195 cost units, while the manager describes a fifteen-unit overrun despite delivering more value than was spent.
Question 419
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A refurbishment reports EV=210 and AC=195 cost units, while the manager describes a fifteen-unit overrun despite delivering more value than was spent. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.
- The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days.
- The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.
- The stated earliest finish equals the longest valid path total and the team knows which branch controls end-to-end duration.
Explanation
Correct Answer
B:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. The approved implementation step was: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
Incorrect Answers
A:Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
C:The project can trace each scheduled activity to an accountable scope package and verify the package's completed output. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
D:This option addresses a different CAPM project management topic (Critical path duration arithmetic) rather than the documented Cost variance EV versus AC decision.
Question 420
For an original CAPM project delivery study scenario, consider: A refurbishment reports EV=210 and AC=195 cost units, while the manager describes a fifteen-unit overrun despite delivering more value than was spent. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Check: Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control.
- Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
- Treat every positive planned value as proof actual cost is within the approved budget regardless of what has been spent.
- Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
- Check: Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
Explanation
Correct Answer
B:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. Evidence: Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
E:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. Required intervention: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
Incorrect Answers
A:Check: Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
C:Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
D:Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.