PMI CAPM Practice Test 40
Question 390
For an original CAPM project delivery study scenario, consider: For a release, path A=5 days then B=8 days and path C=6 days then D=4 days converge on final test E=2 days, but the report uses the shorter branch for the finish date. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Check: Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
- Change: Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.
- Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms.
- Add every parallel branch duration together or select the shortest path as the guaranteed completion date.
- Check: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
Explanation
Correct Answer
A:The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
B:The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. Evidence: Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
Incorrect Answers
C:Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.
D:The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.
E:Check: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.
Question 391
A CAPM project team analyst is reviewing this delivery scenario: A network has a critical testing path of 18 days and a parallel design-review path of 14 days, but the manager calls the shorter path critical and authorizes expensive acceleration there. An unsafe shortcut would be: Spend the compression budget on the easiest noncritical activity and guarantee the whole project's end date will shorten. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
- Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified.
- Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls.
- Spend the compression budget on the easiest noncritical activity and guarantee the whole project's end date will shorten.
Explanation
Correct Answer
B:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Incorrect Answers
A:Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
C:This option addresses a different CAPM project management topic (Quality management plan and control) rather than the documented Total float and schedule compression decision.
D:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Question 392
CAPM predictive scheduling and earned-value calculation. A network has a critical testing path of 18 days and a parallel design-review path of 14 days, but the manager calls the shorter path critical and authorizes expensive acceleration there. How much total float does the noncritical 14-day path have before the 18-day finish is affected, assuming no other constraints? Select ONE best answer.
- 18 days of float
- 0 days of float
- 14 days of float
- 4 days of float
Explanation
Correct Answer
D:The shorter parallel path has 18-14=4 days of total float relative to the controlling 18-day path.
Incorrect Answers
A:The critical-path duration is the finish date, not slack for this branch.
B:0 days of float This result is inconsistent with the required calculation. Zero is characteristic of the stated controlling 18-day path, not the shorter parallel path. Correct work: The shorter parallel path has 18-14=4 days of total float relative to the controlling 18-day path.
C:14 days of float This result is inconsistent with the required calculation. The duration of a path is not the float available. Correct work: The shorter parallel path has 18-14=4 days of total float relative to the controlling 18-day path.
Question 393
The project team has not approved a broad project-plan change. Available evidence indicates: A network has a critical testing path of 18 days and a parallel design-review path of 14 days, but the manager calls the shorter path critical and authorizes expensive acceleration there. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
- Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
- Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
- Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship.
Explanation
Correct Answer
A:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion. Confirm afterward that: Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
Incorrect Answers
B:Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
C:Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
D:Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Question 394
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A network has a critical testing path of 18 days and a parallel design-review path of 14 days, but the manager calls the shorter path critical and authorizes expensive acceleration there. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
- The stated earliest finish equals the longest valid path total and the team knows which branch controls end-to-end duration.
- The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip.
- The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank.
Explanation
Correct Answer
A:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Incorrect Answers
B:The stated earliest finish equals the longest valid path total and the team knows which branch controls end-to-end duration. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
C:The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
D:The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Question 395
An implementation sign-off request identifies the following problem: A network has a critical testing path of 18 days and a parallel design-review path of 14 days, but the manager calls the shorter path critical and authorizes expensive acceleration there. Which paired project management action and verification should close the review? Select ONE best answer.
- Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately. Verify: Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
- Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Verify: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
- Change: Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified. Verify: Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
- Change: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports. Verify: Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion.
Explanation
Correct Answer
C:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Incorrect Answers
A:Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
B:Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
D:This option addresses a different CAPM project management topic (Predictive control artifacts and reporting) rather than the documented Total float and schedule compression decision.
Question 396
A CAPM project team analyst is reviewing this delivery scenario: A delayed noncritical supply task has three days of available float while executives demand immediate cost-intensive crashing without checking if the finish milestone is threatened. An unsafe shortcut would be: Spend the compression budget on the easiest noncritical activity and guarantee the whole project's end date will shorten. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.
- Spend the compression budget on the easiest noncritical activity and guarantee the whole project's end date will shorten.
- Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified.
- Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue.
Explanation
Correct Answer
C:This targeted action addresses the observed delivery, governance or stakeholder-decision gap without discarding necessary controls. Applied case: A delayed noncritical supply task has three days of available float while executives demand immediate cost-intensive crashing without checking if the finish milestone is threatened.
Incorrect Answers
A:Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
B:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
D:Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Question 397
CAPM predictive scheduling and earned-value calculation. A delayed noncritical supply task has three days of available float while executives demand immediate cost-intensive crashing without checking if the finish milestone is threatened. How much stated total float can the supply task consume before it threatens the current finish? Select ONE best answer.
- 3 days of float
- 0 days of float
- 18 days of float
- 6 days of float
Explanation
Correct Answer
A:The case expressly says three days of available float; the task can slip by at most that amount absent other constraints.
Incorrect Answers
B:0 days of float This result is inconsistent with the required calculation. The task is described as noncritical and has explicitly stated available float. Correct work: The case expressly says three days of available float; the task can slip by at most that amount absent other constraints.
C:The critical-path duration from another case is not this activity’s slack.
D:6 days of float This result is inconsistent with the required calculation. This doubles the documented float without a network calculation. Correct work: The case expressly says three days of available float; the task can slip by at most that amount absent other constraints.
Question 398
The project team has not approved a broad project-plan change. Available evidence indicates: A delayed noncritical supply task has three days of available float while executives demand immediate cost-intensive crashing without checking if the finish milestone is threatened. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining.
- Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
- Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
- Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
Explanation
Correct Answer
B:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion. This check evaluates the actual project, quality or delivery decision before a risky project-wide change.
Incorrect Answers
A:Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
C:Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
D:Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Question 399
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A delayed noncritical supply task has three days of available float while executives demand immediate cost-intensive crashing without checking if the finish milestone is threatened. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip.
- The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days.
- Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
- Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
Explanation
Correct Answer
D:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion. The approved implementation step was: Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified.
Incorrect Answers
A:The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip. A delayed noncritical supply task has three days of available float while executives demand immediate cost-intensive crashing without checking if the finish milestone is threatened.
B:This option addresses a different CAPM project management topic (Cost variance EV versus AC) rather than the documented Total float and schedule compression decision.
C:Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
Question 400
For an original CAPM project delivery study scenario, consider: A delayed noncritical supply task has three days of available float while executives demand immediate cost-intensive crashing without checking if the finish milestone is threatened. Select THREE compatible elements: a proper correction, a targeted diagnostic and an acceptance result.
- Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
- Check: Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
- Change: Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified.
- Result: The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank.
- Result: Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
- Check: Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
Explanation
Correct Answer
B:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion. Acceptance: Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
C:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion. Evidence: Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
E:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion. Required intervention: Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified.
Incorrect Answers
A:Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
D:Result: The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
F:Check: Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence. Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.