cert
cert-1
cert-2

Pass PMI CAPM Exam in First Attempt Guaranteed!

Get 100% Latest Exam Questions, Accurate & Verified Answers to Pass the Actual Exam!
30 Days Free Updates, Instant Download!

cert-5
cert-6
CAPM Exam - Verified By Experts
CAPM Premium Bundle
$29.98

CAPM Premium Bundle

$79.99
$109.97
  • Premium File 688 Questions & Answers. Last update: Nov 21, 2026
  • Training Course 123 Video Lectures
  • Study Guide 719 Pages
 
$109.97
$79.99
accept 19 downloads in last 7 days
block-screenshots
Purchase PMI CAPM Exam Training Products Individually
PMI CAPM Premium File
Premium File 688 Q&A
$76.99$69.99
PMI CAPM Video Training Course
Training Course 123 Lectures
$21.99 $19.99
PMI CAPM PDF Study Guide
Study Guide 719 Pages
$21.99 $19.99
PMI CAPM Practice Test 39

Question 380

For an original CAPM project delivery study scenario, consider: A product team schedules final validation to start after prototyping begins, but ignores the approved rule that testing must wait for the complete prototype handover. Select TWO complementary steps: the targeted correction and its strongest prechange validation.

  1. Insert arbitrary fixed dates and remove dependencies so all activities appear to finish before the sponsor's target.
  2. Change: Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule.
  3. Change: Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls.
  4. Check: Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
  5. Check: Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship.

Explanation

Correct Answer

B:

Sequence logic represents technical or contractual dependencies; calendar dates cannot replace a correct dependency network. Acceptance: The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip.

E:

Sequence logic represents technical or contractual dependencies; calendar dates cannot replace a correct dependency network. Required intervention: Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule.

Incorrect Answers

A:

Sequence logic represents technical or contractual dependencies; calendar dates cannot replace a correct dependency network.

C:

Change: Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls. Sequence logic represents technical or contractual dependencies; calendar dates cannot replace a correct dependency network.

D:

Check: Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks. Sequence logic represents technical or contractual dependencies; calendar dates cannot replace a correct dependency network.

Question 381

A CAPM project team analyst is reviewing this delivery scenario: In a renovation network, activities A=4 days then C=6 days run in parallel with activity B=7 days then D=2 days, followed by shared commissioning E=3 days; the coordinator wrongly adds both branches as if serial. An unsafe shortcut would be: Add every parallel branch duration together or select the shortest path as the guaranteed completion date. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.

  1. Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
  2. Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.
  3. Add every parallel branch duration together or select the shortest path as the guaranteed completion date.
  4. Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.

Explanation

Correct Answer

B:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

Incorrect Answers

A:

Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

C:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

D:

This option addresses a different CAPM project management topic (Work packages versus activities) rather than the documented Critical path duration arithmetic decision.

Question 382

CAPM predictive scheduling and earned-value calculation. In a renovation network, activities A=4 days then C=6 days run in parallel with activity B=7 days then D=2 days, followed by shared commissioning E=3 days; the coordinator wrongly adds both branches as if serial. Which total duration sets the earliest project finish for the two parallel branches and shared commissioning? Select ONE best answer.

  1. 10 days
  2. 13 days
  3. 12 days
  4. 22 days

Explanation

Correct Answer

B:

13 days This is the correct result. Path A-C-E is 4+6+3=13 days; path B-D-E is 7+2+3=12 days. The longer path controls at 13 days.

Incorrect Answers

A:

10 days This result is inconsistent with the required calculation. This omits the shared three-day commissioning activity. Correct work: Path A-C-E is 4+6+3=13 days; path B-D-E is 7+2+3=12 days. The longer path controls at 13 days.

C:

The 7+2+3 day branch is shorter and cannot control the finish.

D:

22 days This result is inconsistent with the required calculation. Adding both parallel branches double counts time that overlaps. Correct work: Path A-C-E is 4+6+3=13 days; path B-D-E is 7+2+3=12 days. The longer path controls at 13 days.

Question 383

The project team has not approved a broad project-plan change. Available evidence indicates: In a renovation network, activities A=4 days then C=6 days run in parallel with activity B=7 days then D=2 days, followed by shared commissioning E=3 days; the coordinator wrongly adds both branches as if serial. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.

  1. Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining.
  2. Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
  3. Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
  4. Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.

Explanation

Correct Answer

B:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. This check evaluates the actual project, quality or delivery decision before a risky project-wide change.

Incorrect Answers

A:

This option addresses a different CAPM project management topic (Estimate at completion forecasting) rather than the documented Critical path duration arithmetic decision.

C:

Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

D:

This option addresses a different CAPM project management topic (CPI and SPI index interpretation) rather than the documented Critical path duration arithmetic decision.

Question 384

A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: In a renovation network, activities A=4 days then C=6 days run in parallel with activity B=7 days then D=2 days, followed by shared commissioning E=3 days; the coordinator wrongly adds both branches as if serial. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.

  1. Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
  2. The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank.
  3. The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days.
  4. The stated earliest finish equals the longest valid path total and the team knows which branch controls end-to-end duration.

Explanation

Correct Answer

D:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

Incorrect Answers

A:

This option addresses a different CAPM project management topic (Total float and schedule compression) rather than the documented Critical path duration arithmetic decision.

B:

The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

C:

The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

Question 385

An implementation sign-off request identifies the following problem: In a renovation network, activities A=4 days then C=6 days run in parallel with activity B=7 days then D=2 days, followed by shared commissioning E=3 days; the coordinator wrongly adds both branches as if serial. Which paired project management action and verification should close the review? Select ONE best answer.

  1. Change: Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence. Verify: Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
  2. Change: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports. Verify: Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion.
  3. Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms. Verify: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
  4. Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. Verify: Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.

Explanation

Correct Answer

A:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

Incorrect Answers

B:

This option addresses a different CAPM project management topic (Predictive control artifacts and reporting) rather than the documented Critical path duration arithmetic decision.

C:

Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms.

D:

Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

Question 386

A CAPM project team analyst is reviewing this delivery scenario: For a release, path A=5 days then B=8 days and path C=6 days then D=4 days converge on final test E=2 days, but the report uses the shorter branch for the finish date. An unsafe shortcut would be: Add every parallel branch duration together or select the shortest path as the guaranteed completion date. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.

  1. Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
  2. Add every parallel branch duration together or select the shortest path as the guaranteed completion date.
  3. Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
  4. Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.

Explanation

Correct Answer

D:

Validate the premise using: Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.

Incorrect Answers

A:

Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

B:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. Use this instead: Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.

C:

Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

Question 387

CAPM predictive scheduling and earned-value calculation. For a release, path A=5 days then B=8 days and path C=6 days then D=4 days converge on final test E=2 days, but the report uses the shorter branch for the finish date. What is the earliest completion duration from the start of the two parallel paths through final test? Select ONE best answer.

  1. 12 days
  2. 15 days
  3. 25 days
  4. 13 days

Explanation

Correct Answer

B:

15 days This is the correct result. Path A-B-E is 5+8+2=15 days; path C-D-E is 6+4+2=12 days. The 15-day branch controls.

Incorrect Answers

A:

The other branch is 6+4+2=12 days and is not the controlling path.

C:

This adds parallel branches as if they were consecutive.

D:

13 days This result is inconsistent with the required calculation. The 5+8 activity chain excludes the common two-day final test. Correct work: Path A-B-E is 5+8+2=15 days; path C-D-E is 6+4+2=12 days. The 15-day branch controls.

Question 388

The project team has not approved a broad project-plan change. Available evidence indicates: For a release, path A=5 days then B=8 days and path C=6 days then D=4 days converge on final test E=2 days, but the report uses the shorter branch for the finish date. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.

  1. Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
  2. Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
  3. Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.
  4. Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.

Explanation

Correct Answer

B:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. If confirmed, the proportionate intervention is: Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.

Incorrect Answers

A:

Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

C:

Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

D:

Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

Question 389

A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: For a release, path A=5 days then B=8 days and path C=6 days then D=4 days converge on final test E=2 days, but the report uses the shorter branch for the finish date. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.

  1. The stated earliest finish equals the longest valid path total and the team knows which branch controls end-to-end duration.
  2. The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days.
  3. The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison.
  4. The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank.

Explanation

Correct Answer

A:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. The approved implementation step was: Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.

Incorrect Answers

B:

The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days. For a release, path A=5 days then B=8 days and path C=6 days then D=4 days converge on final test E=2 days, but the report uses the shorter branch for the finish date.

C:

The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

D:

The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank. For a release, path A=5 days then B=8 days and path C=6 days then D=4 days converge on final test E=2 days, but the report uses the shorter branch for the finish date.

Question 390

For an original CAPM project delivery study scenario, consider: For a release, path A=5 days then B=8 days and path C=6 days then D=4 days converge on final test E=2 days, but the report uses the shorter branch for the finish date. Select TWO complementary steps: the targeted correction and its strongest prechange validation.

  1. Check: Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
  2. Change: Determine the longest dependent path through the activity network and calculate finish time after respecting parallel branches and convergence.
  3. Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms.
  4. Add every parallel branch duration together or select the shortest path as the guaranteed completion date.
  5. Check: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.

Explanation

Correct Answer

A:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.

B:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. Evidence: Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.

Incorrect Answers

C:

Change: Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

D:

The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

E:

Check: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests