cert
cert-1
cert-2

Pass PMI CAPM Exam in First Attempt Guaranteed!

Get 100% Latest Exam Questions, Accurate & Verified Answers to Pass the Actual Exam!
30 Days Free Updates, Instant Download!

cert-5
cert-6
CAPM Exam - Verified By Experts
CAPM Premium Bundle
$29.98

CAPM Premium Bundle

$79.99
$109.97
  • Premium File 688 Questions & Answers. Last update: Nov 21, 2026
  • Training Course 123 Video Lectures
  • Study Guide 719 Pages
 
$109.97
$79.99
accept 19 downloads in last 7 days
block-screenshots
Purchase PMI CAPM Exam Training Products Individually
PMI CAPM Premium File
Premium File 688 Q&A
$76.99$69.99
PMI CAPM Video Training Course
Training Course 123 Lectures
$21.99 $19.99
PMI CAPM PDF Study Guide
Study Guide 719 Pages
$21.99 $19.99
PMI CAPM Practice Test 37

Question 360

For an original CAPM project delivery study scenario, consider: A building refurbishment estimate includes a top-level 'renovate building' line but omits electrical testing and handover packages needed to estimate scope. Select TWO complementary steps: the targeted correction and its strongest prechange validation.

  1. Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
  2. Check: Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions.
  3. Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
  4. Organize the WBS solely as a list of employees and meeting dates and assume all contracted outputs are represented.
  5. Check: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.

Explanation

Correct Answer

A:

Acceptance: Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.

E:

Required intervention: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.

Incorrect Answers

B:

Check: Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.

C:

Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.

D:

The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.

Question 361

A CAPM project team analyst is reviewing this delivery scenario: A software team treats a task called 'email the tester' as the entire integration work package without any defined acceptance output. An unsafe shortcut would be: Treat individual calendar reminders as independent product deliverables and omit work-package acceptance criteria. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.

  1. Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified.
  2. Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
  3. Treat individual calendar reminders as independent product deliverables and omit work-package acceptance criteria.
  4. Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.

Explanation

Correct Answer

B:

A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Incorrect Answers

A:

Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

C:

A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

D:

Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Question 362

A project delivery review finds: A software team treats a task called 'email the tester' as the entire integration work package without any defined acceptance output. The team proposes: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. Which project management principle most strongly supports the proposed response? Select ONE best answer.

  1. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.
  2. Predictive planning is effective when major outcomes and dependencies can be defined before substantial execution and changes need visible authorization.
  3. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.
  4. Quality planning specifies how processes and deliverables meet requirements; control measurements demonstrate observed conformance to those requirements.

Explanation

Correct Answer

C:

Demonstrable success requires: The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.

Incorrect Answers

A:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

B:

Predictive planning is effective when major outcomes and dependencies can be defined before substantial execution and changes need visible authorization. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

D:

This option addresses a different CAPM project management topic (Quality management plan and control) rather than the documented Work packages versus activities decision.

Question 363

The project team has not approved a broad project-plan change. Available evidence indicates: A software team treats a task called 'email the tester' as the entire integration work package without any defined acceptance output. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.

  1. Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
  2. Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship.
  3. Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
  4. Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.

Explanation

Correct Answer

A:

Confirm afterward that: The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.

Incorrect Answers

B:

Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

C:

Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

D:

Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Question 364

A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A software team treats a task called 'email the tester' as the entire integration work package without any defined acceptance output. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.

  1. Compliance deliverables meet predefined criteria and unavoidable changes are assessed instead of introducing untraceable requirements drift.
  2. The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.
  3. CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.
  4. The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison.

Explanation

Correct Answer

B:

A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Incorrect Answers

A:

Compliance deliverables meet predefined criteria and unavoidable changes are assessed instead of introducing untraceable requirements drift. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

C:

CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

D:

The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Question 365

An implementation sign-off request identifies the following problem: A software team treats a task called 'email the tester' as the entire integration work package without any defined acceptance output. Which paired project management action and verification should close the review? Select ONE best answer.

  1. Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. Verify: Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
  2. Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue. Verify: Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining.
  3. Change: Use a predictive approach with planned phase sequencing, approved requirements and formal control of changes where requirements and regulatory acceptance are stable. Verify: Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control.
  4. Change: Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule. Verify: Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship.

Explanation

Correct Answer

A:

The change is successful only when: The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.

Incorrect Answers

B:

Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue.

C:

Change: Use a predictive approach with planned phase sequencing, approved requirements and formal control of changes where requirements and regulatory acceptance are stable.

D:

Change: Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Question 366

A CAPM project team analyst is reviewing this delivery scenario: An equipment installation project has a signed WBS work package for test certification but schedules its setup, execution and report tasks as one undifferentiated milestone. An unsafe shortcut would be: Treat individual calendar reminders as independent product deliverables and omit work-package acceptance criteria. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.

  1. Identify the organization's functional, matrix or projectized decision rights and negotiate resource commitments through the recognized management structure.
  2. Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
  3. Treat individual calendar reminders as independent product deliverables and omit work-package acceptance criteria.
  4. Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.

Explanation

Correct Answer

B:

A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Incorrect Answers

A:

Identify the organization's functional, matrix or projectized decision rights and negotiate resource commitments through the recognized management structure. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

C:

A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

D:

Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Question 367

A project delivery review finds: An equipment installation project has a signed WBS work package for test certification but schedules its setup, execution and report tasks as one undifferentiated milestone. The team proposes: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. Which project management principle most strongly supports the proposed response? Select ONE best answer.

  1. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
  2. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
  3. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.
  4. Predictive planning is effective when major outcomes and dependencies can be defined before substantial execution and changes need visible authorization.

Explanation

Correct Answer

C:

Demonstrable success requires: The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.

Incorrect Answers

A:

Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

B:

Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

D:

Predictive planning is effective when major outcomes and dependencies can be defined before substantial execution and changes need visible authorization. An equipment installation project has a signed WBS work package for test certification but schedules its setup, execution and report tasks as one undifferentiated milestone.

Question 368

The project team has not approved a broad project-plan change. Available evidence indicates: An equipment installation project has a signed WBS work package for test certification but schedules its setup, execution and report tasks as one undifferentiated milestone. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.

  1. Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
  2. Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
  3. Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
  4. Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.

Explanation

Correct Answer

C:

Confirm afterward that: The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.

Incorrect Answers

A:

This option addresses a different CAPM project management topic (WBS deliverable decomposition) rather than the documented Work packages versus activities decision.

B:

Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

D:

This option addresses a different CAPM project management topic (Critical path duration arithmetic) rather than the documented Work packages versus activities decision.

Question 369

A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: An equipment installation project has a signed WBS work package for test certification but schedules its setup, execution and report tasks as one undifferentiated milestone. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.

  1. Reports and source controls reconcile at the reporting date, exposing variance, ownership and authorized changes without contradictory status.
  2. The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison.
  3. Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
  4. The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.

Explanation

Correct Answer

D:

A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Incorrect Answers

A:

Reports and source controls reconcile at the reporting date, exposing variance, ownership and authorized changes without contradictory status. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

B:

The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison. An equipment installation project has a signed WBS work package for test certification but schedules its setup, execution and report tasks as one undifferentiated milestone.

C:

Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Question 370

For an original CAPM project delivery study scenario, consider: An equipment installation project has a signed WBS work package for test certification but schedules its setup, execution and report tasks as one undifferentiated milestone. Select TWO complementary steps: the targeted correction and its strongest prechange validation.

  1. Change: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.
  2. Treat individual calendar reminders as independent product deliverables and omit work-package acceptance criteria.
  3. Check: Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
  4. Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
  5. Check: Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion.

Explanation

Correct Answer

C:

Acceptance: The project can trace each scheduled activity to an accountable scope package and verify the package's completed output.

D:

Acceptance: The project can trace each scheduled activity to an accountable scope package and verify the package's completed output. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

Incorrect Answers

A:

Change: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.

B:

A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable. Use this instead: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.

E:

Check: Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion. A work package is a WBS control unit for estimating and responsibility; its constituent activities consume time to produce its deliverable.