PMI CAPM Practice Test 35
Question 340
For an original CAPM project delivery study scenario, consider: A strong-matrix construction program reserves a specialist for delivery, but the coordinator assumes every functional supervisor automatically relinquishes all personnel authority. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Promise dedicated resources across all departments without reviewing functional commitments or escalation rights.
- Change: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports.
- Change: Identify the organization's functional, matrix or projectized decision rights and negotiate resource commitments through the recognized management structure.
- Check: Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions.
- Check: Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
Explanation
Correct Answer
C:In matrix environments authority is shared to varying degrees; project plans must account for functional ownership and explicit priority agreements. Acceptance: The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank.
D:In matrix environments authority is shared to varying degrees; project plans must account for functional ownership and explicit priority agreements. Required intervention: Identify the organization's functional, matrix or projectized decision rights and negotiate resource commitments through the recognized management structure.
Incorrect Answers
A:In matrix environments authority is shared to varying degrees; project plans must account for functional ownership and explicit priority agreements.
B:Change: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports. A strong-matrix construction program reserves a specialist for delivery, but the coordinator assumes every functional supervisor automatically relinquishes all personnel authority.
E:Check: Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish. In matrix environments authority is shared to varying degrees; project plans must account for functional ownership and explicit priority agreements.
Question 341
A CAPM project team analyst is reviewing this delivery scenario: A project team starts manufacturing before defining the baseline and approval authority, believing formal initiation follows testing. An unsafe shortcut would be: Treat the five process groups as rigid technical work stages with no monitoring until all execution is finished. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.
- Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms.
- Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
- Treat the five process groups as rigid technical work stages with no monitoring until all execution is finished.
Explanation
Correct Answer
C:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Incorrect Answers
A:Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
B:Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 342
A project delivery review finds: A project team starts manufacturing before defining the baseline and approval authority, believing formal initiation follows testing. The team proposes: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Which project management principle most strongly supports the proposed response? Select ONE best answer.
- Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
- Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion.
- The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
- In matrix environments authority is shared to varying degrees; project plans must account for functional ownership and explicit priority agreements.
Explanation
Correct Answer
A:Demonstrable success requires: Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure. This principle explains the proposed project response, which is: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
Incorrect Answers
B:Total float is schedule flexibility before project finish or successor constraints are affected; compressing work off the critical path may not improve completion. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
C:The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:In matrix environments authority is shared to varying degrees; project plans must account for functional ownership and explicit priority agreements. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 343
The project team has not approved a broad project-plan change. Available evidence indicates: A project team starts manufacturing before defining the baseline and approval authority, believing formal initiation follows testing. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances.
- Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
- Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
- Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
Explanation
Correct Answer
B:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases. Confirm afterward that: Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
Incorrect Answers
A:Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
C:Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 344
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A project team starts manufacturing before defining the baseline and approval authority, believing formal initiation follows testing. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days.
- Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
- Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
- Everyone executes one approved baseline set and reports performance against the same current definitions.
Explanation
Correct Answer
B:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Incorrect Answers
A:The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
C:Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:Everyone executes one approved baseline set and reports performance against the same current definitions. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 345
An implementation sign-off request identifies the following problem: A project team starts manufacturing before defining the baseline and approval authority, believing formal initiation follows testing. Which paired project management action and verification should close the review? Select ONE best answer.
- Change: Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule. Verify: Review the activity list, predecessor links, dependency type, lag assumptions and consequences of each violated relationship.
- Change: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change. Verify: Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.
- Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Verify: Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
- Change: Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls. Verify: Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances.
Explanation
Correct Answer
C:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Incorrect Answers
A:Change: Model real task precedence and suitable finish-to-start or other valid relationships with explicit lags before calculating the project network schedule.
B:Change: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.
D:Change: Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 346
A CAPM project team analyst is reviewing this delivery scenario: An infrastructure team completes installation but continues spending because it has confused routine monitoring with final acceptance and closing. An unsafe shortcut would be: Treat the five process groups as rigid technical work stages with no monitoring until all execution is finished. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
- Treat the five process groups as rigid technical work stages with no monitoring until all execution is finished.
- Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
- Use a predictive approach with planned phase sequencing, approved requirements and formal control of changes where requirements and regulatory acceptance are stable.
Explanation
Correct Answer
C:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Incorrect Answers
A:Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
B:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:Use a predictive approach with planned phase sequencing, approved requirements and formal control of changes where requirements and regulatory acceptance are stable. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 347
A project delivery review finds: An infrastructure team completes installation but continues spending because it has confused routine monitoring with final acceptance and closing. The team proposes: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Which project management principle most strongly supports the proposed response? Select ONE best answer.
- The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.
- Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs.
- Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
- Quality planning specifies how processes and deliverables meet requirements; control measurements demonstrate observed conformance to those requirements.
Explanation
Correct Answer
C:Demonstrable success requires: Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
Incorrect Answers
A:The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
B:Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:Quality planning specifies how processes and deliverables meet requirements; control measurements demonstrate observed conformance to those requirements. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 348
The project team has not approved a broad project-plan change. Available evidence indicates: An infrastructure team completes installation but continues spending because it has confused routine monitoring with final acceptance and closing. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
- Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
- Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.
- Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish.
Explanation
Correct Answer
A:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases. This check evaluates the actual project, quality or delivery decision before a risky project-wide change.
Incorrect Answers
B:Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
C:Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:Calculate each candidate start-to-finish path, compare durations and verify the converging successor begins only after all required predecessors finish. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 349
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: An infrastructure team completes installation but continues spending because it has confused routine monitoring with final acceptance and closing. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario.
- The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison.
- Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
- The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank.
Explanation
Correct Answer
C:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases. The approved implementation step was: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
Incorrect Answers
A:The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
B:The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:The specialist receives one feasible coordinated work plan and disputes follow documented authority boundaries rather than informal rank. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
Question 350
For an original CAPM project delivery study scenario, consider: An infrastructure team completes installation but continues spending because it has confused routine monitoring with final acceptance and closing. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Check: Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
- Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
- Treat the five process groups as rigid technical work stages with no monitoring until all execution is finished.
- Check: Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.
- Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
Explanation
Correct Answer
A:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases. Acceptance: Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
B:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases. Evidence: Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
Incorrect Answers
C:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:Check: Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
E:This option addresses a different CAPM project management topic (Work packages versus activities) rather than the documented Predictive process groups and transitions decision.