PMI CAPM Practice Test 36
Question 350
For an original CAPM project delivery study scenario, consider: An infrastructure team completes installation but continues spending because it has confused routine monitoring with final acceptance and closing. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Check: Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
- Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
- Treat the five process groups as rigid technical work stages with no monitoring until all execution is finished.
- Check: Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.
- Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
Explanation
Correct Answer
A:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases. Acceptance: Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
B:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases. Evidence: Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
Incorrect Answers
C:Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
D:Check: Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
E:This option addresses a different CAPM project management topic (Work packages versus activities) rather than the documented Predictive process groups and transitions decision.
Question 351
A CAPM project team analyst is reviewing this delivery scenario: A website plan lists 'Monday morning' and 'urgent' as work breakdown structure branches but never identifies the checkout component as a deliverable. An unsafe shortcut would be: Organize the WBS solely as a list of employees and meeting dates and assume all contracted outputs are represented. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Use a predictive approach with planned phase sequencing, approved requirements and formal control of changes where requirements and regulatory acceptance are stable.
- Organize the WBS solely as a list of employees and meeting dates and assume all contracted outputs are represented.
- Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
- Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
Explanation
Correct Answer
C:The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Incorrect Answers
A:Use a predictive approach with planned phase sequencing, approved requirements and formal control of changes where requirements and regulatory acceptance are stable. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
B:The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
D:Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Question 352
A project delivery review finds: A website plan lists 'Monday morning' and 'urgent' as work breakdown structure branches but never identifies the checkout component as a deliverable. The team proposes: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Which project management principle most strongly supports the proposed response? Select ONE best answer.
- Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
- The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.
- Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs.
- The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Explanation
Correct Answer
D:Demonstrable success requires: Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions. This principle explains the proposed project response, which is: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
Incorrect Answers
A:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
B:The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
C:Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Question 353
The project team has not approved a broad project-plan change. Available evidence indicates: A website plan lists 'Monday morning' and 'urgent' as work breakdown structure branches but never identifies the checkout component as a deliverable. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
- Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
- Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
- Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances.
Explanation
Correct Answer
C:If confirmed, the proportionate intervention is: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
Incorrect Answers
A:Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
B:Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
D:Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Question 354
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A website plan lists 'Monday morning' and 'urgent' as work breakdown structure branches but never identifies the checkout component as a deliverable. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- Reports and source controls reconcile at the reporting date, exposing variance, ownership and authorized changes without contradictory status.
- Everyone executes one approved baseline set and reports performance against the same current definitions.
- Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.
- Product measurements and documented controls meet the agreed standard, and deviations have explicit corrective or acceptance decisions.
Explanation
Correct Answer
C:The approved implementation step was: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
Incorrect Answers
A:This option addresses a different CAPM project management topic (Predictive control artifacts and reporting) rather than the documented WBS deliverable decomposition decision.
B:Everyone executes one approved baseline set and reports performance against the same current definitions. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
D:Product measurements and documented controls meet the agreed standard, and deviations have explicit corrective or acceptance decisions. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Question 355
An implementation sign-off request identifies the following problem: A website plan lists 'Monday morning' and 'urgent' as work breakdown structure branches but never identifies the checkout component as a deliverable. Which paired project management action and verification should close the review? Select ONE best answer.
- Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. Verify: Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
- Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Verify: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
- Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately. Verify: Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
- Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Verify: Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
Explanation
Correct Answer
B:The change is successful only when: Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.
Incorrect Answers
A:Change: Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
C:Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
D:This option addresses a different CAPM project management topic (Predictive process groups and transitions) rather than the documented WBS deliverable decomposition decision.
Question 356
A CAPM project team analyst is reviewing this delivery scenario: A building refurbishment estimate includes a top-level 'renovate building' line but omits electrical testing and handover packages needed to estimate scope. An unsafe shortcut would be: Organize the WBS solely as a list of employees and meeting dates and assume all contracted outputs are represented. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
- Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
- Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue.
- Organize the WBS solely as a list of employees and meeting dates and assume all contracted outputs are represented.
Explanation
Correct Answer
B:The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Incorrect Answers
A:Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
C:Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
D:The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work. Use this instead: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
Question 357
A project delivery review finds: A building refurbishment estimate includes a top-level 'renovate building' line but omits electrical testing and handover packages needed to estimate scope. The team proposes: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Which project management principle most strongly supports the proposed response? Select ONE best answer.
- Earned-value schedule variance compares work value accomplished to value planned by the reporting date; it is not a direct measure of calendar days.
- Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.
- Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs.
- The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Explanation
Correct Answer
D:Demonstrable success requires: Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.
Incorrect Answers
A:Earned-value schedule variance compares work value accomplished to value planned by the reporting date; it is not a direct measure of calendar days. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
B:Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. A building refurbishment estimate includes a top-level 'renovate building' line but omits electrical testing and handover packages needed to estimate scope.
C:Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs. A building refurbishment estimate includes a top-level 'renovate building' line but omits electrical testing and handover packages needed to estimate scope.
Question 358
The project team has not approved a broad project-plan change. Available evidence indicates: A building refurbishment estimate includes a top-level 'renovate building' line but omits electrical testing and handover packages needed to estimate scope. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
- Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
- Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions.
- Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
Explanation
Correct Answer
A:If confirmed, the proportionate intervention is: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
Incorrect Answers
B:Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
C:Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
D:This option addresses a different CAPM project management topic (Total float and schedule compression) rather than the documented WBS deliverable decomposition decision.
Question 359
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A building refurbishment estimate includes a top-level 'renovate building' line but omits electrical testing and handover packages needed to estimate scope. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario.
- Compliance deliverables meet predefined criteria and unavoidable changes are assessed instead of introducing untraceable requirements drift.
- Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.
- The stated earliest finish equals the longest valid path total and the team knows which branch controls end-to-end duration.
Explanation
Correct Answer
C:The approved implementation step was: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
Incorrect Answers
A:The report states the selected EAC method, its inputs and a defensible final-cost forecast for each scenario. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
B:Compliance deliverables meet predefined criteria and unavoidable changes are assessed instead of introducing untraceable requirements drift. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
D:The stated earliest finish equals the longest valid path total and the team knows which branch controls end-to-end duration. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
Question 360
For an original CAPM project delivery study scenario, consider: A building refurbishment estimate includes a top-level 'renovate building' line but omits electrical testing and handover packages needed to estimate scope. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
- Check: Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions.
- Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
- Organize the WBS solely as a list of employees and meeting dates and assume all contracted outputs are represented.
- Check: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
Explanation
Correct Answer
A:Acceptance: Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.
E:Required intervention: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified.
Incorrect Answers
B:Check: Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
C:Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
D:The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.