cert
cert-1
cert-2

Pass PMI CAPM Exam in First Attempt Guaranteed!

Get 100% Latest Exam Questions, Accurate & Verified Answers to Pass the Actual Exam!
30 Days Free Updates, Instant Download!

cert-5
cert-6
CAPM Exam - Verified By Experts
CAPM Premium Bundle
$29.98

CAPM Premium Bundle

$79.99
$109.97
  • Premium File 688 Questions & Answers. Last update: Nov 21, 2026
  • Training Course 123 Video Lectures
  • Study Guide 719 Pages
 
$109.97
$79.99
accept 19 downloads in last 7 days
block-screenshots
Purchase PMI CAPM Exam Training Products Individually
PMI CAPM Premium File
Premium File 688 Q&A
$76.99$69.99
PMI CAPM Video Training Course
Training Course 123 Lectures
$21.99 $19.99
PMI CAPM PDF Study Guide
Study Guide 719 Pages
$21.99 $19.99
PMI CAPM Practice Test 44

Question 430

For an original CAPM project delivery study scenario, consider: A compliance rollout reports EV=144 PV=120 AC=160 cost units, yet leadership assumes ahead-of-schedule must also mean under budget. Select TWO complementary steps: the targeted correction and its strongest prechange validation.

  1. Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue.
  2. Check: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost.
  3. Check: Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
  4. Change: Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
  5. Set both performance indices equal to actual spending divided by planned spending without using earned value.

Explanation

Correct Answer

C:

Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. Acceptance: CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.

D:

Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. Evidence: Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.

Incorrect Answers

A:

Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.

B:

Check: Verify EV and PV at the same status date, the units of value and the reported subtraction rather than using actual cost. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.

E:

Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.

Question 431

A CAPM project team analyst is reviewing this delivery scenario: A bridge engineer updates the cost spreadsheet after an approved design change but leaves the schedule and scope baselines at their former configuration. An unsafe shortcut would be: Revise only the easiest spreadsheet and assume remaining project documents automatically receive identical approved changes. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.

  1. Identify the organization's functional, matrix or projectized decision rights and negotiate resource commitments through the recognized management structure.
  2. Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.
  3. Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately.
  4. Revise only the easiest spreadsheet and assume remaining project documents automatically receive identical approved changes.

Explanation

Correct Answer

B:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Incorrect Answers

A:

This option addresses a different CAPM project management topic (Organizational matrix authority) rather than the documented Integrated baseline and change control decision.

C:

Calculate CPI as EV divided by AC and SPI as EV divided by PV, interpreting efficiency and schedule separately. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

D:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Question 432

A project delivery review finds: A bridge engineer updates the cost spreadsheet after an approved design change but leaves the schedule and scope baselines at their former configuration. The team proposes: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change. Which project management principle most strongly supports the proposed response? Select ONE best answer.

  1. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.
  2. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.
  3. The critical path is the longest-duration path through the directed schedule network and typically determines earliest project completion absent constraints or resource effects.
  4. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.

Explanation

Correct Answer

A:

Demonstrable success requires: Everyone executes one approved baseline set and reports performance against the same current definitions.

Incorrect Answers

B:

Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

C:

This option addresses a different CAPM project management topic (Critical path duration arithmetic) rather than the documented Integrated baseline and change control decision.

D:

The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Question 433

The project team has not approved a broad project-plan change. Available evidence indicates: A bridge engineer updates the cost spreadsheet after an approved design change but leaves the schedule and scope baselines at their former configuration. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.

  1. Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion.
  2. Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
  3. Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
  4. Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.

Explanation

Correct Answer

D:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Incorrect Answers

A:

Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

B:

Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

C:

Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Question 434

A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A bridge engineer updates the cost spreadsheet after an approved design change but leaves the schedule and scope baselines at their former configuration. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.

  1. Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure.
  2. Everyone executes one approved baseline set and reports performance against the same current definitions.
  3. CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.
  4. Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.

Explanation

Correct Answer

B:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Incorrect Answers

A:

Teams apply the appropriate management activity when needed and do not mislabel unapproved execution as initiation or monitoring as closure. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

C:

CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

D:

Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Question 435

An implementation sign-off request identifies the following problem: A bridge engineer updates the cost spreadsheet after an approved design change but leaves the schedule and scope baselines at their former configuration. Which paired project management action and verification should close the review? Select ONE best answer.

  1. Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. Verify: Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
  2. Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Verify: Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
  3. Change: Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified. Verify: Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
  4. Change: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change. Verify: Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.

Explanation

Correct Answer

D:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Incorrect Answers

A:

Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

B:

Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

C:

This option addresses a different CAPM project management topic (Total float and schedule compression) rather than the documented Integrated baseline and change control decision.

Question 436

A CAPM project team analyst is reviewing this delivery scenario: A contractor substitutes a component under a formal request but execution teams never receive the approved drawing version and quality criteria. An unsafe shortcut would be: Revise only the easiest spreadsheet and assume remaining project documents automatically receive identical approved changes. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.

  1. Revise only the easiest spreadsheet and assume remaining project documents automatically receive identical approved changes.
  2. Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work.
  3. Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.
  4. Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.

Explanation

Correct Answer

D:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Incorrect Answers

A:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

B:

Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

C:

This option addresses a different CAPM project management topic (Work packages versus activities) rather than the documented Integrated baseline and change control decision.

Question 437

A project delivery review finds: A contractor substitutes a component under a formal request but execution teams never receive the approved drawing version and quality criteria. The team proposes: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change. Which project management principle most strongly supports the proposed response? Select ONE best answer.

  1. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.
  2. Quality planning specifies how processes and deliverables meet requirements; control measurements demonstrate observed conformance to those requirements.
  3. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.
  4. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.

Explanation

Correct Answer

A:

Demonstrable success requires: Everyone executes one approved baseline set and reports performance against the same current definitions.

Incorrect Answers

B:

This option addresses a different CAPM project management topic (Quality management plan and control) rather than the documented Integrated baseline and change control decision.

C:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

D:

Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Question 438

The project team has not approved a broad project-plan change. Available evidence indicates: A contractor substitutes a component under a formal request but execution teams never receive the approved drawing version and quality criteria. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.

  1. Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule.
  2. Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
  3. Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.
  4. Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.

Explanation

Correct Answer

C:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents. This check evaluates the actual project, quality or delivery decision before a risky project-wide change.

Incorrect Answers

A:

Check EV, PV and AC same-date values, calculation denominator and whether the status conclusion separates cost from schedule. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

B:

Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence. A contractor substitutes a component under a formal request but execution teams never receive the approved drawing version and quality criteria.

D:

Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

Question 439

A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A contractor substitutes a component under a formal request but execution teams never receive the approved drawing version and quality criteria. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.

  1. The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip.
  2. Everyone executes one approved baseline set and reports performance against the same current definitions.
  3. The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days.
  4. The status states SV=-20 for EV80/PV100 or SV=+15 for EV150/PV135 and draws the correct baseline comparison.

Explanation

Correct Answer

B:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents. The approved implementation step was: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.

Incorrect Answers

A:

This option addresses a different CAPM project management topic (Precedence dependencies and network sequencing) rather than the documented Integrated baseline and change control decision.

C:

The report correctly shows CV=-30 for EV120/AC150 or CV=+15 for EV210/AC195, with no false comparison to elapsed days. Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

D:

This option addresses a different CAPM project management topic (Schedule variance EV versus PV) rather than the documented Integrated baseline and change control decision.

Question 440

For an original CAPM project delivery study scenario, consider: A contractor substitutes a component under a formal request but execution teams never receive the approved drawing version and quality criteria. Select TWO complementary steps: the targeted correction and its strongest prechange validation.

  1. Check: Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.
  2. Check: Map each proposed activity to its purpose, authorization, baseline, performance information and closure evidence.
  3. Change: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.
  4. Revise only the easiest spreadsheet and assume remaining project documents automatically receive identical approved changes.
  5. Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue.

Explanation

Correct Answer

A:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents. Required intervention: Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.

C:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents. Evidence: Inspect change disposition, document revision IDs, work authorization, updated budgets, dates and acceptance tests across stakeholders.

Incorrect Answers

B:

Applied case: A contractor substitutes a component under a formal request but execution teams never receive the approved drawing version and quality criteria.

D:

Scope, schedule and cost baselines are interdependent control references; an approved change must be translated into coherent current execution documents.

E:

This option addresses a different CAPM project management topic (Estimate at completion forecasting) rather than the documented Integrated baseline and change control decision.