Cisco 350-601 Practice Test 46
Question 450
A server-pool policy selects a rack server with insufficient adapter or firmware capabilities for the required service profile. The observed failure is: blindly assigning a service profile to ineligible hardware results in association faults or nonfunctional interfaces. Which remediation most directly restores the intended behavior?
- The controlled remediation is to assign one service profile simultaneously to every blade chassis as if identities were shared.
- The controlled remediation is to correct qualifications and target eligibility, then validate association and boot on the intended server.
- The controlled remediation is to remove all server pools so profiles automatically match any hardware.
- The controlled remediation is to ignore adapter mismatches if the blade power LED is on.
Explanation
Correct Answer
B:This addresses the observable fault while preserving a check of the expected result. Validate against server pool membership, qualification policy, adapter capabilities and UCS association fault details.
Incorrect Answers
A:Assign one service profile simultaneously to every blade chassis as if identities were shared. This would not reliably restore service after the stated fault. Blindly assigning a service profile to ineligible hardware results in association faults or nonfunctional interfaces. The controlled recovery is to correct qualifications and target eligibility, then validate association and boot on the intended server.
C:Remove all server pools so profiles automatically match any hardware. This would not reliably restore service after the stated fault. Blindly assigning a service profile to ineligible hardware results in association faults or nonfunctional interfaces. The controlled recovery is to correct qualifications and target eligibility, then validate association and boot on the intended server.
D:Ignore adapter mismatches if the blade power LED is on. This would not reliably restore service after the stated fault. Blindly assigning a service profile to ineligible hardware results in association faults or nonfunctional interfaces. The controlled recovery is to correct qualifications and target eligibility, then validate association and boot on the intended server.
Question 451
A UCS service profile update unexpectedly reboots a production host because its maintenance policy permits immediate changes. Which configuration decision MOST directly resolves the issue?
- Disable power management alarms rather than controlling reboot timing.
- Assume all UCS changes are nondisruptive because they are policy based.
- Set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes.
- Force every host to reboot at the moment any template is saved.
Explanation
Correct Answer
C:This directly addresses maintenance policy reboot control because UCS maintenance policies control when policy modifications requiring reboot may be applied. Confirm the change against maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
Incorrect Answers
A:Immediate application without review can interrupt active workloads even when the policy change itself is valid. The relevant correction is to set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes.
B:Assume all UCS changes are nondisruptive because they are policy based. The proposed change targets the wrong mechanism or lacks essential validation. UCS maintenance policies control when policy modifications requiring reboot may be applied. Relevant evidence is maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
D:Immediate application without review can interrupt active workloads even when the policy change itself is valid. The appropriate action remains to set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes.
Question 452
A UCS service profile update unexpectedly reboots a production host because its maintenance policy permits immediate changes. What should the engineer inspect to confirm the actual state?
- A management ping that does not verify the required server or adapter function.
- The planned service profile template without checking effective deployed settings.
- The rack label without current UCS or Intersight policy associations.
- Maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
Explanation
Correct Answer
D:These observations test the actual maintenance policy reboot control mechanism rather than a superficial management status. They should be checked after set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes.
Incorrect Answers
A:This information cannot independently verify maintenance policy reboot control. The decisive records instead include maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
B:This information cannot independently verify maintenance policy reboot control. UCS maintenance policies control when policy modifications requiring reboot may be applied.
C:This information cannot independently verify maintenance policy reboot control. The rack label without current UCS or Intersight policy associations.
Question 453
A UCS service profile update unexpectedly reboots a production host because its maintenance policy permits immediate changes. What technical behavior underlies the correct decision?
- UCS maintenance policies control when policy modifications requiring reboot may be applied.
- All UCS configuration edits take effect without maintenance, validation or dependencies.
- A rack server that powers on is automatically configured for every SAN and LAN service.
- Service profiles can never change effective network identity or firmware behavior.
Explanation
Correct Answer
A:This explains why the most appropriate response is to set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes. Validation depends on maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
Incorrect Answers
B:All UCS configuration edits take effect without maintenance, validation or dependencies. This is an incorrect generalization for maintenance policy reboot control. The applicable technical behavior is that UCS maintenance policies control when policy modifications requiring reboot may be applied. The operator should verify maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
C:A rack server that powers on is automatically configured for every SAN and LAN service. This is an incorrect generalization for maintenance policy reboot control. The applicable technical behavior is that UCS maintenance policies control when policy modifications requiring reboot may be applied. The operator should verify maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
D:Service profiles can never change effective network identity or firmware behavior. This is an incorrect generalization for maintenance policy reboot control. The applicable technical behavior is that UCS maintenance policies control when policy modifications requiring reboot may be applied. The operator should verify maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
Question 454
A UCS service profile update unexpectedly reboots a production host because its maintenance policy permits immediate changes. Assume an engineer instead chooses to disable power management alarms rather than controlling reboot timing. Which resulting risk or fault should the reviewer identify?
- Checking effective service-profile bindings caused the original hardware mismatch.
- Immediate application without review can interrupt active workloads even when the policy change itself is valid.
- The underlying fault was caused only by retaining accurate firmware inventory.
- A controlled failover test itself proves that the previous outage had no cause.
Explanation
Correct Answer
B:The proper corrective action is to set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes. That is the direct consequence of choosing the misleading shortcut.
Incorrect Answers
A:This does not explain the actual maintenance policy reboot control defect after the shortcut. The meaningful failure is that immediate application without review can interrupt active workloads even when the policy change itself is valid.
C:This does not explain the actual maintenance policy reboot control defect after the shortcut. The relevant evidence is maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
D:This does not explain the actual maintenance policy reboot control defect after the shortcut. In the given case, a UCS service profile update unexpectedly reboots a production host because its maintenance policy permits immediate changes.
Question 455
A UCS service profile update unexpectedly reboots a production host because its maintenance policy permits immediate changes. The observed failure is: immediate application without review can interrupt active workloads even when the policy change itself is valid. Which remediation most directly restores the intended behavior?
- Assume all UCS changes are nondisruptive because they are policy based.
- Force every host to reboot at the moment any template is saved.
- Use approved user acknowledgment or schedule and verify stable host return after applying changes.
- Disable power management alarms rather than controlling reboot timing.
Explanation
Correct Answer
C:This addresses the observable fault while preserving a check of the expected result. Validate against maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
Incorrect Answers
A:Assume all UCS changes are nondisruptive because they are policy based. This would not reliably restore service after the stated fault. Immediate application without review can interrupt active workloads even when the policy change itself is valid. The controlled recovery is to use approved user acknowledgment or schedule and verify stable host return after applying changes.
B:Force every host to reboot at the moment any template is saved. This would not reliably restore service after the stated fault. Immediate application without review can interrupt active workloads even when the policy change itself is valid. The controlled recovery is to use approved user acknowledgment or schedule and verify stable host return after applying changes.
D:Disable power management alarms rather than controlling reboot timing. This would not reliably restore service after the stated fault. Immediate application without review can interrupt active workloads even when the policy change itself is valid. The controlled recovery is to use approved user acknowledgment or schedule and verify stable host return after applying changes.
Question 456
A network policy edit would require a blade reboot but the business expects the change to occur only during its approved window. Which operator action best meets this technical requirement?
- On this affected device, the engineer should assume all UCS changes are nondisruptive because they are policy based.
- On this affected device, the engineer should force every host to reboot at the moment any template is saved.
- On this affected device, the engineer should disable power management alarms rather than controlling reboot timing.
- On this affected device, the engineer should set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes.
Explanation
Correct Answer
D:This directly addresses maintenance policy reboot control because UCS maintenance policies control when policy modifications requiring reboot may be applied.
Incorrect Answers
A:Assume all UCS changes are nondisruptive because they are policy based. The proposed change targets the wrong mechanism or lacks essential validation. UCS maintenance policies control when policy modifications requiring reboot may be applied. Relevant evidence is maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
B:Immediate application without review can interrupt active workloads even when the policy change itself is valid.
C:Immediate application without review can interrupt active workloads even when the policy change itself is valid. Disable power management alarms rather than controlling reboot timing.
Question 457
A network policy edit would require a blade reboot but the business expects the change to occur only during its approved window. Which collection of observations most directly tests the suspected cause?
- For this deployment, examine maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
- For this deployment, examine an old inventory export that omits the current chassis and firmware state.
- For this deployment, examine a management ping that does not verify the required server or adapter function.
- For this deployment, examine the planned service profile template without checking effective deployed settings.
Explanation
Correct Answer
A:These observations test the actual maintenance policy reboot control mechanism rather than a superficial management status. UCS maintenance policies control when policy modifications requiring reboot may be applied.
Incorrect Answers
B:This information cannot independently verify maintenance policy reboot control. An old inventory export that omits the current chassis and firmware state.
C:This information cannot independently verify maintenance policy reboot control. A management ping that does not verify the required server or adapter function.
D:This information cannot independently verify maintenance policy reboot control. The planned service profile template without checking effective deployed settings.
Question 458
A network policy edit would require a blade reboot but the business expects the change to occur only during its approved window. Which statement most accurately explains this scenario?
- For this condition, the applicable principle is that service profiles can never change effective network identity or firmware behavior.
- For this condition, the applicable principle is that UCS maintenance policies control when policy modifications requiring reboot may be applied.
- For this condition, the applicable principle is that all UCS configuration edits take effect without maintenance, validation or dependencies.
- For this condition, the applicable principle is that out-of-band management reachability guarantees that all host interfaces operate correctly.
Explanation
Correct Answer
B:This explains why the most appropriate response is to set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes.
Incorrect Answers
A:Service profiles can never change effective network identity or firmware behavior. This is an incorrect generalization for maintenance policy reboot control. The applicable technical behavior is that UCS maintenance policies control when policy modifications requiring reboot may be applied. The operator should verify maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
C:All UCS configuration edits take effect without maintenance, validation or dependencies. This is an incorrect generalization for maintenance policy reboot control. The applicable technical behavior is that UCS maintenance policies control when policy modifications requiring reboot may be applied. The operator should verify maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
D:Out-of-band management reachability guarantees that all host interfaces operate correctly. This is an incorrect generalization for maintenance policy reboot control. The applicable technical behavior is that UCS maintenance policies control when policy modifications requiring reboot may be applied. The operator should verify maintenance policy, pending changes, generated reboot acknowledgment and scheduled service window.
Question 459
A network policy edit would require a blade reboot but the business expects the change to occur only during its approved window. Assume an engineer instead chooses to disable power management alarms rather than controlling reboot timing. What is the principal technical consequence of the mistaken choice?
- The resulting defect is that a controlled failover test itself proves that the previous outage had no cause.
- The resulting defect is that the only failure is that the administrator preserved a known-good backup.
- The resulting defect is that immediate application without review can interrupt active workloads even when the policy change itself is valid.
- The resulting defect is that the underlying fault was caused only by retaining accurate firmware inventory.
Explanation
Correct Answer
C:The proper corrective action is to set the correct service-profile maintenance and user-acknowledgment policy for disruptive changes. UCS maintenance policies control when policy modifications requiring reboot may be applied.
Incorrect Answers
A:This does not explain the actual maintenance policy reboot control defect after the shortcut. In the given case, a network policy edit would require a blade reboot but the business expects the change to occur only during its approved window.
B:This does not explain the actual maintenance policy reboot control defect after the shortcut. The only failure is that the administrator preserved a known-good backup.
D:This does not explain the actual maintenance policy reboot control defect after the shortcut. The underlying fault was caused only by retaining accurate firmware inventory.
Question 460
A network policy edit would require a blade reboot but the business expects the change to occur only during its approved window. The observed failure is: immediate application without review can interrupt active workloads even when the policy change itself is valid. What should the engineer do to recover and validate the service?
- The controlled remediation is to force every host to reboot at the moment any template is saved.
- The controlled remediation is to disable power management alarms rather than controlling reboot timing.
- The controlled remediation is to assume all UCS changes are nondisruptive because they are policy based.
- The controlled remediation is to use approved user acknowledgment or schedule and verify stable host return after applying changes.
Explanation
Correct Answer
D:This addresses the observable fault while preserving a check of the expected result. UCS maintenance policies control when policy modifications requiring reboot may be applied.
Incorrect Answers
A:Force every host to reboot at the moment any template is saved. This would not reliably restore service after the stated fault. Immediate application without review can interrupt active workloads even when the policy change itself is valid. The controlled recovery is to use approved user acknowledgment or schedule and verify stable host return after applying changes.
B:Disable power management alarms rather than controlling reboot timing. This would not reliably restore service after the stated fault. Immediate application without review can interrupt active workloads even when the policy change itself is valid. The controlled recovery is to use approved user acknowledgment or schedule and verify stable host return after applying changes.
C:Assume all UCS changes are nondisruptive because they are policy based. This would not reliably restore service after the stated fault. Immediate application without review can interrupt active workloads even when the policy change itself is valid. The controlled recovery is to use approved user acknowledgment or schedule and verify stable host return after applying changes.