cert
cert-1
cert-2

Pass PRINCE2 PRINCE2 7 Practitioner Exam in First Attempt Guaranteed!

Get 100% Latest Exam Questions, Accurate & Verified Answers to Pass the Actual Exam!
30 Days Free Updates, Instant Download!

cert-5
cert-6
PRINCE2 7 Practitioner Exam - Verified By Experts
PRINCE2 7 Practitioner Premium File

PRINCE2 7 Practitioner Premium File

$69.99
$76.99
  • Premium File 93 Questions & Answers. Last Update: Nov 19, 2026

Whats Included:

  • Latest Questions
  • 100% Accurate Answers
  • Fast Exam Updates
 
$76.99
$69.99
accept 11 downloads in the last 7 days
block-screenshots
PRINCE2 PRINCE2 7 Practitioner Practice Test 78

Question 770

A team wants to simplify its response to this situation: a community energy scheme has a cost exception proposal with competing recovery and cancellation options. Which shortcut is the LEAST defensible? Select ONE answer.

  1. Record residual issues, ownership, due dates and follow-on recommendations before closing
  2. Allow the project manager to authorize an exception plan beyond their own tolerance
  3. Negotiate and accept the work package with realistic scope, interfaces and quality criteria
  4. Have the project board assess the project brief and authorize a bounded initiation stage

Explanation

Correct Answer

B:

The unsafe shortcut is to allow the project manager to authorize an exception plan beyond their own tolerance. Directing a project retains board control when delegated management limits can no longer be met. The defensible response is instead to present the exception and alternatives for an authorized project board decision, using the diagnostic step to inspect the exception cause, forecast effect on business case and available corrective options before changing settings. Afterward, the team should confirm this result: A documented board decision approves revised tolerances, changes direction or stops the work. It must maintain the safeguard to track exception decisions and the approved replacement baseline. By contrast, the response tied to this evidence is: Allow the project manager to authorize an exception plan beyond their own tolerance.

Incorrect Answers

A:

Record residual issues, ownership, due dates and follow-on recommendations before closing. The board approves closure with clear transfer of every outstanding responsibility. Directing a project retains board control when delegated management limits can no longer be met. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.

C:

Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. Directing a project retains board control when delegated management limits can no longer be met. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.

D:

Have the project board assess the project brief and authorize a bounded initiation stage. Initiation expenditure is explicitly authorized without pre-approving the entire project. Directing a project retains board control when delegated management limits can no longer be met. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.

Question 771

A project delivery team reports that a civic data platform's product passes acceptance but the project manager closes it without sponsor review of residual risks. Which action directly addresses the issue? Select ONE answer.

  1. Negotiate and accept the work package with realistic scope, interfaces and quality criteria
  2. Produce a proportionate project brief and outline business case to support initiation authorization
  3. Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure
  4. Collect team checkpoint information and update stage forecasts against approved tolerances

Explanation

Correct Answer

C:

First, review end project report, user acceptance and any handover or follow-on recommendations. Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. The reported operational condition is that a civic data platform's product passes acceptance but the project manager closes it without sponsor review of residual risks. Project closure is a governance decision informed by benefits and operational readiness. Success means the board formally authorizes closure with operational ownership and residual obligations identified. Repeating schedule post-project benefit reviews and capture closure lessons helps prevent recurrence.

Incorrect Answers

A:

Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. Project closure is a governance decision informed by benefits and operational readiness.

B:

Produce a proportionate project brief and outline business case to support initiation authorization. The board can approve or reject initiation on a coherent brief with clear assumptions. Project closure is a governance decision informed by benefits and operational readiness.

D:

Collect team checkpoint information and update stage forecasts against approved tolerances. The project manager knows stage health early enough to take in-tolerance corrective action. Project closure is a governance decision informed by benefits and operational readiness.

Question 772

An administrator wants to identify the failure before making a change: a civic data platform's product passes acceptance but the project manager closes it without sponsor review of residual risks. Which inspection is the most informative? Select ONE answer.

  1. Inspect the project brief and identify missing organization, quality, risk, issue and progress controls
  2. Inspect the mandate, sponsor authority and initial expected products and constraints
  3. Compare team reports, accepted products and remaining dependencies with the stage plan
  4. Review end project report, user acceptance and any handover or follow-on recommendations

Explanation

Correct Answer

D:

The strongest first investigation is to review end project report, user acceptance and any handover or follow-on recommendations. Project closure is a governance decision informed by benefits and operational readiness. If that evidence confirms the issue, the team should give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. A subsequent acceptance check should confirm this result: The board formally authorizes closure with operational ownership and residual obligations identified. This check produces evidence before any broad configuration change, avoiding the risky proposal to erase unresolved follow-on actions as soon as a supplier marks delivery complete.

Incorrect Answers

A:

Inspect the project brief and identify missing organization, quality, risk, issue and progress controls. The board receives a coherent PID that establishes how the project will be managed and controlled. Project closure is a governance decision informed by benefits and operational readiness. The relevant investigation is: Review end project report, user acceptance and any handover or follow-on recommendations.

B:

Inspect the mandate, sponsor authority and initial expected products and constraints. The initiation decision is supported by a credible mandate and defined responsibilities. Project closure is a governance decision informed by benefits and operational readiness. The relevant investigation is: Review end project report, user acceptance and any handover or follow-on recommendations.

C:

Compare team reports, accepted products and remaining dependencies with the stage plan. The project manager knows stage health early enough to take in-tolerance corrective action. Project closure is a governance decision informed by benefits and operational readiness. The relevant investigation is: Review end project report, user acceptance and any handover or follow-on recommendations.

Question 773

After a controlled change, the team needs to resolve this report: a civic data platform's product passes acceptance but the project manager closes it without sponsor review of residual risks. Which observable result would best establish success? Select ONE answer.

  1. The board formally authorizes closure with operational ownership and residual obligations identified
  2. The revised plan is explicitly approved with renewed tolerances and managed dependencies
  3. Stage forecasts reflect actual work package progress and risks before failure
  4. The project approach is justified and can support realistic initiation planning

Explanation

Correct Answer

A:

A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to schedule post-project benefit reviews and capture closure lessons. The decisive acceptance evidence is this result: The board formally authorizes closure with operational ownership and residual obligations identified. Project closure is a governance decision informed by benefits and operational readiness. The operating team should diagnose it by checking whether it can review end project report, user acceptance and any handover or follow-on recommendations, then give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure where justified.

Incorrect Answers

B:

The revised plan is explicitly approved with renewed tolerances and managed dependencies. Project closure is a governance decision informed by benefits and operational readiness. Success in this case requires: The board formally authorizes closure with operational ownership and residual obligations identified.

C:

Stage forecasts reflect actual work package progress and risks before failure. Project closure is a governance decision informed by benefits and operational readiness. Success in this case requires: The board formally authorizes closure with operational ownership and residual obligations identified.

D:

The project approach is justified and can support realistic initiation planning. An early approach decision should be informed rather than prematurely irreversible. Project closure is a governance decision informed by benefits and operational readiness. Success in this case requires: The board formally authorizes closure with operational ownership and residual obligations identified.

Question 774

A project assurance reviewer sees a pattern in this report: a civic data platform's product passes acceptance but the project manager closes it without sponsor review of residual risks. Which recurring safeguard should remain in force? Select ONE answer.

  1. Follow up on significant lessons through organizational learning arrangements
  2. Schedule post-project benefit reviews and capture closure lessons
  3. Monitor recovery assumptions and report further predicted exceptions promptly
  4. Carry startup lessons into initiation and review them at later stages

Explanation

Correct Answer

B:

It complements, rather than replaces, the immediate administrative action to give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure and diagnostic evidence to review end project report, user acceptance and any handover or follow-on recommendations. Periodic testing should confirm this result: The board formally authorizes closure with operational ownership and residual obligations identified. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to schedule post-project benefit reviews and capture closure lessons. Project closure is a governance decision informed by benefits and operational readiness.

Incorrect Answers

A:

Follow up on significant lessons through organizational learning arrangements. A final lessons report has actionable recommendations and accountable dissemination. Project closure is a governance decision informed by benefits and operational readiness. To avoid recurrence, schedule post-project benefit reviews and capture closure lessons.

C:

Monitor recovery assumptions and report further predicted exceptions promptly. The revised plan is explicitly approved with renewed tolerances and managed dependencies. Project closure is a governance decision informed by benefits and operational readiness. To avoid recurrence, schedule post-project benefit reviews and capture closure lessons.

D:

Carry startup lessons into initiation and review them at later stages. The start-up documentation demonstrates applied learning and workable responsibilities. Project closure is a governance decision informed by benefits and operational readiness. To avoid recurrence, schedule post-project benefit reviews and capture closure lessons.

Question 775

A team wants to simplify its response to this situation: a civic data platform's product passes acceptance but the project manager closes it without sponsor review of residual risks. Which shortcut is the LEAST defensible? Select ONE answer.

  1. Record residual issues, ownership, due dates and follow-on recommendations before closing
  2. Document meaningful lessons and disseminate owned recommendations to relevant future project teams
  3. Erase unresolved follow-on actions as soon as a supplier marks delivery complete
  4. Prepare and seek approval of an exception plan that replaces the relevant affected plan

Explanation

Correct Answer

C:

The unsafe shortcut is to erase unresolved follow-on actions as soon as a supplier marks delivery complete. Project closure is a governance decision informed by benefits and operational readiness. The defensible response is instead to give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure, using the diagnostic step to review end project report, user acceptance and any handover or follow-on recommendations before changing settings. Afterward, the team should confirm this result: The board formally authorizes closure with operational ownership and residual obligations identified. It must maintain the safeguard to schedule post-project benefit reviews and capture closure lessons.

Incorrect Answers

A:

Record residual issues, ownership, due dates and follow-on recommendations before closing. The board approves closure with clear transfer of every outstanding responsibility. Project closure is a governance decision informed by benefits and operational readiness. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.

B:

Document meaningful lessons and disseminate owned recommendations to relevant future project teams. A final lessons report has actionable recommendations and accountable dissemination. Project closure is a governance decision informed by benefits and operational readiness. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.

D:

Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. Project closure is a governance decision informed by benefits and operational readiness. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.

Question 776

A project sponsor describes this requirement: a coastal infrastructure project finishes physical works but post-project benefit ownership is unclear at closure. Which step best meets it without creating unnecessary access? Select ONE answer.

  1. Agree project roles, reporting relationships, assurance and delegations in initiation documents
  2. Select and authorize proportionate corrective action within the project manager's delegated authority
  3. Confirm formal user acceptance against the project product description before recommending closure
  4. Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure

Explanation

Correct Answer

D:

First, review end project report, user acceptance and any handover or follow-on recommendations. Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. Project closure is a governance decision informed by benefits and operational readiness. Success means the board formally authorizes closure with operational ownership and residual obligations identified. Repeating schedule post-project benefit reviews and capture closure lessons helps prevent recurrence.

Incorrect Answers

A:

Agree project roles, reporting relationships, assurance and delegations in initiation documents. A working board and delivery organization are documented with accountable decisions and checks. The board formally authorizes closure with operational ownership and residual obligations identified.

B:

Select and authorize proportionate corrective action within the project manager's delegated authority. Recovery actions improve the forecast without changing unauthorized baselines. The board formally authorizes closure with operational ownership and residual obligations identified.

C:

Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The board formally authorizes closure with operational ownership and residual obligations identified.

Question 777

A project manager needs to diagnose this problem: a coastal infrastructure project finishes physical works but post-project benefit ownership is unclear at closure. Which investigation is the best initial check? Select ONE answer.

  1. Review end project report, user acceptance and any handover or follow-on recommendations
  2. Review completed product evidence, outstanding issues and assumptions for the upcoming stage
  3. Compare delivery evidence and unresolved findings with the agreed work package description
  4. Compare required controls with project risks, stakeholders, contracts and operating context

Explanation

Correct Answer

A:

The strongest first investigation is to review end project report, user acceptance and any handover or follow-on recommendations. Project closure is a governance decision informed by benefits and operational readiness. If that evidence confirms the issue, the team should give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. A subsequent acceptance check should confirm this result: The board formally authorizes closure with operational ownership and residual obligations identified. This check produces evidence before any broad configuration change, avoiding the risky proposal to erase unresolved follow-on actions as soon as a supplier marks delivery complete. By contrast, the response tied to this evidence is: Review end project report, user acceptance and any handover or follow-on recommendations.

Incorrect Answers

B:

Review completed product evidence, outstanding issues and assumptions for the upcoming stage. Stage boundaries create informed authorization points instead of unconditional funding. The board formally authorizes closure with operational ownership and residual obligations identified. The relevant investigation is: Review end project report, user acceptance and any handover or follow-on recommendations.

C:

Compare delivery evidence and unresolved findings with the agreed work package description. The receiving authority acknowledges accepted products and remaining obligations. The board formally authorizes closure with operational ownership and residual obligations identified. The relevant investigation is: Review end project report, user acceptance and any handover or follow-on recommendations.

D:

Compare required controls with project risks, stakeholders, contracts and operating context. Coordinated project controls must be established before distributed delivery begins. The board formally authorizes closure with operational ownership and residual obligations identified. The relevant investigation is: Review end project report, user acceptance and any handover or follow-on recommendations.

Question 778

The project team has corrected a reported weakness: a coastal infrastructure project finishes physical works but post-project benefit ownership is unclear at closure. Which acceptance result should the owner require? Select ONE answer.

  1. Board-level direction is requested before continuing work beyond delegated limits
  2. The board formally authorizes closure with operational ownership and residual obligations identified
  3. A working board and delivery organization are documented with accountable decisions and checks
  4. The board approves closure with clear transfer of every outstanding responsibility

Explanation

Correct Answer

B:

A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to schedule post-project benefit reviews and capture closure lessons. The decisive acceptance evidence is this result: The board formally authorizes closure with operational ownership and residual obligations identified. Project closure is a governance decision informed by benefits and operational readiness. The operating team should diagnose it by checking whether it can review end project report, user acceptance and any handover or follow-on recommendations, then give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure where justified. By contrast, the response tied to this evidence is: The board formally authorizes closure with operational ownership and residual obligations identified.

Incorrect Answers

A:

Board-level direction is requested before continuing work beyond delegated limits. Exception management is based on forecast tolerance breaches and decision rights. The board formally authorizes closure with operational ownership and residual obligations identified.

C:

A working board and delivery organization are documented with accountable decisions and checks. The board formally authorizes closure with operational ownership and residual obligations identified.

D:

The board approves closure with clear transfer of every outstanding responsibility. The board formally authorizes closure with operational ownership and residual obligations identified.

Question 779

The team has remediated this situation: a coastal infrastructure project finishes physical works but post-project benefit ownership is unclear at closure. What maintenance control most directly reduces repeat failures? Select ONE answer.

  1. Review justification at future stage boundaries and material external changes
  2. Replan at stage boundaries using updated evidence
  3. Schedule post-project benefit reviews and capture closure lessons
  4. Reconsider delivery assumptions if early supplier or technical evidence changes

Explanation

Correct Answer

C:

It complements, rather than replaces, the immediate administrative action to give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure and diagnostic evidence to review end project report, user acceptance and any handover or follow-on recommendations. Periodic testing should confirm this result: The board formally authorizes closure with operational ownership and residual obligations identified. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to schedule post-project benefit reviews and capture closure lessons. Project closure is a governance decision informed by benefits and operational readiness. By contrast, the response tied to this evidence is: Schedule post-project benefit reviews and capture closure lessons.

Incorrect Answers

A:

Review justification at future stage boundaries and material external changes. The board decides whether continued investment remains appropriate with transparent tradeoffs. The board formally authorizes closure with operational ownership and residual obligations identified. To avoid recurrence, schedule post-project benefit reviews and capture closure lessons.

B:

Replan at stage boundaries using updated evidence. The board can authorize staged delivery against a defensible project baseline. The board formally authorizes closure with operational ownership and residual obligations identified. To avoid recurrence, schedule post-project benefit reviews and capture closure lessons.

D:

Reconsider delivery assumptions if early supplier or technical evidence changes. An early approach decision should be informed rather than prematurely irreversible. The board formally authorizes closure with operational ownership and residual obligations identified. To avoid recurrence, schedule post-project benefit reviews and capture closure lessons.

Question 780

The service owner is reviewing actions after this report: a coastal infrastructure project finishes physical works but post-project benefit ownership is unclear at closure. Which proposed bypass would undermine the relevant security control? Select ONE answer.

  1. Negotiate and accept the work package with realistic scope, interfaces and quality criteria
  2. Provide timely checkpoint progress, issues and forecast updates to the project manager
  3. Use prior experience to tailor preliminary roles and startup controls before initiating
  4. Erase unresolved follow-on actions as soon as a supplier marks delivery complete

Explanation

Correct Answer

D:

The unsafe shortcut is to erase unresolved follow-on actions as soon as a supplier marks delivery complete. Project closure is a governance decision informed by benefits and operational readiness. The defensible response is instead to give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure, using the diagnostic step to review end project report, user acceptance and any handover or follow-on recommendations before changing settings. Afterward, the team should confirm this result: The board formally authorizes closure with operational ownership and residual obligations identified. It must maintain the safeguard to schedule post-project benefit reviews and capture closure lessons. By contrast, the response tied to this evidence is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.

Incorrect Answers

A:

Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. The board formally authorizes closure with operational ownership and residual obligations identified. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.

B:

Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. The board formally authorizes closure with operational ownership and residual obligations identified. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.

C:

Use prior experience to tailor preliminary roles and startup controls before initiating. The start-up documentation demonstrates applied learning and workable responsibilities. The board formally authorizes closure with operational ownership and residual obligations identified. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.