PRINCE2 PRINCE2 7 Practitioner Practice Test 80
Question 790
An operator suggests skipping safeguards after this event: a regional clinic transformation starts detailed development with unclear stage authority and no agreed baseline. Which action should be ruled out? Select ONE answer.
- Confirm formal user acceptance against the project product description before recommending closure
- Begin delivery with only a task list and no controlled management approaches
- Produce an exception report and escalate the forecast to the project board promptly
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
Explanation
Correct Answer
B:The unsafe shortcut is to begin delivery with only a task list and no controlled management approaches. Initiation defines credible governance before a full delivery commitment. The defensible response is instead to establish the project initiation documentation with management approaches, plans and tolerances, using the diagnostic step to inspect the project brief and identify missing organization, quality, risk, issue and progress controls before changing settings. Afterward, the team should confirm this result: The board receives a coherent PID that establishes how the project will be managed and controlled. It must maintain the safeguard to update the PID through authorized change and stage learning. By contrast, the response tied to this evidence is: Begin delivery with only a task list and no controlled management approaches.
Incorrect Answers
A:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.
C:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.
D:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.
Question 791
A PRINCE2 project manager receives this situation: a fisheries monitoring initiative selects an expensive platform without credible operating-benefit evidence. Which targeted corrective action should be chosen? Select ONE answer.
- Authorize a work package with products, acceptance, reporting and agreed constraints
- Evaluate how the project could be delivered and document a credible approach for initiation
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
Explanation
Correct Answer
C:First, check evidence for the proposed costs and benefit owners against available options. Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The initiation stage turns preliminary justification into an informed investment decision. Success means the board can assess desirability, viability and achievability before authorizing the project. Repeating refresh the business case and benefits approach after meaningful scope changes helps prevent recurrence.
Incorrect Answers
A:Authorize a work package with products, acceptance, reporting and agreed constraints. The team manager accepts a clear scope and reports against defined products and tolerances. The board can assess desirability, viability and achievability before authorizing the project.
B:Evaluate how the project could be delivered and document a credible approach for initiation. An early approach decision should be informed rather than prematurely irreversible. The board can assess desirability, viability and achievability before authorizing the project.
D:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. The board can assess desirability, viability and achievability before authorizing the project.
Question 792
A support engineer investigates this project governance report: a fisheries monitoring initiative selects an expensive platform without credible operating-benefit evidence. Which comparison should be made first? Select ONE answer.
- Inspect remaining defects, contracts and operational obligations against handover acceptance
- Compare issue effects on product descriptions, stage forecasts and decision limits
- Compare requested work with the approved stage plan and product descriptions
- Check evidence for the proposed costs and benefit owners against available options
Explanation
Correct Answer
D:The strongest first investigation is to check evidence for the proposed costs and benefit owners against available options. The initiation stage turns preliminary justification into an informed investment decision. If that evidence confirms the issue, the team should develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. A subsequent acceptance check should confirm this result: The board can assess desirability, viability and achievability before authorizing the project. This check produces evidence before any broad configuration change, avoiding the risky proposal to reuse an optimistic outline business case without examining new information.
Incorrect Answers
A:Inspect remaining defects, contracts and operational obligations against handover acceptance. The board approves closure with clear transfer of every outstanding responsibility. The board can assess desirability, viability and achievability before authorizing the project. The relevant investigation is: Check evidence for the proposed costs and benefit owners against available options.
B:Compare issue effects on product descriptions, stage forecasts and decision limits. Approved issue actions and escalations remain traceable to the current stage baseline. The board can assess desirability, viability and achievability before authorizing the project. The relevant investigation is: Check evidence for the proposed costs and benefit owners against available options.
C:Compare requested work with the approved stage plan and product descriptions. The team manager accepts a clear scope and reports against defined products and tolerances. The board can assess desirability, viability and achievability before authorizing the project. The relevant investigation is: Check evidence for the proposed costs and benefit owners against available options.
Question 793
An auditor asks how to validate resolution of this situation: a fisheries monitoring initiative selects an expensive platform without credible operating-benefit evidence. Which direct evidence is strongest? Select ONE answer.
- The board can assess desirability, viability and achievability before authorizing the project
- The revised plan is explicitly approved with renewed tolerances and managed dependencies
- The project approach is justified and can support realistic initiation planning
- The receiving authority acknowledges accepted products and remaining obligations
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to refresh the business case and benefits approach after meaningful scope changes. The decisive acceptance evidence is this result: The board can assess desirability, viability and achievability before authorizing the project. The initiation stage turns preliminary justification into an informed investment decision. The operating team should diagnose it by checking whether it can check evidence for the proposed costs and benefit owners against available options, then develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions where justified.
Incorrect Answers
B:The revised plan is explicitly approved with renewed tolerances and managed dependencies. The board can assess desirability, viability and achievability before authorizing the project.
C:The project approach is justified and can support realistic initiation planning. An early approach decision should be informed rather than prematurely irreversible. The board can assess desirability, viability and achievability before authorizing the project.
D:The receiving authority acknowledges accepted products and remaining obligations. The board can assess desirability, viability and achievability before authorizing the project.
Question 794
The project executive wants lasting assurance after this event: a fisheries monitoring initiative selects an expensive platform without credible operating-benefit evidence. Which preventive practice should be adopted? Select ONE answer.
- Reconsider delivery assumptions if early supplier or technical evidence changes
- Refresh the business case and benefits approach after meaningful scope changes
- Retain acceptance artifacts and residual obligations in the closure record
- Review issue status and cumulative change effects at each stage control point
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions and diagnostic evidence to check evidence for the proposed costs and benefit owners against available options. Periodic testing should confirm this result: The board can assess desirability, viability and achievability before authorizing the project. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to refresh the business case and benefits approach after meaningful scope changes. The initiation stage turns preliminary justification into an informed investment decision.
Incorrect Answers
A:Reconsider delivery assumptions if early supplier or technical evidence changes. An early approach decision should be informed rather than prematurely irreversible. The board can assess desirability, viability and achievability before authorizing the project. To avoid recurrence, refresh the business case and benefits approach after meaningful scope changes.
C:Retain acceptance artifacts and residual obligations in the closure record. Evidence of the products delivered, not simply a completed activity list. The board can assess desirability, viability and achievability before authorizing the project. To avoid recurrence, refresh the business case and benefits approach after meaningful scope changes.
D:Review issue status and cumulative change effects at each stage control point. Approved issue actions and escalations remain traceable to the current stage baseline. The board can assess desirability, viability and achievability before authorizing the project. To avoid recurrence, refresh the business case and benefits approach after meaningful scope changes.
Question 795
An operator suggests skipping safeguards after this event: a fisheries monitoring initiative selects an expensive platform without credible operating-benefit evidence. Which action should be ruled out? Select ONE answer.
- Define proportionate agreed approaches for risk, issues, quality, communications, change and project information
- Execute the agreed work package and its quality activities under team management control
- Reuse an optimistic outline business case without examining new information
- Handover operational responsibilities and future benefit reviews to named accountable owners
Explanation
Correct Answer
C:The unsafe shortcut is to reuse an optimistic outline business case without examining new information. The initiation stage turns preliminary justification into an informed investment decision. The defensible response is instead to develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions, using the diagnostic step to check evidence for the proposed costs and benefit owners against available options before changing settings. Afterward, the team should confirm this result: The board can assess desirability, viability and achievability before authorizing the project. It must maintain the safeguard to refresh the business case and benefits approach after meaningful scope changes.
Incorrect Answers
A:Define proportionate agreed approaches for risk, issues, quality, communications, change and project information. Coordinated project controls must be established before distributed delivery begins. The board can assess desirability, viability and achievability before authorizing the project. The shortcut most directly implicated here is: Reuse an optimistic outline business case without examining new information.
B:Execute the agreed work package and its quality activities under team management control. The team produces quality-verified deliverables that can be formally handed over. The board can assess desirability, viability and achievability before authorizing the project. The shortcut most directly implicated here is: Reuse an optimistic outline business case without examining new information.
D:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. The board can assess desirability, viability and achievability before authorizing the project. The shortcut most directly implicated here is: Reuse an optimistic outline business case without examining new information.
Question 796
A project board needs to manage this condition: a digital court program has initial scope but has not tested whether future benefits justify staff disruption. Which administrative action best resolves the specific control gap? Select ONE answer.
- Define proportionate agreed approaches for risk, issues, quality, communications, change and project information
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Authorize a work package with products, acceptance, reporting and agreed constraints
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
Explanation
Correct Answer
D:First, check evidence for the proposed costs and benefit owners against available options. Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The initiation stage turns preliminary justification into an informed investment decision. Success means the board can assess desirability, viability and achievability before authorizing the project. Repeating refresh the business case and benefits approach after meaningful scope changes helps prevent recurrence. By contrast, the response tied to this evidence is: Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions.
Incorrect Answers
A:Define proportionate agreed approaches for risk, issues, quality, communications, change and project information. Coordinated project controls must be established before distributed delivery begins. The board can assess desirability, viability and achievability before authorizing the project.
B:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. The board can assess desirability, viability and achievability before authorizing the project. By contrast, the response tied to this evidence is: Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions.
C:Authorize a work package with products, acceptance, reporting and agreed constraints. The team manager accepts a clear scope and reports against defined products and tolerances. The board can assess desirability, viability and achievability before authorizing the project. By contrast, the response tied to this evidence is: Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions.
Question 797
An operations team is unsure why this occurred: a digital court program has initial scope but has not tested whether future benefits justify staff disruption. Which targeted diagnostic step would produce the most relevant evidence? Select ONE answer.
- Check evidence for the proposed costs and benefit owners against available options
- Compare preliminary user objectives, constraints, risks and known delivery options
- Compare delivery alternatives against expected products, capabilities, constraints and risks
- Compare issue effects on product descriptions, stage forecasts and decision limits
Explanation
Correct Answer
A:The strongest first investigation is to check evidence for the proposed costs and benefit owners against available options. The initiation stage turns preliminary justification into an informed investment decision. If that evidence confirms the issue, the team should develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. A subsequent acceptance check should confirm this result: The board can assess desirability, viability and achievability before authorizing the project. This check produces evidence before any broad configuration change, avoiding the risky proposal to reuse an optimistic outline business case without examining new information. By contrast, the response tied to this evidence is: Check evidence for the proposed costs and benefit owners against available options.
Incorrect Answers
B:Compare preliminary user objectives, constraints, risks and known delivery options. The board can approve or reject initiation on a coherent brief with clear assumptions. The board can assess desirability, viability and achievability before authorizing the project. The relevant investigation is: Check evidence for the proposed costs and benefit owners against available options.
C:Compare delivery alternatives against expected products, capabilities, constraints and risks. An early approach decision should be informed rather than prematurely irreversible. The board can assess desirability, viability and achievability before authorizing the project. The relevant investigation is: Check evidence for the proposed costs and benefit owners against available options.
D:Compare issue effects on product descriptions, stage forecasts and decision limits. Approved issue actions and escalations remain traceable to the current stage baseline. The board can assess desirability, viability and achievability before authorizing the project. The relevant investigation is: Check evidence for the proposed costs and benefit owners against available options. This check produces evidence before any broad configuration change, avoiding the risky proposal to reuse an optimistic outline business case without examining new information.
Question 798
The senior user wants proof that this problem is resolved: a digital court program has initial scope but has not tested whether future benefits justify staff disruption. Which end-to-end verification is most useful? Select ONE answer.
- Board-level direction is requested before continuing work beyond delegated limits
- The board can assess desirability, viability and achievability before authorizing the project
- The project approach is justified and can support realistic initiation planning
- The team manager accepts a clear scope and reports against defined products and tolerances
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to refresh the business case and benefits approach after meaningful scope changes. The decisive acceptance evidence is this result: The board can assess desirability, viability and achievability before authorizing the project. The initiation stage turns preliminary justification into an informed investment decision. The operating team should diagnose it by checking whether it can check evidence for the proposed costs and benefit owners against available options, then develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions where justified. By contrast, the response tied to this evidence is: The board can assess desirability, viability and achievability before authorizing the project.
Incorrect Answers
A:Board-level direction is requested before continuing work beyond delegated limits. Exception management is based on forecast tolerance breaches and decision rights. The board can assess desirability, viability and achievability before authorizing the project.
C:The project approach is justified and can support realistic initiation planning. An early approach decision should be informed rather than prematurely irreversible. The board can assess desirability, viability and achievability before authorizing the project. The operating team should diagnose it by checking whether it can check evidence for the proposed costs and benefit owners against available options, then develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions where justified.
D:The team manager accepts a clear scope and reports against defined products and tolerances. The board can assess desirability, viability and achievability before authorizing the project.
Question 799
An incident has been closed after the team addressed this condition: a digital court program has initial scope but has not tested whether future benefits justify staff disruption. Which follow-up control is most effective? Select ONE answer.
- Retain approval conditions and monitor authorized tolerances throughout delivery
- Monitor recovery assumptions and report further predicted exceptions promptly
- Refresh the business case and benefits approach after meaningful scope changes
- Monitor package-level progress, defects and dependency risks during delivery
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions and diagnostic evidence to check evidence for the proposed costs and benefit owners against available options. Periodic testing should confirm this result: The board can assess desirability, viability and achievability before authorizing the project. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to refresh the business case and benefits approach after meaningful scope changes. The initiation stage turns preliminary justification into an informed investment decision. By contrast, the response tied to this evidence is: Refresh the business case and benefits approach after meaningful scope changes.
Incorrect Answers
A:Retain approval conditions and monitor authorized tolerances throughout delivery. The project board authorizes the project and first management stage on coherent evidence. The board can assess desirability, viability and achievability before authorizing the project. To avoid recurrence, refresh the business case and benefits approach after meaningful scope changes.
B:Monitor recovery assumptions and report further predicted exceptions promptly. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The board can assess desirability, viability and achievability before authorizing the project. To avoid recurrence, refresh the business case and benefits approach after meaningful scope changes.
D:Monitor package-level progress, defects and dependency risks during delivery. The team produces quality-verified deliverables that can be formally handed over. The board can assess desirability, viability and achievability before authorizing the project. To avoid recurrence, refresh the business case and benefits approach after meaningful scope changes.
Question 800
For this project-management problem, the team is comparing possible shortcuts: a digital court program has initial scope but has not tested whether future benefits justify staff disruption. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure
- Record residual issues, ownership, due dates and follow-on recommendations before closing
- Prepare a detailed next management stage plan grounded in actual results and current forecasts
- Reuse an optimistic outline business case without examining new information
Explanation
Correct Answer
D:The unsafe shortcut is to reuse an optimistic outline business case without examining new information. The initiation stage turns preliminary justification into an informed investment decision. The defensible response is instead to develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions, using the diagnostic step to check evidence for the proposed costs and benefit owners against available options before changing settings. Afterward, the team should confirm this result: The board can assess desirability, viability and achievability before authorizing the project. It must maintain the safeguard to refresh the business case and benefits approach after meaningful scope changes. By contrast, the response tied to this evidence is: Reuse an optimistic outline business case without examining new information.
Incorrect Answers
A:Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. Project closure is a governance decision informed by benefits and operational readiness. The board can assess desirability, viability and achievability before authorizing the project. The shortcut most directly implicated here is: Reuse an optimistic outline business case without examining new information.
B:Record residual issues, ownership, due dates and follow-on recommendations before closing. The board approves closure with clear transfer of every outstanding responsibility. The board can assess desirability, viability and achievability before authorizing the project. The shortcut most directly implicated here is: Reuse an optimistic outline business case without examining new information.
C:Prepare a detailed next management stage plan grounded in actual results and current forecasts. Stage boundaries create informed authorization points instead of unconditional funding. The board can assess desirability, viability and achievability before authorizing the project. The shortcut most directly implicated here is: Reuse an optimistic outline business case without examining new information.