PRINCE2 PRINCE2 7 Practitioner Practice Test 79
Question 780
The service owner is reviewing actions after this report: a coastal infrastructure project finishes physical works but post-project benefit ownership is unclear at closure. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Provide timely checkpoint progress, issues and forecast updates to the project manager
- Use prior experience to tailor preliminary roles and startup controls before initiating
- Erase unresolved follow-on actions as soon as a supplier marks delivery complete
Explanation
Correct Answer
D:The unsafe shortcut is to erase unresolved follow-on actions as soon as a supplier marks delivery complete. Project closure is a governance decision informed by benefits and operational readiness. The defensible response is instead to give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure, using the diagnostic step to review end project report, user acceptance and any handover or follow-on recommendations before changing settings. Afterward, the team should confirm this result: The board formally authorizes closure with operational ownership and residual obligations identified. It must maintain the safeguard to schedule post-project benefit reviews and capture closure lessons. By contrast, the response tied to this evidence is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.
Incorrect Answers
A:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. The board formally authorizes closure with operational ownership and residual obligations identified. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.
B:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. The board formally authorizes closure with operational ownership and residual obligations identified. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.
C:Use prior experience to tailor preliminary roles and startup controls before initiating. The start-up documentation demonstrates applied learning and workable responsibilities. The board formally authorizes closure with operational ownership and residual obligations identified. The shortcut most directly implicated here is: Erase unresolved follow-on actions as soon as a supplier marks delivery complete.
Question 781
A project sponsor describes this requirement: a national grant system has an approved brief but no plan for reporting or exception escalation across agencies. Which step best meets it without creating unnecessary access? Select ONE answer.
- Establish the project initiation documentation with management approaches, plans and tolerances
- Select and authorize proportionate corrective action within the project manager's delegated authority
- Present the exception and alternatives for an authorized project board decision
- Handover operational responsibilities and future benefit reviews to named accountable owners
Explanation
Correct Answer
A:First, inspect the project brief and identify missing organization, quality, risk, issue and progress controls. Establish the project initiation documentation with management approaches, plans and tolerances. Initiation defines credible governance before a full delivery commitment. Success means the board receives a coherent PID that establishes how the project will be managed and controlled. Repeating update the PID through authorized change and stage learning helps prevent recurrence.
Incorrect Answers
B:Select and authorize proportionate corrective action within the project manager's delegated authority. Recovery actions improve the forecast without changing unauthorized baselines. The board receives a coherent PID that establishes how the project will be managed and controlled.
C:Present the exception and alternatives for an authorized project board decision. A documented board decision approves revised tolerances, changes direction or stops the work. The board receives a coherent PID that establishes how the project will be managed and controlled.
D:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. The board receives a coherent PID that establishes how the project will be managed and controlled.
Question 782
A project manager needs to diagnose this problem: a national grant system has an approved brief but no plan for reporting or exception escalation across agencies. Which investigation is the best initial check? Select ONE answer.
- Inspect the exception cause, forecast effect on business case and available corrective options
- Inspect the project brief and identify missing organization, quality, risk, issue and progress controls
- Compare required controls with project risks, stakeholders, contracts and operating context
- Inspect planned product dependencies, resource commitments and forecast tolerances
Explanation
Correct Answer
B:The strongest first investigation is to inspect the project brief and identify missing organization, quality, risk, issue and progress controls. Initiation defines credible governance before a full delivery commitment. If that evidence confirms the issue, the team should establish the project initiation documentation with management approaches, plans and tolerances. A subsequent acceptance check should confirm this result: The board receives a coherent PID that establishes how the project will be managed and controlled. This check produces evidence before any broad configuration change, avoiding the risky proposal to begin delivery with only a task list and no controlled management approaches.
Incorrect Answers
A:Inspect the exception cause, forecast effect on business case and available corrective options. A documented board decision approves revised tolerances, changes direction or stops the work. The board receives a coherent PID that establishes how the project will be managed and controlled. The relevant investigation is: Inspect the project brief and identify missing organization, quality, risk, issue and progress controls.
C:Compare required controls with project risks, stakeholders, contracts and operating context. Coordinated project controls must be established before distributed delivery begins. The board receives a coherent PID that establishes how the project will be managed and controlled. The relevant investigation is: Inspect the project brief and identify missing organization, quality, risk, issue and progress controls.
D:Inspect planned product dependencies, resource commitments and forecast tolerances. The board can authorize staged delivery against a defensible project baseline. The board receives a coherent PID that establishes how the project will be managed and controlled. The relevant investigation is: Inspect the project brief and identify missing organization, quality, risk, issue and progress controls.
Question 783
The project team has corrected a reported weakness: a national grant system has an approved brief but no plan for reporting or exception escalation across agencies. Which acceptance result should the owner require? Select ONE answer.
- The board decides whether continued investment remains appropriate with transparent tradeoffs
- A working board and delivery organization are documented with accountable decisions and checks
- The board receives a coherent PID that establishes how the project will be managed and controlled
- The board receives a credible next-stage plan with justified commitments and tolerances
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to update the PID through authorized change and stage learning. The decisive acceptance evidence is this result: The board receives a coherent PID that establishes how the project will be managed and controlled. Initiation defines credible governance before a full delivery commitment. The operating team should diagnose it by checking whether it can inspect the project brief and identify missing organization, quality, risk, issue and progress controls, then establish the project initiation documentation with management approaches, plans and tolerances where justified.
Incorrect Answers
A:The board decides whether continued investment remains appropriate with transparent tradeoffs. The board receives a coherent PID that establishes how the project will be managed and controlled.
B:A working board and delivery organization are documented with accountable decisions and checks. The board receives a coherent PID that establishes how the project will be managed and controlled.
D:The board receives a credible next-stage plan with justified commitments and tolerances. Stage boundaries create informed authorization points instead of unconditional funding. The board receives a coherent PID that establishes how the project will be managed and controlled.
Question 784
The team has remediated this situation: a national grant system has an approved brief but no plan for reporting or exception escalation across agencies. What maintenance control most directly reduces repeat failures? Select ONE answer.
- Conduct planned post-project reviews outside the closed delivery project
- Refresh tolerance forecasts as corrective actions or risk assumptions change
- Review work package interfaces when dependencies or product criteria change
- Update the PID through authorized change and stage learning
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to establish the project initiation documentation with management approaches, plans and tolerances and diagnostic evidence to inspect the project brief and identify missing organization, quality, risk, issue and progress controls. Periodic testing should confirm this result: The board receives a coherent PID that establishes how the project will be managed and controlled. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to update the PID through authorized change and stage learning. Initiation defines credible governance before a full delivery commitment.
Incorrect Answers
A:Conduct planned post-project reviews outside the closed delivery project. Some benefits mature after project closure and must have real ownership. The board receives a coherent PID that establishes how the project will be managed and controlled. To avoid recurrence, update the PID through authorized change and stage learning.
B:Refresh tolerance forecasts as corrective actions or risk assumptions change. Exception management is based on forecast tolerance breaches and decision rights. The board receives a coherent PID that establishes how the project will be managed and controlled. To avoid recurrence, update the PID through authorized change and stage learning.
C:Review work package interfaces when dependencies or product criteria change. The team manager accepts a clear scope and reports against defined products and tolerances. The board receives a coherent PID that establishes how the project will be managed and controlled. To avoid recurrence, update the PID through authorized change and stage learning.
Question 785
The service owner is reviewing actions after this report: a national grant system has an approved brief but no plan for reporting or exception escalation across agencies. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Begin delivery with only a task list and no controlled management approaches
- Evaluate how the project could be delivered and document a credible approach for initiation
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Have the project board assess the project brief and authorize a bounded initiation stage
Explanation
Correct Answer
A:The unsafe shortcut is to begin delivery with only a task list and no controlled management approaches. Initiation defines credible governance before a full delivery commitment. The defensible response is instead to establish the project initiation documentation with management approaches, plans and tolerances, using the diagnostic step to inspect the project brief and identify missing organization, quality, risk, issue and progress controls before changing settings. Afterward, the team should confirm this result: The board receives a coherent PID that establishes how the project will be managed and controlled. It must maintain the safeguard to update the PID through authorized change and stage learning.
Incorrect Answers
B:Evaluate how the project could be delivered and document a credible approach for initiation. An early approach decision should be informed rather than prematurely irreversible. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.
C:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.
D:Have the project board assess the project brief and authorize a bounded initiation stage. Initiation expenditure is explicitly authorized without pre-approving the entire project. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.
Question 786
A PRINCE2 project manager receives this situation: a regional clinic transformation starts detailed development with unclear stage authority and no agreed baseline. Which targeted corrective action should be chosen? Select ONE answer.
- Submit the completed initiation documentation and initial stage plan for formal board authorization
- Establish the project initiation documentation with management approaches, plans and tolerances
- Present the exception and alternatives for an authorized project board decision
- Handover operational responsibilities and future benefit reviews to named accountable owners
Explanation
Correct Answer
B:First, inspect the project brief and identify missing organization, quality, risk, issue and progress controls. Establish the project initiation documentation with management approaches, plans and tolerances. Initiation defines credible governance before a full delivery commitment. Success means the board receives a coherent PID that establishes how the project will be managed and controlled. Repeating update the PID through authorized change and stage learning helps prevent recurrence. By contrast, the response tied to this evidence is: Establish the project initiation documentation with management approaches, plans and tolerances.
Incorrect Answers
A:Submit the completed initiation documentation and initial stage plan for formal board authorization. The project board authorizes the project and first management stage on coherent evidence. The board receives a coherent PID that establishes how the project will be managed and controlled.
C:Present the exception and alternatives for an authorized project board decision. A documented board decision approves revised tolerances, changes direction or stops the work. The board receives a coherent PID that establishes how the project will be managed and controlled. By contrast, the response tied to this evidence is: Establish the project initiation documentation with management approaches, plans and tolerances.
D:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. The board receives a coherent PID that establishes how the project will be managed and controlled. By contrast, the response tied to this evidence is: Establish the project initiation documentation with management approaches, plans and tolerances.
Question 787
A support engineer investigates this project governance report: a regional clinic transformation starts detailed development with unclear stage authority and no agreed baseline. Which comparison should be made first? Select ONE answer.
- Compare preliminary user objectives, constraints, risks and known delivery options
- Inspect outstanding criteria, quality evidence and authorized acceptance decisions
- Inspect the project brief and identify missing organization, quality, risk, issue and progress controls
- Compare delivery alternatives against expected products, capabilities, constraints and risks
Explanation
Correct Answer
C:The strongest first investigation is to inspect the project brief and identify missing organization, quality, risk, issue and progress controls. Initiation defines credible governance before a full delivery commitment. If that evidence confirms the issue, the team should establish the project initiation documentation with management approaches, plans and tolerances. A subsequent acceptance check should confirm this result: The board receives a coherent PID that establishes how the project will be managed and controlled. This check produces evidence before any broad configuration change, avoiding the risky proposal to begin delivery with only a task list and no controlled management approaches. By contrast, the response tied to this evidence is: Inspect the project brief and identify missing organization, quality, risk, issue and progress controls.
Incorrect Answers
A:Compare preliminary user objectives, constraints, risks and known delivery options. The board can approve or reject initiation on a coherent brief with clear assumptions. The board receives a coherent PID that establishes how the project will be managed and controlled. The relevant investigation is: Inspect the project brief and identify missing organization, quality, risk, issue and progress controls.
B:Inspect outstanding criteria, quality evidence and authorized acceptance decisions. Evidence of the products delivered, not simply a completed activity list. The board receives a coherent PID that establishes how the project will be managed and controlled. The relevant investigation is: Inspect the project brief and identify missing organization, quality, risk, issue and progress controls.
D:Compare delivery alternatives against expected products, capabilities, constraints and risks. An early approach decision should be informed rather than prematurely irreversible. The board receives a coherent PID that establishes how the project will be managed and controlled. The relevant investigation is: Inspect the project brief and identify missing organization, quality, risk, issue and progress controls.
Question 788
An auditor asks how to validate resolution of this situation: a regional clinic transformation starts detailed development with unclear stage authority and no agreed baseline. Which direct evidence is strongest? Select ONE answer.
- The project board receives evidence that the final products meet agreed acceptance conditions
- The receiving authority acknowledges accepted products and remaining obligations
- The team produces quality-verified deliverables that can be formally handed over
- The board receives a coherent PID that establishes how the project will be managed and controlled
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to update the PID through authorized change and stage learning. The decisive acceptance evidence is this result: The board receives a coherent PID that establishes how the project will be managed and controlled. Initiation defines credible governance before a full delivery commitment. The operating team should diagnose it by checking whether it can inspect the project brief and identify missing organization, quality, risk, issue and progress controls, then establish the project initiation documentation with management approaches, plans and tolerances where justified. By contrast, the response tied to this evidence is: The board receives a coherent PID that establishes how the project will be managed and controlled.
Incorrect Answers
A:The project board receives evidence that the final products meet agreed acceptance conditions. Evidence of the products delivered, not simply a completed activity list. The board receives a coherent PID that establishes how the project will be managed and controlled.
B:The receiving authority acknowledges accepted products and remaining obligations. The board receives a coherent PID that establishes how the project will be managed and controlled.
C:The team produces quality-verified deliverables that can be formally handed over. The board receives a coherent PID that establishes how the project will be managed and controlled.
Question 789
The project executive wants lasting assurance after this event: a regional clinic transformation starts detailed development with unclear stage authority and no agreed baseline. Which preventive practice should be adopted? Select ONE answer.
- Update the PID through authorized change and stage learning
- Refresh the business case and benefits approach after meaningful scope changes
- Maintain regular evidence-based checkpoint reporting for all active packages
- Retain acceptance artifacts and residual obligations in the closure record
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to establish the project initiation documentation with management approaches, plans and tolerances and diagnostic evidence to inspect the project brief and identify missing organization, quality, risk, issue and progress controls. Periodic testing should confirm this result: The board receives a coherent PID that establishes how the project will be managed and controlled. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to update the PID through authorized change and stage learning. Initiation defines credible governance before a full delivery commitment. By contrast, the response tied to this evidence is: Update the PID through authorized change and stage learning.
Incorrect Answers
B:Refresh the business case and benefits approach after meaningful scope changes. The board can assess desirability, viability and achievability before authorizing the project. The board receives a coherent PID that establishes how the project will be managed and controlled. To avoid recurrence, update the PID through authorized change and stage learning.
C:Maintain regular evidence-based checkpoint reporting for all active packages. Stage forecasts reflect actual work package progress and risks before failure. The board receives a coherent PID that establishes how the project will be managed and controlled. To avoid recurrence, update the PID through authorized change and stage learning.
D:Retain acceptance artifacts and residual obligations in the closure record. Evidence of the products delivered, not simply a completed activity list. The board receives a coherent PID that establishes how the project will be managed and controlled. To avoid recurrence, update the PID through authorized change and stage learning.
Question 790
An operator suggests skipping safeguards after this event: a regional clinic transformation starts detailed development with unclear stage authority and no agreed baseline. Which action should be ruled out? Select ONE answer.
- Confirm formal user acceptance against the project product description before recommending closure
- Begin delivery with only a task list and no controlled management approaches
- Produce an exception report and escalate the forecast to the project board promptly
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
Explanation
Correct Answer
B:The unsafe shortcut is to begin delivery with only a task list and no controlled management approaches. Initiation defines credible governance before a full delivery commitment. The defensible response is instead to establish the project initiation documentation with management approaches, plans and tolerances, using the diagnostic step to inspect the project brief and identify missing organization, quality, risk, issue and progress controls before changing settings. Afterward, the team should confirm this result: The board receives a coherent PID that establishes how the project will be managed and controlled. It must maintain the safeguard to update the PID through authorized change and stage learning. By contrast, the response tied to this evidence is: Begin delivery with only a task list and no controlled management approaches.
Incorrect Answers
A:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.
C:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.
D:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The board receives a coherent PID that establishes how the project will be managed and controlled. The shortcut most directly implicated here is: Begin delivery with only a task list and no controlled management approaches.