PRINCE2 PRINCE2 7 Practitioner Practice Test 77
Question 760
A project manager is under pressure to address the following issue quickly: a water treatment replacement has a validated business case but no signed stage plan or clear project-level tolerances. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Select and authorize proportionate corrective action within the project manager's delegated authority
- Collect team checkpoint information and update stage forecasts against approved tolerances
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
- Treat completion of planning documents as automatic permission to deliver
Explanation
Correct Answer
D:The unsafe shortcut is to treat completion of planning documents as automatic permission to deliver. Only the appropriate authority should commit the project after initiation clarifies its viability. The defensible response is instead to submit the completed initiation documentation and initial stage plan for formal board authorization, using the diagnostic step to compare the PID, business case, project plan and proposed tolerances with the project brief before changing settings. Afterward, the team should confirm this result: The project board authorizes the project and first management stage on coherent evidence. It must maintain the safeguard to retain approval conditions and monitor authorized tolerances throughout delivery. By contrast, the response tied to this evidence is: Treat completion of planning documents as automatic permission to deliver.
Incorrect Answers
A:Select and authorize proportionate corrective action within the project manager's delegated authority. Recovery actions improve the forecast without changing unauthorized baselines. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.
B:Collect team checkpoint information and update stage forecasts against approved tolerances. The project manager knows stage health early enough to take in-tolerance corrective action. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.
C:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.
Question 761
During a PRINCE2 management-stage review, the team encounters this situation: a public library upgrade forecasts an unrecoverable stage delay but the project manager wants to approve a private workaround. What is the most appropriate controlled response? Select ONE answer.
- Present the exception and alternatives for an authorized project board decision
- Select and authorize proportionate corrective action within the project manager's delegated authority
- Produce an exception report and escalate the forecast to the project board promptly
- Prepare a detailed next management stage plan grounded in actual results and current forecasts
Explanation
Correct Answer
A:First, inspect the exception cause, forecast effect on business case and available corrective options. Present the exception and alternatives for an authorized project board decision. Directing a project retains board control when delegated management limits can no longer be met. Success requires: A documented board decision approves revised tolerances, changes direction or stops the work. Repeating track exception decisions and the approved replacement baseline helps prevent recurrence.
Incorrect Answers
B:Select and authorize proportionate corrective action within the project manager's delegated authority. Recovery actions improve the forecast without changing unauthorized baselines. A documented board decision approves revised tolerances, changes direction or stops the work.
C:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. A documented board decision approves revised tolerances, changes direction or stops the work.
D:Prepare a detailed next management stage plan grounded in actual results and current forecasts. Stage boundaries create informed authorization points instead of unconditional funding. A documented board decision approves revised tolerances, changes direction or stops the work.
Question 762
The project management team is troubleshooting this situation: a public library upgrade forecasts an unrecoverable stage delay but the project manager wants to approve a private workaround. Which check isolates the likely operating dependency? Select ONE answer.
- Review the benefits management approach and operational readiness obligations
- Inspect the exception cause, forecast effect on business case and available corrective options
- Review the authorized work package for capacity, dependencies and acceptance conditions
- Check evidence for the proposed costs and benefit owners against available options
Explanation
Correct Answer
B:The strongest first investigation is to inspect the exception cause, forecast effect on business case and available corrective options. Directing a project retains board control when delegated management limits can no longer be met. If that evidence confirms the issue, the team should present the exception and alternatives for an authorized project board decision. A subsequent acceptance check should confirm this result: A documented board decision approves revised tolerances, changes direction or stops the work. This check produces evidence before any broad configuration change, avoiding the risky proposal to allow the project manager to authorize an exception plan beyond their own tolerance.
Incorrect Answers
A:Review the benefits management approach and operational readiness obligations. Some benefits mature after project closure and must have real ownership. A documented board decision approves revised tolerances, changes direction or stops the work. The relevant investigation is: Inspect the exception cause, forecast effect on business case and available corrective options.
C:Review the authorized work package for capacity, dependencies and acceptance conditions. Team and project manager share an agreed deliverable commitment before work starts. A documented board decision approves revised tolerances, changes direction or stops the work. The relevant investigation is: Inspect the exception cause, forecast effect on business case and available corrective options.
D:Check evidence for the proposed costs and benefit owners against available options. The board can assess desirability, viability and achievability before authorizing the project. A documented board decision approves revised tolerances, changes direction or stops the work. The relevant investigation is: Inspect the exception cause, forecast effect on business case and available corrective options.
Question 763
An administrator claims the following problem is resolved: a public library upgrade forecasts an unrecoverable stage delay but the project manager wants to approve a private workaround. Which measured outcome confirms that claim? Select ONE answer.
- The board receives a coherent PID that establishes how the project will be managed and controlled
- The board decides whether continued investment remains appropriate with transparent tradeoffs
- A documented board decision approves revised tolerances, changes direction or stops the work
- Approved issue actions and escalations remain traceable to the current stage baseline
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to track exception decisions and the approved replacement baseline. The decisive acceptance evidence is this result: A documented board decision approves revised tolerances, changes direction or stops the work. Directing a project retains board control when delegated management limits can no longer be met. The operating team should diagnose it by checking whether it can inspect the exception cause, forecast effect on business case and available corrective options, then present the exception and alternatives for an authorized project board decision where justified.
Incorrect Answers
A:The board receives a coherent PID that establishes how the project will be managed and controlled. A documented board decision approves revised tolerances, changes direction or stops the work.
B:The board decides whether continued investment remains appropriate with transparent tradeoffs. A documented board decision approves revised tolerances, changes direction or stops the work.
D:Approved issue actions and escalations remain traceable to the current stage baseline. A documented board decision approves revised tolerances, changes direction or stops the work.
Question 764
After resolving the following issue, the operations team wants to prevent a recurrence: a public library upgrade forecasts an unrecoverable stage delay but the project manager wants to approve a private workaround. Which ongoing control is best? Select ONE answer.
- Follow up on significant lessons through organizational learning arrangements
- Validate the mandate and named owners when organizational priorities change
- Replan at stage boundaries using updated evidence
- Track exception decisions and the approved replacement baseline
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to present the exception and alternatives for an authorized project board decision and diagnostic evidence to inspect the exception cause, forecast effect on business case and available corrective options. Periodic testing should confirm this result: A documented board decision approves revised tolerances, changes direction or stops the work. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to track exception decisions and the approved replacement baseline. Directing a project retains board control when delegated management limits can no longer be met.
Incorrect Answers
A:Follow up on significant lessons through organizational learning arrangements. A final lessons report has actionable recommendations and accountable dissemination. A documented board decision approves revised tolerances, changes direction or stops the work. To avoid recurrence, track exception decisions and the approved replacement baseline.
B:Validate the mandate and named owners when organizational priorities change. The initiation decision is supported by a credible mandate and defined responsibilities. A documented board decision approves revised tolerances, changes direction or stops the work. To avoid recurrence, track exception decisions and the approved replacement baseline.
C:Replan at stage boundaries using updated evidence. The board can authorize staged delivery against a defensible project baseline. A documented board decision approves revised tolerances, changes direction or stops the work. To avoid recurrence, track exception decisions and the approved replacement baseline.
Question 765
A project manager is under pressure to address the following issue quickly: a public library upgrade forecasts an unrecoverable stage delay but the project manager wants to approve a private workaround. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Allow the project manager to authorize an exception plan beyond their own tolerance
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
- Confirm formal user acceptance against the project product description before recommending closure
- Compile an end-stage assessment with lessons, achieved products and unresolved matters
Explanation
Correct Answer
A:The unsafe shortcut is to allow the project manager to authorize an exception plan beyond their own tolerance. Directing a project retains board control when delegated management limits can no longer be met. The defensible response is instead to present the exception and alternatives for an authorized project board decision, using the diagnostic step to inspect the exception cause, forecast effect on business case and available corrective options before changing settings. Afterward, the team should confirm this result: A documented board decision approves revised tolerances, changes direction or stops the work. It must maintain the safeguard to track exception decisions and the approved replacement baseline.
Incorrect Answers
B:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. A documented board decision approves revised tolerances, changes direction or stops the work. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.
C:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. A documented board decision approves revised tolerances, changes direction or stops the work. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.
D:Compile an end-stage assessment with lessons, achieved products and unresolved matters. The board can see what worked, what failed and how the next stage will improve. A documented board decision approves revised tolerances, changes direction or stops the work. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.
Question 766
A project delivery team reports that a community energy scheme has a cost exception proposal with competing recovery and cancellation options. Which action directly addresses the issue? Select ONE answer.
- Collect team checkpoint information and update stage forecasts against approved tolerances
- Present the exception and alternatives for an authorized project board decision
- Submit the completed initiation documentation and initial stage plan for formal board authorization
- Execute the agreed work package and its quality activities under team management control
Explanation
Correct Answer
B:First, inspect the exception cause, forecast effect on business case and available corrective options. Present the exception and alternatives for an authorized project board decision. The reported operational condition is that a community energy scheme has a cost exception proposal with competing recovery and cancellation options. Directing a project retains board control when delegated management limits can no longer be met. Success requires: A documented board decision approves revised tolerances, changes direction or stops the work. Repeating track exception decisions and the approved replacement baseline helps prevent recurrence.
Incorrect Answers
A:Collect team checkpoint information and update stage forecasts against approved tolerances. The project manager knows stage health early enough to take in-tolerance corrective action. Directing a project retains board control when delegated management limits can no longer be met.
C:Submit the completed initiation documentation and initial stage plan for formal board authorization. The project board authorizes the project and first management stage on coherent evidence. Directing a project retains board control when delegated management limits can no longer be met.
D:Execute the agreed work package and its quality activities under team management control. The team produces quality-verified deliverables that can be formally handed over. Directing a project retains board control when delegated management limits can no longer be met.
Question 767
An administrator wants to identify the failure before making a change: a community energy scheme has a cost exception proposal with competing recovery and cancellation options. Which inspection is the most informative? Select ONE answer.
- Inspect remaining defects, contracts and operational obligations against handover acceptance
- Review the benefits management approach and operational readiness obligations
- Inspect the exception cause, forecast effect on business case and available corrective options
- Compare predicted final stage outcome with approved time, cost, scope and quality tolerances
Explanation
Correct Answer
C:The strongest first investigation is to inspect the exception cause, forecast effect on business case and available corrective options. Directing a project retains board control when delegated management limits can no longer be met. If that evidence confirms the issue, the team should present the exception and alternatives for an authorized project board decision. A subsequent acceptance check should confirm this result: A documented board decision approves revised tolerances, changes direction or stops the work. This check produces evidence before any broad configuration change, avoiding the risky proposal to allow the project manager to authorize an exception plan beyond their own tolerance. By contrast, the response tied to this evidence is: Inspect the exception cause, forecast effect on business case and available corrective options.
Incorrect Answers
A:Inspect remaining defects, contracts and operational obligations against handover acceptance. The board approves closure with clear transfer of every outstanding responsibility. Directing a project retains board control when delegated management limits can no longer be met. The relevant investigation is: Inspect the exception cause, forecast effect on business case and available corrective options.
B:Review the benefits management approach and operational readiness obligations. Some benefits mature after project closure and must have real ownership. Directing a project retains board control when delegated management limits can no longer be met. The relevant investigation is: Inspect the exception cause, forecast effect on business case and available corrective options.
D:Compare predicted final stage outcome with approved time, cost, scope and quality tolerances. Exception management is based on forecast tolerance breaches and decision rights. Directing a project retains board control when delegated management limits can no longer be met. The relevant investigation is: Inspect the exception cause, forecast effect on business case and available corrective options.
Question 768
After a controlled change, the team needs to resolve this report: a community energy scheme has a cost exception proposal with competing recovery and cancellation options. Which observable result would best establish success? Select ONE answer.
- The project board receives evidence that the final products meet agreed acceptance conditions
- The board formally authorizes closure with operational ownership and residual obligations identified
- The board approves closure with clear transfer of every outstanding responsibility
- A documented board decision approves revised tolerances, changes direction or stops the work
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to track exception decisions and the approved replacement baseline. The decisive acceptance evidence is this result: A documented board decision approves revised tolerances, changes direction or stops the work. Directing a project retains board control when delegated management limits can no longer be met. The operating team should diagnose it by checking whether it can inspect the exception cause, forecast effect on business case and available corrective options, then present the exception and alternatives for an authorized project board decision where justified. By contrast, the response tied to this evidence is: A documented board decision approves revised tolerances, changes direction or stops the work.
Incorrect Answers
A:The project board receives evidence that the final products meet agreed acceptance conditions. Evidence of the products delivered, not simply a completed activity list. Directing a project retains board control when delegated management limits can no longer be met. Success in this case requires: A documented board decision approves revised tolerances, changes direction or stops the work.
B:The board formally authorizes closure with operational ownership and residual obligations identified. Project closure is a governance decision informed by benefits and operational readiness. Directing a project retains board control when delegated management limits can no longer be met. Success in this case requires: A documented board decision approves revised tolerances, changes direction or stops the work.
C:The board approves closure with clear transfer of every outstanding responsibility. Directing a project retains board control when delegated management limits can no longer be met. Success in this case requires: A documented board decision approves revised tolerances, changes direction or stops the work.
Question 769
A project assurance reviewer sees a pattern in this report: a community energy scheme has a cost exception proposal with competing recovery and cancellation options. Which recurring safeguard should remain in force? Select ONE answer.
- Track exception decisions and the approved replacement baseline
- Reconsider delivery assumptions if early supplier or technical evidence changes
- Review management approaches after substantial changes or lessons
- Follow up on significant lessons through organizational learning arrangements
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to present the exception and alternatives for an authorized project board decision and diagnostic evidence to inspect the exception cause, forecast effect on business case and available corrective options. Periodic testing should confirm this result: A documented board decision approves revised tolerances, changes direction or stops the work. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to track exception decisions and the approved replacement baseline. Directing a project retains board control when delegated management limits can no longer be met. By contrast, the response tied to this evidence is: Track exception decisions and the approved replacement baseline.
Incorrect Answers
B:Reconsider delivery assumptions if early supplier or technical evidence changes. An early approach decision should be informed rather than prematurely irreversible. Directing a project retains board control when delegated management limits can no longer be met. To avoid recurrence, track exception decisions and the approved replacement baseline.
C:Review management approaches after substantial changes or lessons. Coordinated project controls must be established before distributed delivery begins. Directing a project retains board control when delegated management limits can no longer be met. To avoid recurrence, track exception decisions and the approved replacement baseline.
D:Follow up on significant lessons through organizational learning arrangements. A final lessons report has actionable recommendations and accountable dissemination. Directing a project retains board control when delegated management limits can no longer be met. To avoid recurrence, track exception decisions and the approved replacement baseline.
Question 770
A team wants to simplify its response to this situation: a community energy scheme has a cost exception proposal with competing recovery and cancellation options. Which shortcut is the LEAST defensible? Select ONE answer.
- Record residual issues, ownership, due dates and follow-on recommendations before closing
- Allow the project manager to authorize an exception plan beyond their own tolerance
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Have the project board assess the project brief and authorize a bounded initiation stage
Explanation
Correct Answer
B:The unsafe shortcut is to allow the project manager to authorize an exception plan beyond their own tolerance. Directing a project retains board control when delegated management limits can no longer be met. The defensible response is instead to present the exception and alternatives for an authorized project board decision, using the diagnostic step to inspect the exception cause, forecast effect on business case and available corrective options before changing settings. Afterward, the team should confirm this result: A documented board decision approves revised tolerances, changes direction or stops the work. It must maintain the safeguard to track exception decisions and the approved replacement baseline. By contrast, the response tied to this evidence is: Allow the project manager to authorize an exception plan beyond their own tolerance.
Incorrect Answers
A:Record residual issues, ownership, due dates and follow-on recommendations before closing. The board approves closure with clear transfer of every outstanding responsibility. Directing a project retains board control when delegated management limits can no longer be met. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.
C:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. Directing a project retains board control when delegated management limits can no longer be met. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.
D:Have the project board assess the project brief and authorize a bounded initiation stage. Initiation expenditure is explicitly authorized without pre-approving the entire project. Directing a project retains board control when delegated management limits can no longer be met. The shortcut most directly implicated here is: Allow the project manager to authorize an exception plan beyond their own tolerance.