PRINCE2 PRINCE2 7 Practitioner Practice Test 76
Question 750
For this project-management problem, the team is comparing possible shortcuts: a charitable logistics redesign has an outline business case but no decision on whether detailed planning is worth funding. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
- Assume a manager's verbal enthusiasm authorizes both initiation and full project delivery
- Compile an end-stage assessment with lessons, achieved products and unresolved matters
- Confirm formal user acceptance against the project product description before recommending closure
Explanation
Correct Answer
B:The unsafe shortcut is to assume a manager's verbal enthusiasm authorizes both initiation and full project delivery. The board controls the step from plausible idea to detailed project definition. The defensible response is instead to have the project board assess the project brief and authorize a bounded initiation stage, using the diagnostic step to review outline justification, initial risk and readiness of named roles before changing settings. Afterward, the team should confirm this result: Initiation expenditure is explicitly authorized without pre-approving the entire project. It must maintain the safeguard to track the initiation decision and its conditions through the initiation stage. By contrast, the response tied to this evidence is: Assume a manager's verbal enthusiasm authorizes both initiation and full project delivery.
Incorrect Answers
A:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. Initiation expenditure is explicitly authorized without pre-approving the entire project. The shortcut most directly implicated here is: Assume a manager's verbal enthusiasm authorizes both initiation and full project delivery.
C:Compile an end-stage assessment with lessons, achieved products and unresolved matters. The board can see what worked, what failed and how the next stage will improve. Initiation expenditure is explicitly authorized without pre-approving the entire project. The shortcut most directly implicated here is: Assume a manager's verbal enthusiasm authorizes both initiation and full project delivery.
D:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. Initiation expenditure is explicitly authorized without pre-approving the entire project. The shortcut most directly implicated here is: Assume a manager's verbal enthusiasm authorizes both initiation and full project delivery.
Question 751
A project board needs to manage this condition: a telecom project finishes its PID but the delivery team begins execution before board approval. Which administrative action best resolves the specific control gap? Select ONE answer.
- Collect team checkpoint information and update stage forecasts against approved tolerances
- Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure
- Submit the completed initiation documentation and initial stage plan for formal board authorization
- Execute the agreed work package and its quality activities under team management control
Explanation
Correct Answer
C:First, compare the PID, business case, project plan and proposed tolerances with the project brief. Submit the completed initiation documentation and initial stage plan for formal board authorization. Only the appropriate authority should commit the project after initiation clarifies its viability. Success means the project board authorizes the project and first management stage on coherent evidence. Repeating retain approval conditions and monitor authorized tolerances throughout delivery helps prevent recurrence.
Incorrect Answers
A:Collect team checkpoint information and update stage forecasts against approved tolerances. The project manager knows stage health early enough to take in-tolerance corrective action. The project board authorizes the project and first management stage on coherent evidence.
B:Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. Project closure is a governance decision informed by benefits and operational readiness. The project board authorizes the project and first management stage on coherent evidence.
D:Execute the agreed work package and its quality activities under team management control. The team produces quality-verified deliverables that can be formally handed over. The project board authorizes the project and first management stage on coherent evidence.
Question 752
An operations team is unsure why this occurred: a telecom project finishes its PID but the delivery team begins execution before board approval. Which targeted diagnostic step would produce the most relevant evidence? Select ONE answer.
- Inspect the exception cause, forecast effect on business case and available corrective options
- Inspect exception causes, feasible recovery products and the board's authorization conditions
- Compare team reports, accepted products and remaining dependencies with the stage plan
- Compare the PID, business case, project plan and proposed tolerances with the project brief
Explanation
Correct Answer
D:The strongest first investigation is to compare the PID, business case, project plan and proposed tolerances with the project brief. Only the appropriate authority should commit the project after initiation clarifies its viability. If that evidence confirms the issue, the team should submit the completed initiation documentation and initial stage plan for formal board authorization. A subsequent acceptance check should confirm this result: The project board authorizes the project and first management stage on coherent evidence. This check produces evidence before any broad configuration change, avoiding the risky proposal to treat completion of planning documents as automatic permission to deliver.
Incorrect Answers
A:Inspect the exception cause, forecast effect on business case and available corrective options. A documented board decision approves revised tolerances, changes direction or stops the work. The project board authorizes the project and first management stage on coherent evidence. The relevant investigation is: Compare the PID, business case, project plan and proposed tolerances with the project brief.
B:Inspect exception causes, feasible recovery products and the board's authorization conditions. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The project board authorizes the project and first management stage on coherent evidence. The relevant investigation is: Compare the PID, business case, project plan and proposed tolerances with the project brief.
C:Compare team reports, accepted products and remaining dependencies with the stage plan. The project manager knows stage health early enough to take in-tolerance corrective action. The project board authorizes the project and first management stage on coherent evidence. The relevant investigation is: Compare the PID, business case, project plan and proposed tolerances with the project brief.
Question 753
The senior user wants proof that this problem is resolved: a telecom project finishes its PID but the delivery team begins execution before board approval. Which end-to-end verification is most useful? Select ONE answer.
- The project board authorizes the project and first management stage on coherent evidence
- Teams follow documented methods that produce evidence for board oversight
- The team manager accepts a clear scope and reports against defined products and tolerances
- The receiving authority acknowledges accepted products and remaining obligations
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to retain approval conditions and monitor authorized tolerances throughout delivery. The decisive acceptance evidence is this result: The project board authorizes the project and first management stage on coherent evidence. Only the appropriate authority should commit the project after initiation clarifies its viability. The operating team should diagnose it by checking whether it can compare the PID, business case, project plan and proposed tolerances with the project brief, then submit the completed initiation documentation and initial stage plan for formal board authorization where justified.
Incorrect Answers
B:Teams follow documented methods that produce evidence for board oversight. Coordinated project controls must be established before distributed delivery begins. The project board authorizes the project and first management stage on coherent evidence.
C:The team manager accepts a clear scope and reports against defined products and tolerances. The project board authorizes the project and first management stage on coherent evidence.
D:The receiving authority acknowledges accepted products and remaining obligations. The project board authorizes the project and first management stage on coherent evidence.
Question 754
An incident has been closed after the team addressed this condition: a telecom project finishes its PID but the delivery team begins execution before board approval. Which follow-up control is most effective? Select ONE answer.
- Replan at stage boundaries using updated evidence
- Retain approval conditions and monitor authorized tolerances throughout delivery
- Review progress and forecasts at planned control intervals
- Monitor corrective-action effects on cost, quality and dependencies
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to submit the completed initiation documentation and initial stage plan for formal board authorization and diagnostic evidence to compare the PID, business case, project plan and proposed tolerances with the project brief. Periodic testing should confirm this result: The project board authorizes the project and first management stage on coherent evidence. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to retain approval conditions and monitor authorized tolerances throughout delivery. Only the appropriate authority should commit the project after initiation clarifies its viability.
Incorrect Answers
A:Replan at stage boundaries using updated evidence. The board can authorize staged delivery against a defensible project baseline. The project board authorizes the project and first management stage on coherent evidence. To avoid recurrence, retain approval conditions and monitor authorized tolerances throughout delivery.
C:Review progress and forecasts at planned control intervals. The project manager knows stage health early enough to take in-tolerance corrective action. The project board authorizes the project and first management stage on coherent evidence. To avoid recurrence, retain approval conditions and monitor authorized tolerances throughout delivery.
D:Monitor corrective-action effects on cost, quality and dependencies. Recovery actions improve the forecast without changing unauthorized baselines. The project board authorizes the project and first management stage on coherent evidence. To avoid recurrence, retain approval conditions and monitor authorized tolerances throughout delivery.
Question 755
For this project-management problem, the team is comparing possible shortcuts: a telecom project finishes its PID but the delivery team begins execution before board approval. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions
- Present the exception and alternatives for an authorized project board decision
- Treat completion of planning documents as automatic permission to deliver
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
Explanation
Correct Answer
C:The unsafe shortcut is to treat completion of planning documents as automatic permission to deliver. Only the appropriate authority should commit the project after initiation clarifies its viability. The defensible response is instead to submit the completed initiation documentation and initial stage plan for formal board authorization, using the diagnostic step to compare the PID, business case, project plan and proposed tolerances with the project brief before changing settings. Afterward, the team should confirm this result: The project board authorizes the project and first management stage on coherent evidence. It must maintain the safeguard to retain approval conditions and monitor authorized tolerances throughout delivery.
Incorrect Answers
A:Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. The board can authorize staged delivery against a defensible project baseline. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.
B:Present the exception and alternatives for an authorized project board decision. A documented board decision approves revised tolerances, changes direction or stops the work. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.
D:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.
Question 756
During a PRINCE2 management-stage review, the team encounters this situation: a water treatment replacement has a validated business case but no signed stage plan or clear project-level tolerances. What is the most appropriate controlled response? Select ONE answer.
- Confirm formal user acceptance against the project product description before recommending closure
- Use prior experience to tailor preliminary roles and startup controls before initiating
- Submit tested products with required handover evidence and obtain authorized acceptance
- Submit the completed initiation documentation and initial stage plan for formal board authorization
Explanation
Correct Answer
D:First, compare the PID, business case, project plan and proposed tolerances with the project brief. Submit the completed initiation documentation and initial stage plan for formal board authorization. Only the appropriate authority should commit the project after initiation clarifies its viability. Success means the project board authorizes the project and first management stage on coherent evidence. Repeating retain approval conditions and monitor authorized tolerances throughout delivery helps prevent recurrence. By contrast, the response tied to this evidence is: Submit the completed initiation documentation and initial stage plan for formal board authorization.
Incorrect Answers
A:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The project board authorizes the project and first management stage on coherent evidence.
B:Use prior experience to tailor preliminary roles and startup controls before initiating. The start-up documentation demonstrates applied learning and workable responsibilities. The project board authorizes the project and first management stage on coherent evidence.
C:Submit tested products with required handover evidence and obtain authorized acceptance. The receiving authority acknowledges accepted products and remaining obligations. The project board authorizes the project and first management stage on coherent evidence.
Question 757
The project management team is troubleshooting this situation: a water treatment replacement has a validated business case but no signed stage plan or clear project-level tolerances. Which check isolates the likely operating dependency? Select ONE answer.
- Compare the PID, business case, project plan and proposed tolerances with the project brief
- Compare delivery alternatives against expected products, capabilities, constraints and risks
- Compare completed products and test evidence with the package's acceptance criteria
- Compare requested work with the approved stage plan and product descriptions
Explanation
Correct Answer
A:The strongest first investigation is to compare the PID, business case, project plan and proposed tolerances with the project brief. Only the appropriate authority should commit the project after initiation clarifies its viability. If that evidence confirms the issue, the team should submit the completed initiation documentation and initial stage plan for formal board authorization. A subsequent acceptance check should confirm this result: The project board authorizes the project and first management stage on coherent evidence. This check produces evidence before any broad configuration change, avoiding the risky proposal to treat completion of planning documents as automatic permission to deliver. By contrast, the response tied to this evidence is: Compare the PID, business case, project plan and proposed tolerances with the project brief.
Incorrect Answers
B:Compare delivery alternatives against expected products, capabilities, constraints and risks. An early approach decision should be informed rather than prematurely irreversible. The project board authorizes the project and first management stage on coherent evidence. The relevant investigation is: Compare the PID, business case, project plan and proposed tolerances with the project brief.
C:Compare completed products and test evidence with the package's acceptance criteria. The team produces quality-verified deliverables that can be formally handed over. The project board authorizes the project and first management stage on coherent evidence. The relevant investigation is: Compare the PID, business case, project plan and proposed tolerances with the project brief.
D:Compare requested work with the approved stage plan and product descriptions. The team manager accepts a clear scope and reports against defined products and tolerances. The project board authorizes the project and first management stage on coherent evidence. The relevant investigation is: Compare the PID, business case, project plan and proposed tolerances with the project brief.
Question 758
An administrator claims the following problem is resolved: a water treatment replacement has a validated business case but no signed stage plan or clear project-level tolerances. Which measured outcome confirms that claim? Select ONE answer.
- Initiation expenditure is explicitly authorized without pre-approving the entire project
- The project board authorizes the project and first management stage on coherent evidence
- The team manager accepts a clear scope and reports against defined products and tolerances
- The team produces quality-verified deliverables that can be formally handed over
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to retain approval conditions and monitor authorized tolerances throughout delivery. The decisive acceptance evidence is this result: The project board authorizes the project and first management stage on coherent evidence. Only the appropriate authority should commit the project after initiation clarifies its viability. The operating team should diagnose it by checking whether it can compare the PID, business case, project plan and proposed tolerances with the project brief, then submit the completed initiation documentation and initial stage plan for formal board authorization where justified. By contrast, the response tied to this evidence is: The project board authorizes the project and first management stage on coherent evidence.
Incorrect Answers
A:Initiation expenditure is explicitly authorized without pre-approving the entire project. The project board authorizes the project and first management stage on coherent evidence.
C:The team manager accepts a clear scope and reports against defined products and tolerances. The project board authorizes the project and first management stage on coherent evidence. The operating team should diagnose it by checking whether it can compare the PID, business case, project plan and proposed tolerances with the project brief, then submit the completed initiation documentation and initial stage plan for formal board authorization where justified.
D:The team produces quality-verified deliverables that can be formally handed over. The project board authorizes the project and first management stage on coherent evidence.
Question 759
After resolving the following issue, the operations team wants to prevent a recurrence: a water treatment replacement has a validated business case but no signed stage plan or clear project-level tolerances. Which ongoing control is best? Select ONE answer.
- Refine scope and justification as discovery improves the evidence base
- Follow up on significant lessons through organizational learning arrangements
- Retain approval conditions and monitor authorized tolerances throughout delivery
- Track transferred actions in operational governance after project closure
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to submit the completed initiation documentation and initial stage plan for formal board authorization and diagnostic evidence to compare the PID, business case, project plan and proposed tolerances with the project brief. Periodic testing should confirm this result: The project board authorizes the project and first management stage on coherent evidence. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to retain approval conditions and monitor authorized tolerances throughout delivery. Only the appropriate authority should commit the project after initiation clarifies its viability. By contrast, the response tied to this evidence is: Retain approval conditions and monitor authorized tolerances throughout delivery.
Incorrect Answers
A:Refine scope and justification as discovery improves the evidence base. The board can approve or reject initiation on a coherent brief with clear assumptions. The project board authorizes the project and first management stage on coherent evidence. To avoid recurrence, retain approval conditions and monitor authorized tolerances throughout delivery.
B:Follow up on significant lessons through organizational learning arrangements. A final lessons report has actionable recommendations and accountable dissemination. The project board authorizes the project and first management stage on coherent evidence. To avoid recurrence, retain approval conditions and monitor authorized tolerances throughout delivery.
D:Track transferred actions in operational governance after project closure. The board approves closure with clear transfer of every outstanding responsibility. The project board authorizes the project and first management stage on coherent evidence. To avoid recurrence, retain approval conditions and monitor authorized tolerances throughout delivery.
Question 760
A project manager is under pressure to address the following issue quickly: a water treatment replacement has a validated business case but no signed stage plan or clear project-level tolerances. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Select and authorize proportionate corrective action within the project manager's delegated authority
- Collect team checkpoint information and update stage forecasts against approved tolerances
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
- Treat completion of planning documents as automatic permission to deliver
Explanation
Correct Answer
D:The unsafe shortcut is to treat completion of planning documents as automatic permission to deliver. Only the appropriate authority should commit the project after initiation clarifies its viability. The defensible response is instead to submit the completed initiation documentation and initial stage plan for formal board authorization, using the diagnostic step to compare the PID, business case, project plan and proposed tolerances with the project brief before changing settings. Afterward, the team should confirm this result: The project board authorizes the project and first management stage on coherent evidence. It must maintain the safeguard to retain approval conditions and monitor authorized tolerances throughout delivery. By contrast, the response tied to this evidence is: Treat completion of planning documents as automatic permission to deliver.
Incorrect Answers
A:Select and authorize proportionate corrective action within the project manager's delegated authority. Recovery actions improve the forecast without changing unauthorized baselines. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.
B:Collect team checkpoint information and update stage forecasts against approved tolerances. The project manager knows stage health early enough to take in-tolerance corrective action. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.
C:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. The project board authorizes the project and first management stage on coherent evidence. The shortcut most directly implicated here is: Treat completion of planning documents as automatic permission to deliver.