PRINCE2 PRINCE2 7 Practitioner Practice Test 82
Question 810
A project manager is under pressure to address the following issue quickly: a regional transport initiative changes sponsors mid-initiation and leaves board authority undocumented. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
- Let suppliers self-appoint user acceptance authorities to accelerate startup
- Authorize a work package with products, acceptance, reporting and agreed constraints
- Submit tested products with required handover evidence and obtain authorized acceptance
Explanation
Correct Answer
B:The unsafe shortcut is to let suppliers self-appoint user acceptance authorities to accelerate startup. The initiation stage should resolve accountability before work expands. The defensible response is instead to agree project roles, reporting relationships, assurance and delegations in initiation documents, using the diagnostic step to compare decision rights and role coverage with business, user and supplier interests before changing settings. Afterward, the team should confirm this result: A working board and delivery organization are documented with accountable decisions and checks. It must maintain the safeguard to reconfirm role assignments when partners and project governance change. By contrast, the response tied to this evidence is: Let suppliers self-appoint user acceptance authorities to accelerate startup.
Incorrect Answers
A:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. A working board and delivery organization are documented with accountable decisions and checks. The shortcut most directly implicated here is: Let suppliers self-appoint user acceptance authorities to accelerate startup.
C:Authorize a work package with products, acceptance, reporting and agreed constraints. The team manager accepts a clear scope and reports against defined products and tolerances. A working board and delivery organization are documented with accountable decisions and checks. The shortcut most directly implicated here is: Let suppliers self-appoint user acceptance authorities to accelerate startup.
D:Submit tested products with required handover evidence and obtain authorized acceptance. The receiving authority acknowledges accepted products and remaining obligations. A working board and delivery organization are documented with accountable decisions and checks. The shortcut most directly implicated here is: Let suppliers self-appoint user acceptance authorities to accelerate startup.
Question 811
During a PRINCE2 management-stage review, the team encounters this situation: a housing renovation proposal contains a final deadline but no product breakdown or stage boundaries. What is the most appropriate controlled response? Select ONE answer.
- Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
- Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
Explanation
Correct Answer
C:First, inspect planned product dependencies, resource commitments and forecast tolerances. Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. Project planning combines scope, time, cost, quality and control assumptions. Success means the board can authorize staged delivery against a defensible project baseline. Repeating replan at stage boundaries using updated evidence helps prevent recurrence.
Incorrect Answers
A:Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. Project closure is a governance decision informed by benefits and operational readiness. The board can authorize staged delivery against a defensible project baseline.
B:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The board can authorize staged delivery against a defensible project baseline.
D:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The board can authorize staged delivery against a defensible project baseline.
Question 812
The project management team is troubleshooting this situation: a housing renovation proposal contains a final deadline but no product breakdown or stage boundaries. Which check isolates the likely operating dependency? Select ONE answer.
- Compare delivery evidence and unresolved findings with the agreed work package description
- Compare issue effects on product descriptions, stage forecasts and decision limits
- Compare preliminary user objectives, constraints, risks and known delivery options
- Inspect planned product dependencies, resource commitments and forecast tolerances
Explanation
Correct Answer
D:The strongest first investigation is to inspect planned product dependencies, resource commitments and forecast tolerances. Project planning combines scope, time, cost, quality and control assumptions. If that evidence confirms the issue, the team should create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. A subsequent acceptance check should confirm this result: The board can authorize staged delivery against a defensible project baseline. This check produces evidence before any broad configuration change, avoiding the risky proposal to treat a target launch date as a sufficient project plan.
Incorrect Answers
A:Compare delivery evidence and unresolved findings with the agreed work package description. The receiving authority acknowledges accepted products and remaining obligations. The board can authorize staged delivery against a defensible project baseline. The relevant investigation is: Inspect planned product dependencies, resource commitments and forecast tolerances.
B:Compare issue effects on product descriptions, stage forecasts and decision limits. Approved issue actions and escalations remain traceable to the current stage baseline. The board can authorize staged delivery against a defensible project baseline. The relevant investigation is: Inspect planned product dependencies, resource commitments and forecast tolerances.
C:Compare preliminary user objectives, constraints, risks and known delivery options. The board can approve or reject initiation on a coherent brief with clear assumptions. The board can authorize staged delivery against a defensible project baseline. The relevant investigation is: Inspect planned product dependencies, resource commitments and forecast tolerances.
Question 813
An administrator claims the following problem is resolved: a housing renovation proposal contains a final deadline but no product breakdown or stage boundaries. Which measured outcome confirms that claim? Select ONE answer.
- The board can authorize staged delivery against a defensible project baseline
- The team manager accepts a clear scope and reports against defined products and tolerances
- The board receives a credible next-stage plan with justified commitments and tolerances
- The board can see what worked, what failed and how the next stage will improve
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to replan at stage boundaries using updated evidence. The decisive acceptance evidence is this result: The board can authorize staged delivery against a defensible project baseline. Project planning combines scope, time, cost, quality and control assumptions. The operating team should diagnose it by checking whether it can inspect planned product dependencies, resource commitments and forecast tolerances, then create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions where justified.
Incorrect Answers
B:The team manager accepts a clear scope and reports against defined products and tolerances. The board can authorize staged delivery against a defensible project baseline.
C:The board receives a credible next-stage plan with justified commitments and tolerances. Stage boundaries create informed authorization points instead of unconditional funding. The board can authorize staged delivery against a defensible project baseline.
D:The board can see what worked, what failed and how the next stage will improve. The board can authorize staged delivery against a defensible project baseline.
Question 814
After resolving the following issue, the operations team wants to prevent a recurrence: a housing renovation proposal contains a final deadline but no product breakdown or stage boundaries. Which ongoing control is best? Select ONE answer.
- Reconsider delivery assumptions if early supplier or technical evidence changes
- Replan at stage boundaries using updated evidence
- Monitor recovery assumptions and report further predicted exceptions promptly
- Monitor package-level progress, defects and dependency risks during delivery
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions and diagnostic evidence to inspect planned product dependencies, resource commitments and forecast tolerances. Periodic testing should confirm this result: The board can authorize staged delivery against a defensible project baseline. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to replan at stage boundaries using updated evidence. Project planning combines scope, time, cost, quality and control assumptions.
Incorrect Answers
A:Reconsider delivery assumptions if early supplier or technical evidence changes. An early approach decision should be informed rather than prematurely irreversible. The board can authorize staged delivery against a defensible project baseline. To avoid recurrence, replan at stage boundaries using updated evidence.
C:Monitor recovery assumptions and report further predicted exceptions promptly. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The board can authorize staged delivery against a defensible project baseline. To avoid recurrence, replan at stage boundaries using updated evidence.
D:Monitor package-level progress, defects and dependency risks during delivery. The team produces quality-verified deliverables that can be formally handed over. The board can authorize staged delivery against a defensible project baseline. To avoid recurrence, replan at stage boundaries using updated evidence.
Question 815
A project manager is under pressure to address the following issue quickly: a housing renovation proposal contains a final deadline but no product breakdown or stage boundaries. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Treat a target launch date as a sufficient project plan
- Confirm formal user acceptance against the project product description before recommending closure
Explanation
Correct Answer
C:The unsafe shortcut is to treat a target launch date as a sufficient project plan. Project planning combines scope, time, cost, quality and control assumptions. The defensible response is instead to create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions, using the diagnostic step to inspect planned product dependencies, resource commitments and forecast tolerances before changing settings. Afterward, the team should confirm this result: The board can authorize staged delivery against a defensible project baseline. It must maintain the safeguard to replan at stage boundaries using updated evidence.
Incorrect Answers
A:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. The board can authorize staged delivery against a defensible project baseline. The shortcut most directly implicated here is: Treat a target launch date as a sufficient project plan.
B:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. The board can authorize staged delivery against a defensible project baseline. The shortcut most directly implicated here is: Treat a target launch date as a sufficient project plan.
D:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The board can authorize staged delivery against a defensible project baseline. The shortcut most directly implicated here is: Treat a target launch date as a sufficient project plan.
Question 816
A project delivery team reports that a national licensing project has work-package estimates but no credible top-level plan for benefits and funding. Which action directly addresses the issue? Select ONE answer.
- Compile an end-stage assessment with lessons, achieved products and unresolved matters
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
- Update business justification and project forecasts before recommending continuation
- Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions
Explanation
Correct Answer
D:First, inspect planned product dependencies, resource commitments and forecast tolerances. Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. The reported operational condition is that a national licensing project has work-package estimates but no credible top-level plan for benefits and funding. Project planning combines scope, time, cost, quality and control assumptions. Success means the board can authorize staged delivery against a defensible project baseline. Repeating replan at stage boundaries using updated evidence helps prevent recurrence.
Incorrect Answers
A:Compile an end-stage assessment with lessons, achieved products and unresolved matters. The board can see what worked, what failed and how the next stage will improve. Project planning combines scope, time, cost, quality and control assumptions.
B:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. Project planning combines scope, time, cost, quality and control assumptions.
C:Update business justification and project forecasts before recommending continuation. The board decides whether continued investment remains appropriate with transparent tradeoffs. Project planning combines scope, time, cost, quality and control assumptions.
Question 817
An administrator wants to identify the failure before making a change: a national licensing project has work-package estimates but no credible top-level plan for benefits and funding. Which inspection is the most informative? Select ONE answer.
- Inspect planned product dependencies, resource commitments and forecast tolerances
- Compare decision rights and role coverage with business, user and supplier interests
- Compare stage results with baselines, quality evidence and learning objectives
- Review outline justification, initial risk and readiness of named roles
Explanation
Correct Answer
A:The strongest first investigation is to inspect planned product dependencies, resource commitments and forecast tolerances. Project planning combines scope, time, cost, quality and control assumptions. If that evidence confirms the issue, the team should create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. A subsequent acceptance check should confirm this result: The board can authorize staged delivery against a defensible project baseline. This check produces evidence before any broad configuration change, avoiding the risky proposal to treat a target launch date as a sufficient project plan. By contrast, the response tied to this evidence is: Inspect planned product dependencies, resource commitments and forecast tolerances.
Incorrect Answers
B:Compare decision rights and role coverage with business, user and supplier interests. A working board and delivery organization are documented with accountable decisions and checks. Project planning combines scope, time, cost, quality and control assumptions. The relevant investigation is: Inspect planned product dependencies, resource commitments and forecast tolerances.
C:Compare stage results with baselines, quality evidence and learning objectives. The board can see what worked, what failed and how the next stage will improve. Project planning combines scope, time, cost, quality and control assumptions. The relevant investigation is: Inspect planned product dependencies, resource commitments and forecast tolerances.
D:Review outline justification, initial risk and readiness of named roles. Initiation expenditure is explicitly authorized without pre-approving the entire project. Project planning combines scope, time, cost, quality and control assumptions. The relevant investigation is: Inspect planned product dependencies, resource commitments and forecast tolerances.
Question 818
After a controlled change, the team needs to resolve this report: a national licensing project has work-package estimates but no credible top-level plan for benefits and funding. Which observable result would best establish success? Select ONE answer.
- The revised plan is explicitly approved with renewed tolerances and managed dependencies
- The board can authorize staged delivery against a defensible project baseline
- Teams follow documented methods that produce evidence for board oversight
- The board receives a credible next-stage plan with justified commitments and tolerances
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to replan at stage boundaries using updated evidence. The decisive acceptance evidence is this result: The board can authorize staged delivery against a defensible project baseline. Project planning combines scope, time, cost, quality and control assumptions. The operating team should diagnose it by checking whether it can inspect planned product dependencies, resource commitments and forecast tolerances, then create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions where justified. By contrast, the response tied to this evidence is: The board can authorize staged delivery against a defensible project baseline.
Incorrect Answers
A:The revised plan is explicitly approved with renewed tolerances and managed dependencies. Project planning combines scope, time, cost, quality and control assumptions. Success in this case requires: The board can authorize staged delivery against a defensible project baseline.
C:Teams follow documented methods that produce evidence for board oversight. Coordinated project controls must be established before distributed delivery begins. Project planning combines scope, time, cost, quality and control assumptions. Success in this case requires: The board can authorize staged delivery against a defensible project baseline.
D:The board receives a credible next-stage plan with justified commitments and tolerances. Stage boundaries create informed authorization points instead of unconditional funding. Project planning combines scope, time, cost, quality and control assumptions. Success in this case requires: The board can authorize staged delivery against a defensible project baseline.
Question 819
A project assurance reviewer sees a pattern in this report: a national licensing project has work-package estimates but no credible top-level plan for benefits and funding. Which recurring safeguard should remain in force? Select ONE answer.
- Track the initiation decision and its conditions through the initiation stage
- Monitor recovery assumptions and report further predicted exceptions promptly
- Replan at stage boundaries using updated evidence
- Replan successive stages using lessons and updated risk forecasts
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions and diagnostic evidence to inspect planned product dependencies, resource commitments and forecast tolerances. Periodic testing should confirm this result: The board can authorize staged delivery against a defensible project baseline. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to replan at stage boundaries using updated evidence. Project planning combines scope, time, cost, quality and control assumptions. By contrast, the response tied to this evidence is: Replan at stage boundaries using updated evidence.
Incorrect Answers
A:Track the initiation decision and its conditions through the initiation stage. Initiation expenditure is explicitly authorized without pre-approving the entire project. Project planning combines scope, time, cost, quality and control assumptions. To avoid recurrence, replan at stage boundaries using updated evidence.
B:Monitor recovery assumptions and report further predicted exceptions promptly. The revised plan is explicitly approved with renewed tolerances and managed dependencies. Project planning combines scope, time, cost, quality and control assumptions. To avoid recurrence, replan at stage boundaries using updated evidence.
D:Replan successive stages using lessons and updated risk forecasts. Stage boundaries create informed authorization points instead of unconditional funding. Project planning combines scope, time, cost, quality and control assumptions. To avoid recurrence, replan at stage boundaries using updated evidence.
Question 820
A team wants to simplify its response to this situation: a national licensing project has work-package estimates but no credible top-level plan for benefits and funding. Which shortcut is the LEAST defensible? Select ONE answer.
- Handover operational responsibilities and future benefit reviews to named accountable owners
- Provide timely checkpoint progress, issues and forecast updates to the project manager
- Execute the agreed work package and its quality activities under team management control
- Treat a target launch date as a sufficient project plan
Explanation
Correct Answer
D:The unsafe shortcut is to treat a target launch date as a sufficient project plan. Project planning combines scope, time, cost, quality and control assumptions. The defensible response is instead to create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions, using the diagnostic step to inspect planned product dependencies, resource commitments and forecast tolerances before changing settings. Afterward, the team should confirm this result: The board can authorize staged delivery against a defensible project baseline. It must maintain the safeguard to replan at stage boundaries using updated evidence. By contrast, the response tied to this evidence is: Treat a target launch date as a sufficient project plan.
Incorrect Answers
A:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. Project planning combines scope, time, cost, quality and control assumptions. The shortcut most directly implicated here is: Treat a target launch date as a sufficient project plan.
B:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. Project planning combines scope, time, cost, quality and control assumptions. The shortcut most directly implicated here is: Treat a target launch date as a sufficient project plan.
C:Execute the agreed work package and its quality activities under team management control. The team produces quality-verified deliverables that can be formally handed over. Project planning combines scope, time, cost, quality and control assumptions. The shortcut most directly implicated here is: Treat a target launch date as a sufficient project plan.