cert
cert-1
cert-2

Pass PMI CAPM Exam in First Attempt Guaranteed!

Get 100% Latest Exam Questions, Accurate & Verified Answers to Pass the Actual Exam!
30 Days Free Updates, Instant Download!

cert-5
cert-6
CAPM Exam - Verified By Experts
CAPM Premium Bundle
$29.98

CAPM Premium Bundle

$79.99
$109.97
  • Premium File 688 Questions & Answers. Last update: Nov 21, 2026
  • Training Course 123 Video Lectures
  • Study Guide 719 Pages
 
$109.97
$79.99
accept 19 downloads in last 7 days
block-screenshots
Purchase PMI CAPM Exam Training Products Individually
PMI CAPM Premium File
Premium File 688 Q&A
$76.99$69.99
PMI CAPM Video Training Course
Training Course 123 Lectures
$21.99 $19.99
PMI CAPM PDF Study Guide
Study Guide 719 Pages
$21.99 $19.99
PMI CAPM Practice Test 47

Question 460

For an original CAPM project delivery study scenario, consider: A repair program has BAC=800 EV=400 AC=500 cost units and wants a new estimate using the observed CPI for the remaining comparable work. Select TWO complementary steps: the targeted correction and its strongest prechange validation.

  1. Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks.
  2. Check: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
  3. Report BAC as the guaranteed final expenditure even when actual performance shows a sustained cost-efficiency problem.
  4. Change: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue.
  5. Check: Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining.

Explanation

Correct Answer

D:

Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs. Evidence: Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining.

E:

Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs. Required intervention: Forecast final cost using an appropriate earned-value assumption, such as EAC=BAC divided by CPI when current cost efficiency is expected to continue.

Incorrect Answers

A:

Change: Distinguish initiating authorization, planning baselines, executing work, monitoring and controlling deviations, and closing or handover tasks. Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs.

B:

Check: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs.

C:

Forecast assumptions must be explicit: BAC/CPI presumes observed cost efficiency continues, while alternate formulas apply when future performance differs.

Question 461

A CAPM project team analyst is reviewing this delivery scenario: A sponsor requests objective performance data but the team sends only verbal assurances and cannot locate the cost baseline or issue log. An unsafe shortcut would be: Replace all baselines and logs with a self-reported percent complete that no one can verify. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.

  1. Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports.
  2. Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified.
  3. Compute schedule variance as EV minus PV and interpret negative as behind the value baseline and positive as ahead in earned-value terms.
  4. Replace all baselines and logs with a self-reported percent complete that no one can verify.

Explanation

Correct Answer

A:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Incorrect Answers

B:

Identify the actual controlling path and available total float before deciding whether fast-tracking, crashing or no compression is justified. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

C:

This option addresses a different CAPM project management topic (Schedule variance EV versus PV) rather than the documented Predictive control artifacts and reporting decision.

D:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 462

A project delivery review finds: A sponsor requests objective performance data but the team sends only verbal assurances and cannot locate the cost baseline or issue log. The team proposes: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports. Which project management principle most strongly supports the proposed response? Select ONE best answer.

  1. Quality planning specifies how processes and deliverables meet requirements; control measurements demonstrate observed conformance to those requirements.
  2. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.
  3. In matrix environments authority is shared to varying degrees; project plans must account for functional ownership and explicit priority agreements.
  4. Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity.

Explanation

Correct Answer

B:

Demonstrable success requires: Reports and source controls reconcile at the reporting date, exposing variance, ownership and authorized changes without contradictory status. This principle explains the proposed project response, which is: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports.

Incorrect Answers

A:

Quality planning specifies how processes and deliverables meet requirements; control measurements demonstrate observed conformance to those requirements. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

C:

In matrix environments authority is shared to varying degrees; project plans must account for functional ownership and explicit priority agreements. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

D:

Earned-value cost variance compares credited work value to the actual cost of that performed work, not the planned value of future activity. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 463

The project team has not approved a broad project-plan change. Available evidence indicates: A sponsor requests objective performance data but the team sends only verbal assurances and cannot locate the cost baseline or issue log. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.

  1. Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions.
  2. Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control.
  3. Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
  4. Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion.

Explanation

Correct Answer

D:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Incorrect Answers

A:

Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

B:

Verify that requirements are sufficiently stable, mandatory approvals are known and schedule or contract constraints justify baseline control. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

C:

Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 464

A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A sponsor requests objective performance data but the team sends only verbal assurances and cannot locate the cost baseline or issue log. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.

  1. Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions.
  2. CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them.
  3. Reports and source controls reconcile at the reporting date, exposing variance, ownership and authorized changes without contradictory status.
  4. Product measurements and documented controls meet the agreed standard, and deviations have explicit corrective or acceptance decisions.

Explanation

Correct Answer

C:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence. The approved implementation step was: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports.

Incorrect Answers

A:

Every agreed deliverable maps to one accountable work package and detailed activity planning can follow without unapproved additions. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

B:

CPI and SPI match the inputs and the narrative distinguishes cost overrun from schedule advancement instead of combining them. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

D:

Product measurements and documented controls meet the agreed standard, and deviations have explicit corrective or acceptance decisions. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 465

An implementation sign-off request identifies the following problem: A sponsor requests objective performance data but the team sends only verbal assurances and cannot locate the cost baseline or issue log. Which paired project management action and verification should close the review? Select ONE best answer.

  1. Change: Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls. Verify: Compare planned test methods, sampling, calibration or audit evidence and actual failure handling against acceptance tolerances.
  2. Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Verify: Compare the scope statement against WBS coverage, work package descriptions and exclusions to detect omitted deliverables or duplicate branches.
  3. Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. Verify: Check EV earned through status and AC booked for the same work, then calculate the signed difference and variance narrative.
  4. Change: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports. Verify: Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion.

Explanation

Correct Answer

D:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Incorrect Answers

A:

Change: Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

B:

Change: Decompose approved scope into a deliverable-oriented WBS whose lowest work packages can be estimated, assigned and verified. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

C:

Change: Compute cost variance as EV minus AC, using comparable value and actual-cost units; negative means over budget for performed work. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 466

A CAPM project team analyst is reviewing this delivery scenario: A procurement-led rollout makes scope changes without updating its change log, risk records or schedule forecasts, leaving monthly status reports inconsistent. An unsafe shortcut would be: Replace all baselines and logs with a self-reported percent complete that no one can verify. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.

  1. Replace all baselines and logs with a self-reported percent complete that no one can verify.
  2. Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change.
  3. Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports.
  4. Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them.

Explanation

Correct Answer

C:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Incorrect Answers

A:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence. Use this instead: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports.

B:

Maintain a consistent integrated plan and update all impacted baselines, requirements and communications following an authorized change. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

D:

Define work packages as manageable units of deliverable scope and derive scheduled activities and milestones to complete them. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 467

A project delivery review finds: A procurement-led rollout makes scope changes without updating its change log, risk records or schedule forecasts, leaving monthly status reports inconsistent. The team proposes: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports. Which project management principle most strongly supports the proposed response? Select ONE best answer.

  1. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.
  2. Process groups describe types of management activity that can overlap and recur; they are not identical to sequential product development phases.
  3. The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work.
  4. Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension.

Explanation

Correct Answer

A:

Demonstrable success requires: Reports and source controls reconcile at the reporting date, exposing variance, ownership and authorized changes without contradictory status.

Incorrect Answers

B:

This option addresses a different CAPM project management topic (Predictive process groups and transitions) rather than the documented Predictive control artifacts and reporting decision.

C:

The WBS organizes all approved project scope by deliverables and supports a scope baseline; activities and calendar dates are planned from that work. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

D:

Cost efficiency and earned-value schedule performance can move in different directions; an index below one denotes unfavorable comparison for that dimension. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 468

The project team has not approved a broad project-plan change. Available evidence indicates: A procurement-led rollout makes scope changes without updating its change log, risk records or schedule forecasts, leaving monthly status reports inconsistent. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.

  1. Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence.
  2. Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions.
  3. Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks.
  4. Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion.

Explanation

Correct Answer

D:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Incorrect Answers

A:

Check WBS dictionary boundaries, work-package deliverables, ownership, activity sequencing and acceptance evidence. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

B:

Examine the organization chart, resource assignment, delegated project authority and the two managers' priority decisions. A procurement-led rollout makes scope changes without updating its change log, risk records or schedule forecasts, leaving monthly status reports inconsistent.

C:

Compare early and late dates, current critical-path activities, float remaining, technical dependencies and risk of overlapping tasks. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 469

A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A procurement-led rollout makes scope changes without updating its change log, risk records or schedule forecasts, leaving monthly status reports inconsistent. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.

  1. The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip.
  2. Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor.
  3. Compliance deliverables meet predefined criteria and unavoidable changes are assessed instead of introducing untraceable requirements drift.
  4. Reports and source controls reconcile at the reporting date, exposing variance, ownership and authorized changes without contradictory status.

Explanation

Correct Answer

D:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Incorrect Answers

A:

The planned sequence respects mandatory handoffs and its schedule can be recalculated when predecessor activities slip. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

B:

Intervention targets the actual completion constraint, and remaining float or compression risk is reported transparently to the sponsor. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

C:

Compliance deliverables meet predefined criteria and unavoidable changes are assessed instead of introducing untraceable requirements drift. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

Question 470

For an original CAPM project delivery study scenario, consider: A procurement-led rollout makes scope changes without updating its change log, risk records or schedule forecasts, leaving monthly status reports inconsistent. Select TWO complementary steps: the targeted correction and its strongest prechange validation.

  1. Change: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports.
  2. Replace all baselines and logs with a self-reported percent complete that no one can verify.
  3. Change: Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls.
  4. Check: Inspect artifact version, owner, status-date consistency, change approvals and reconciliation of progress to measurable work completion.
  5. Check: Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining.

Explanation

Correct Answer

A:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence. Acceptance: Reports and source controls reconcile at the reporting date, exposing variance, ownership and authorized changes without contradictory status.

D:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence. Required intervention: Keep integrated control artifacts current: approved baseline, change and issue logs, risk records, work performance measurements and forecast reports.

Incorrect Answers

B:

Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.

C:

Change: Plan prevention and verification methods, measurement thresholds and nonconformance responses, then execute the documented quality controls. A procurement-led rollout makes scope changes without updating its change log, risk records or schedule forecasts, leaving monthly status reports inconsistent.

E:

Check: Check baseline BAC, earned EV, actual AC, computed CPI and whether the proposed forecasting assumption fits the work remaining. Predictive monitoring depends on traceable baseline comparisons and controlled records; one status narrative cannot replace underlying evidence.