PRINCE2 PRINCE2 7 Practitioner Practice Test 96
Question 950
For this project-management problem, the team is comparing possible shortcuts: a school access-control pilot succeeds despite a novel operating method that the wider rollout has not documented. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Use prior experience to tailor preliminary roles and startup controls before initiating
- Declare success using the schedule alone and omit significant delivery lessons
- Establish the project initiation documentation with management approaches, plans and tolerances
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
Explanation
Correct Answer
B:The unsafe shortcut is to declare success using the schedule alone and omit significant delivery lessons. Stage assessments support better decisions in subsequent work. The defensible response is instead to compile an end-stage assessment with lessons, achieved products and unresolved matters, using the diagnostic step to compare stage results with baselines, quality evidence and learning objectives before changing settings. Afterward, the team should confirm this result: The board can see what worked, what failed and how the next stage will improve. It must maintain the safeguard to assign and verify actions arising from the end-stage lessons report. By contrast, the response tied to this evidence is: Declare success using the schedule alone and omit significant delivery lessons.
Incorrect Answers
A:Use prior experience to tailor preliminary roles and startup controls before initiating. The start-up documentation demonstrates applied learning and workable responsibilities. The board can see what worked, what failed and how the next stage will improve. The shortcut most directly implicated here is: Declare success using the schedule alone and omit significant delivery lessons.
C:Establish the project initiation documentation with management approaches, plans and tolerances. The board receives a coherent PID that establishes how the project will be managed and controlled. The board can see what worked, what failed and how the next stage will improve. The shortcut most directly implicated here is: Declare success using the schedule alone and omit significant delivery lessons.
D:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The board can see what worked, what failed and how the next stage will improve. The shortcut most directly implicated here is: Declare success using the schedule alone and omit significant delivery lessons.
Question 951
A project board needs to manage this condition: a public safety modernization project receives board direction to recover after forecast tolerance breach. Which administrative action best resolves the specific control gap? Select ONE answer.
- Submit tested products with required handover evidence and obtain authorized acceptance
- Compile an end-stage assessment with lessons, achieved products and unresolved matters
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
- Record residual issues, ownership, due dates and follow-on recommendations before closing
Explanation
Correct Answer
C:First, inspect exception causes, feasible recovery products and the board's authorization conditions. Prepare and seek approval of an exception plan that replaces the relevant affected plan. An exception plan restores controlled delivery after authorized deviation. Success means the revised plan is explicitly approved with renewed tolerances and managed dependencies. Repeating monitor recovery assumptions and report further predicted exceptions promptly helps prevent recurrence.
Incorrect Answers
A:Submit tested products with required handover evidence and obtain authorized acceptance. The receiving authority acknowledges accepted products and remaining obligations. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
B:Compile an end-stage assessment with lessons, achieved products and unresolved matters. The board can see what worked, what failed and how the next stage will improve. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
D:Record residual issues, ownership, due dates and follow-on recommendations before closing. The board approves closure with clear transfer of every outstanding responsibility. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
Question 952
An operations team is unsure why this occurred: a public safety modernization project receives board direction to recover after forecast tolerance breach. Which targeted diagnostic step would produce the most relevant evidence? Select ONE answer.
- Compare completed products and test evidence with the package's acceptance criteria
- Inspect the exception cause, forecast effect on business case and available corrective options
- Compare actual stage results and revised future benefits with the current business case
- Inspect exception causes, feasible recovery products and the board's authorization conditions
Explanation
Correct Answer
D:The strongest first investigation is to inspect exception causes, feasible recovery products and the board's authorization conditions. An exception plan restores controlled delivery after authorized deviation. If that evidence confirms the issue, the team should prepare and seek approval of an exception plan that replaces the relevant affected plan. A subsequent acceptance check should confirm this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. This check produces evidence before any broad configuration change, avoiding the risky proposal to treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
Incorrect Answers
A:Compare completed products and test evidence with the package's acceptance criteria. The team produces quality-verified deliverables that can be formally handed over. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The relevant investigation is: Inspect exception causes, feasible recovery products and the board's authorization conditions.
B:Inspect the exception cause, forecast effect on business case and available corrective options. A documented board decision approves revised tolerances, changes direction or stops the work. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The relevant investigation is: Inspect exception causes, feasible recovery products and the board's authorization conditions.
C:Compare actual stage results and revised future benefits with the current business case. The board decides whether continued investment remains appropriate with transparent tradeoffs. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The relevant investigation is: Inspect exception causes, feasible recovery products and the board's authorization conditions.
Question 953
The senior user wants proof that this problem is resolved: a public safety modernization project receives board direction to recover after forecast tolerance breach. Which end-to-end verification is most useful? Select ONE answer.
- The revised plan is explicitly approved with renewed tolerances and managed dependencies
- The board formally authorizes closure with operational ownership and residual obligations identified
- A working board and delivery organization are documented with accountable decisions and checks
- The team manager accepts a clear scope and reports against defined products and tolerances
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to monitor recovery assumptions and report further predicted exceptions promptly. The decisive acceptance evidence is this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. An exception plan restores controlled delivery after authorized deviation. The operating team should diagnose it by checking whether it can inspect exception causes, feasible recovery products and the board's authorization conditions, then prepare and seek approval of an exception plan that replaces the relevant affected plan where justified.
Incorrect Answers
B:The board formally authorizes closure with operational ownership and residual obligations identified. Project closure is a governance decision informed by benefits and operational readiness. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
C:A working board and delivery organization are documented with accountable decisions and checks. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
D:The team manager accepts a clear scope and reports against defined products and tolerances. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
Question 954
An incident has been closed after the team addressed this condition: a public safety modernization project receives board direction to recover after forecast tolerance breach. Which follow-up control is most effective? Select ONE answer.
- Reconsider delivery assumptions if early supplier or technical evidence changes
- Monitor recovery assumptions and report further predicted exceptions promptly
- Refresh tolerance forecasts as corrective actions or risk assumptions change
- Retain acceptance artifacts and residual obligations in the closure record
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to prepare and seek approval of an exception plan that replaces the relevant affected plan and diagnostic evidence to inspect exception causes, feasible recovery products and the board's authorization conditions. Periodic testing should confirm this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to monitor recovery assumptions and report further predicted exceptions promptly. An exception plan restores controlled delivery after authorized deviation.
Incorrect Answers
A:Reconsider delivery assumptions if early supplier or technical evidence changes. An early approach decision should be informed rather than prematurely irreversible. The revised plan is explicitly approved with renewed tolerances and managed dependencies. To avoid recurrence, monitor recovery assumptions and report further predicted exceptions promptly.
C:Refresh tolerance forecasts as corrective actions or risk assumptions change. Exception management is based on forecast tolerance breaches and decision rights. The revised plan is explicitly approved with renewed tolerances and managed dependencies. To avoid recurrence, monitor recovery assumptions and report further predicted exceptions promptly.
D:Retain acceptance artifacts and residual obligations in the closure record. Evidence of the products delivered, not simply a completed activity list. The revised plan is explicitly approved with renewed tolerances and managed dependencies. To avoid recurrence, monitor recovery assumptions and report further predicted exceptions promptly.
Question 955
For this project-management problem, the team is comparing possible shortcuts: a public safety modernization project receives board direction to recover after forecast tolerance breach. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Confirm formal user acceptance against the project product description before recommending closure
- Evaluate how the project could be delivered and document a credible approach for initiation
- Treat an unapproved recovery spreadsheet as a replacement for the governing baseline
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
Explanation
Correct Answer
C:The unsafe shortcut is to treat an unapproved recovery spreadsheet as a replacement for the governing baseline. An exception plan restores controlled delivery after authorized deviation. The defensible response is instead to prepare and seek approval of an exception plan that replaces the relevant affected plan, using the diagnostic step to inspect exception causes, feasible recovery products and the board's authorization conditions before changing settings. Afterward, the team should confirm this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. It must maintain the safeguard to monitor recovery assumptions and report further predicted exceptions promptly.
Incorrect Answers
A:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
B:Evaluate how the project could be delivered and document a credible approach for initiation. An early approach decision should be informed rather than prematurely irreversible. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
D:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
Question 956
During a PRINCE2 management-stage review, the team encounters this situation: a large museum upgrade must substitute a recovery stage because the current plan is no longer attainable. What is the most appropriate controlled response? Select ONE answer.
- Evaluate how the project could be delivered and document a credible approach for initiation
- Update business justification and project forecasts before recommending continuation
- Record residual issues, ownership, due dates and follow-on recommendations before closing
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
Explanation
Correct Answer
D:First, inspect exception causes, feasible recovery products and the board's authorization conditions. Prepare and seek approval of an exception plan that replaces the relevant affected plan. An exception plan restores controlled delivery after authorized deviation. Success means the revised plan is explicitly approved with renewed tolerances and managed dependencies. Repeating monitor recovery assumptions and report further predicted exceptions promptly helps prevent recurrence. By contrast, the response tied to this evidence is: Prepare and seek approval of an exception plan that replaces the relevant affected plan.
Incorrect Answers
A:Evaluate how the project could be delivered and document a credible approach for initiation. An early approach decision should be informed rather than prematurely irreversible. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
B:Update business justification and project forecasts before recommending continuation. The board decides whether continued investment remains appropriate with transparent tradeoffs. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
C:Record residual issues, ownership, due dates and follow-on recommendations before closing. The board approves closure with clear transfer of every outstanding responsibility. The revised plan is explicitly approved with renewed tolerances and managed dependencies. By contrast, the response tied to this evidence is: Prepare and seek approval of an exception plan that replaces the relevant affected plan.
Question 957
The project management team is troubleshooting this situation: a large museum upgrade must substitute a recovery stage because the current plan is no longer attainable. Which check isolates the likely operating dependency? Select ONE answer.
- Inspect exception causes, feasible recovery products and the board's authorization conditions
- Inspect outstanding criteria, quality evidence and authorized acceptance decisions
- Compare actual stage results and revised future benefits with the current business case
- Compare completed products and test evidence with the package's acceptance criteria
Explanation
Correct Answer
A:The strongest first investigation is to inspect exception causes, feasible recovery products and the board's authorization conditions. An exception plan restores controlled delivery after authorized deviation. If that evidence confirms the issue, the team should prepare and seek approval of an exception plan that replaces the relevant affected plan. A subsequent acceptance check should confirm this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. This check produces evidence before any broad configuration change, avoiding the risky proposal to treat an unapproved recovery spreadsheet as a replacement for the governing baseline. By contrast, the response tied to this evidence is: Inspect exception causes, feasible recovery products and the board's authorization conditions.
Incorrect Answers
B:Inspect outstanding criteria, quality evidence and authorized acceptance decisions. Evidence of the products delivered, not simply a completed activity list. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The relevant investigation is: Inspect exception causes, feasible recovery products and the board's authorization conditions.
C:Compare actual stage results and revised future benefits with the current business case. The board decides whether continued investment remains appropriate with transparent tradeoffs. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The relevant investigation is: Inspect exception causes, feasible recovery products and the board's authorization conditions. This check produces evidence before any broad configuration change, avoiding the risky proposal to treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
D:Compare completed products and test evidence with the package's acceptance criteria. The team produces quality-verified deliverables that can be formally handed over. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The relevant investigation is: Inspect exception causes, feasible recovery products and the board's authorization conditions. This check produces evidence before any broad configuration change, avoiding the risky proposal to treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
Question 958
An administrator claims the following problem is resolved: a large museum upgrade must substitute a recovery stage because the current plan is no longer attainable. Which measured outcome confirms that claim? Select ONE answer.
- The board can approve or reject initiation on a coherent brief with clear assumptions
- The revised plan is explicitly approved with renewed tolerances and managed dependencies
- A working board and delivery organization are documented with accountable decisions and checks
- A documented board decision approves revised tolerances, changes direction or stops the work
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to monitor recovery assumptions and report further predicted exceptions promptly. The decisive acceptance evidence is this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. An exception plan restores controlled delivery after authorized deviation. The operating team should diagnose it by checking whether it can inspect exception causes, feasible recovery products and the board's authorization conditions, then prepare and seek approval of an exception plan that replaces the relevant affected plan where justified. By contrast, the response tied to this evidence is: The revised plan is explicitly approved with renewed tolerances and managed dependencies.
Incorrect Answers
A:The board can approve or reject initiation on a coherent brief with clear assumptions. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
C:A working board and delivery organization are documented with accountable decisions and checks. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The operating team should diagnose it by checking whether it can inspect exception causes, feasible recovery products and the board's authorization conditions, then prepare and seek approval of an exception plan that replaces the relevant affected plan where justified.
D:A documented board decision approves revised tolerances, changes direction or stops the work. The revised plan is explicitly approved with renewed tolerances and managed dependencies.
Question 959
After resolving the following issue, the operations team wants to prevent a recurrence: a large museum upgrade must substitute a recovery stage because the current plan is no longer attainable. Which ongoing control is best? Select ONE answer.
- Use a consistent handover checklist for future work packages
- Replan successive stages using lessons and updated risk forecasts
- Monitor recovery assumptions and report further predicted exceptions promptly
- Retain approval conditions and monitor authorized tolerances throughout delivery
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to prepare and seek approval of an exception plan that replaces the relevant affected plan and diagnostic evidence to inspect exception causes, feasible recovery products and the board's authorization conditions. Periodic testing should confirm this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to monitor recovery assumptions and report further predicted exceptions promptly. An exception plan restores controlled delivery after authorized deviation. By contrast, the response tied to this evidence is: Monitor recovery assumptions and report further predicted exceptions promptly.
Incorrect Answers
A:Use a consistent handover checklist for future work packages. The receiving authority acknowledges accepted products and remaining obligations. The revised plan is explicitly approved with renewed tolerances and managed dependencies. To avoid recurrence, monitor recovery assumptions and report further predicted exceptions promptly.
B:Replan successive stages using lessons and updated risk forecasts. Stage boundaries create informed authorization points instead of unconditional funding. The revised plan is explicitly approved with renewed tolerances and managed dependencies. To avoid recurrence, monitor recovery assumptions and report further predicted exceptions promptly.
D:Retain approval conditions and monitor authorized tolerances throughout delivery. The project board authorizes the project and first management stage on coherent evidence. The revised plan is explicitly approved with renewed tolerances and managed dependencies. To avoid recurrence, monitor recovery assumptions and report further predicted exceptions promptly.
Question 960
A project manager is under pressure to address the following issue quickly: a large museum upgrade must substitute a recovery stage because the current plan is no longer attainable. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Define proportionate agreed approaches for risk, issues, quality, communications, change and project information
- Produce an exception report and escalate the forecast to the project board promptly
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Treat an unapproved recovery spreadsheet as a replacement for the governing baseline
Explanation
Correct Answer
D:The unsafe shortcut is to treat an unapproved recovery spreadsheet as a replacement for the governing baseline. An exception plan restores controlled delivery after authorized deviation. The defensible response is instead to prepare and seek approval of an exception plan that replaces the relevant affected plan, using the diagnostic step to inspect exception causes, feasible recovery products and the board's authorization conditions before changing settings. Afterward, the team should confirm this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. It must maintain the safeguard to monitor recovery assumptions and report further predicted exceptions promptly. By contrast, the response tied to this evidence is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
Incorrect Answers
A:Define proportionate agreed approaches for risk, issues, quality, communications, change and project information. Coordinated project controls must be established before distributed delivery begins. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
B:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
C:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.