PRINCE2 PRINCE2 7 Practitioner Practice Test 97
Question 960
A project manager is under pressure to address the following issue quickly: a large museum upgrade must substitute a recovery stage because the current plan is no longer attainable. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Define proportionate agreed approaches for risk, issues, quality, communications, change and project information
- Produce an exception report and escalate the forecast to the project board promptly
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Treat an unapproved recovery spreadsheet as a replacement for the governing baseline
Explanation
Correct Answer
D:The unsafe shortcut is to treat an unapproved recovery spreadsheet as a replacement for the governing baseline. An exception plan restores controlled delivery after authorized deviation. The defensible response is instead to prepare and seek approval of an exception plan that replaces the relevant affected plan, using the diagnostic step to inspect exception causes, feasible recovery products and the board's authorization conditions before changing settings. Afterward, the team should confirm this result: The revised plan is explicitly approved with renewed tolerances and managed dependencies. It must maintain the safeguard to monitor recovery assumptions and report further predicted exceptions promptly. By contrast, the response tied to this evidence is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
Incorrect Answers
A:Define proportionate agreed approaches for risk, issues, quality, communications, change and project information. Coordinated project controls must be established before distributed delivery begins. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
B:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
C:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The shortcut most directly implicated here is: Treat an unapproved recovery spreadsheet as a replacement for the governing baseline.
Question 961
During a PRINCE2 management-stage review, the team encounters this situation: a city permit service goes live before senior users approve its accessibility acceptance results. What is the most appropriate controlled response? Select ONE answer.
- Confirm formal user acceptance against the project product description before recommending closure
- Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions
- Submit tested products with required handover evidence and obtain authorized acceptance
- Provide timely checkpoint progress, issues and forecast updates to the project manager
Explanation
Correct Answer
A:First, inspect outstanding criteria, quality evidence and authorized acceptance decisions. Confirm formal user acceptance against the project product description before recommending closure. Project closure requires evidence of the products delivered, not simply a completed activity list. Success means the project board receives evidence that the final products meet agreed acceptance conditions. Repeating retain acceptance artifacts and residual obligations in the closure record helps prevent recurrence.
Incorrect Answers
B:Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. The board can authorize staged delivery against a defensible project baseline. Evidence of the products delivered, not simply a completed activity list.
C:Submit tested products with required handover evidence and obtain authorized acceptance. The receiving authority acknowledges accepted products and remaining obligations. Evidence of the products delivered, not simply a completed activity list.
D:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. Evidence of the products delivered, not simply a completed activity list.
Question 962
The project management team is troubleshooting this situation: a city permit service goes live before senior users approve its accessibility acceptance results. Which check isolates the likely operating dependency? Select ONE answer.
- Inspect remaining defects, contracts and operational obligations against handover acceptance
- Inspect outstanding criteria, quality evidence and authorized acceptance decisions
- Compare issue effects on product descriptions, stage forecasts and decision limits
- Inspect the agreed reporting cadence and quality/dependency evidence
Explanation
Correct Answer
B:The strongest first investigation is to inspect outstanding criteria, quality evidence and authorized acceptance decisions. Project closure requires evidence of the products delivered, not simply a completed activity list. If that evidence confirms the issue, the team should confirm formal user acceptance against the project product description before recommending closure. A subsequent acceptance check should confirm this result: The project board receives evidence that the final products meet agreed acceptance conditions. This check produces evidence before any broad configuration change, avoiding the risky proposal to close the project because the supplier says its final invoice is ready.
Incorrect Answers
A:Inspect remaining defects, contracts and operational obligations against handover acceptance. The board approves closure with clear transfer of every outstanding responsibility. Evidence of the products delivered, not simply a completed activity list. The relevant investigation is: Inspect outstanding criteria, quality evidence and authorized acceptance decisions.
C:Compare issue effects on product descriptions, stage forecasts and decision limits. Approved issue actions and escalations remain traceable to the current stage baseline. Evidence of the products delivered, not simply a completed activity list. The relevant investigation is: Inspect outstanding criteria, quality evidence and authorized acceptance decisions.
D:Inspect the agreed reporting cadence and quality/dependency evidence. Stage forecasts reflect actual work package progress and risks before failure. Evidence of the products delivered, not simply a completed activity list. The relevant investigation is: Inspect outstanding criteria, quality evidence and authorized acceptance decisions.
Question 963
An administrator claims the following problem is resolved: a city permit service goes live before senior users approve its accessibility acceptance results. Which measured outcome confirms that claim? Select ONE answer.
- Recovery actions improve the forecast without changing unauthorized baselines
- The board can assess desirability, viability and achievability before authorizing the project
- The project board receives evidence that the final products meet agreed acceptance conditions
- The project approach is justified and can support realistic initiation planning
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to retain acceptance artifacts and residual obligations in the closure record. The decisive acceptance evidence is this result: The project board receives evidence that the final products meet agreed acceptance conditions. Project closure requires evidence of the products delivered, not simply a completed activity list. The operating team should diagnose it by checking whether it can inspect outstanding criteria, quality evidence and authorized acceptance decisions, then confirm formal user acceptance against the project product description before recommending closure where justified.
Incorrect Answers
A:Recovery actions improve the forecast without changing unauthorized baselines. Evidence of the products delivered, not simply a completed activity list. Success in this case requires: The project board receives evidence that the final products meet agreed acceptance conditions.
B:The board can assess desirability, viability and achievability before authorizing the project. Evidence of the products delivered, not simply a completed activity list. Success in this case requires: The project board receives evidence that the final products meet agreed acceptance conditions.
D:The project approach is justified and can support realistic initiation planning. An early approach decision should be informed rather than prematurely irreversible. Evidence of the products delivered, not simply a completed activity list. Success in this case requires: The project board receives evidence that the final products meet agreed acceptance conditions.
Question 964
After resolving the following issue, the operations team wants to prevent a recurrence: a city permit service goes live before senior users approve its accessibility acceptance results. Which ongoing control is best? Select ONE answer.
- Review justification at future stage boundaries and material external changes
- Follow up on significant lessons through organizational learning arrangements
- Review progress and forecasts at planned control intervals
- Retain acceptance artifacts and residual obligations in the closure record
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to confirm formal user acceptance against the project product description before recommending closure and diagnostic evidence to inspect outstanding criteria, quality evidence and authorized acceptance decisions. Periodic testing should confirm this result: The project board receives evidence that the final products meet agreed acceptance conditions. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to retain acceptance artifacts and residual obligations in the closure record. Project closure requires evidence of the products delivered, not simply a completed activity list.
Incorrect Answers
A:Review justification at future stage boundaries and material external changes. The board decides whether continued investment remains appropriate with transparent tradeoffs. Evidence of the products delivered, not simply a completed activity list. To avoid recurrence, retain acceptance artifacts and residual obligations in the closure record.
B:Follow up on significant lessons through organizational learning arrangements. A final lessons report has actionable recommendations and accountable dissemination. Evidence of the products delivered, not simply a completed activity list. To avoid recurrence, retain acceptance artifacts and residual obligations in the closure record.
C:Review progress and forecasts at planned control intervals. The project manager knows stage health early enough to take in-tolerance corrective action. Evidence of the products delivered, not simply a completed activity list. To avoid recurrence, retain acceptance artifacts and residual obligations in the closure record.
Question 965
A project manager is under pressure to address the following issue quickly: a city permit service goes live before senior users approve its accessibility acceptance results. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Close the project because the supplier says its final invoice is ready
- Produce a proportionate project brief and outline business case to support initiation authorization
- Present the exception and alternatives for an authorized project board decision
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
Explanation
Correct Answer
A:The unsafe shortcut is to close the project because the supplier says its final invoice is ready. Project closure requires evidence of the products delivered, not simply a completed activity list. The defensible response is instead to confirm formal user acceptance against the project product description before recommending closure, using the diagnostic step to inspect outstanding criteria, quality evidence and authorized acceptance decisions before changing settings. Afterward, the team should confirm this result: The project board receives evidence that the final products meet agreed acceptance conditions. It must maintain the safeguard to retain acceptance artifacts and residual obligations in the closure record.
Incorrect Answers
B:Produce a proportionate project brief and outline business case to support initiation authorization. The board can approve or reject initiation on a coherent brief with clear assumptions. Evidence of the products delivered, not simply a completed activity list. The shortcut most directly implicated here is: Close the project because the supplier says its final invoice is ready.
C:Present the exception and alternatives for an authorized project board decision. A documented board decision approves revised tolerances, changes direction or stops the work. Evidence of the products delivered, not simply a completed activity list. The shortcut most directly implicated here is: Close the project because the supplier says its final invoice is ready.
D:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. Evidence of the products delivered, not simply a completed activity list. The shortcut most directly implicated here is: Close the project because the supplier says its final invoice is ready.
Question 966
A project delivery team reports that a hospital communications program finishes deliveries but its final product acceptance record is missing. Which action directly addresses the issue? Select ONE answer.
- Handover operational responsibilities and future benefit reviews to named accountable owners
- Confirm formal user acceptance against the project product description before recommending closure
- Prepare a detailed next management stage plan grounded in actual results and current forecasts
- Authorize a work package with products, acceptance, reporting and agreed constraints
Explanation
Correct Answer
B:First, inspect outstanding criteria, quality evidence and authorized acceptance decisions. Confirm formal user acceptance against the project product description before recommending closure. The reported operational condition is that a hospital communications program finishes deliveries but its final product acceptance record is missing. Project closure requires evidence of the products delivered, not simply a completed activity list. Success means the project board receives evidence that the final products meet agreed acceptance conditions. Repeating retain acceptance artifacts and residual obligations in the closure record helps prevent recurrence.
Incorrect Answers
A:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. Evidence of the products delivered, not simply a completed activity list.
C:Prepare a detailed next management stage plan grounded in actual results and current forecasts. Stage boundaries create informed authorization points instead of unconditional funding. Evidence of the products delivered, not simply a completed activity list.
D:Authorize a work package with products, acceptance, reporting and agreed constraints. The team manager accepts a clear scope and reports against defined products and tolerances. Evidence of the products delivered, not simply a completed activity list.
Question 967
An administrator wants to identify the failure before making a change: a hospital communications program finishes deliveries but its final product acceptance record is missing. Which inspection is the most informative? Select ONE answer.
- Inspect planned product dependencies, resource commitments and forecast tolerances
- Inspect the agreed reporting cadence and quality/dependency evidence
- Inspect outstanding criteria, quality evidence and authorized acceptance decisions
- Compare decision rights and role coverage with business, user and supplier interests
Explanation
Correct Answer
C:The strongest first investigation is to inspect outstanding criteria, quality evidence and authorized acceptance decisions. Project closure requires evidence of the products delivered, not simply a completed activity list. If that evidence confirms the issue, the team should confirm formal user acceptance against the project product description before recommending closure. A subsequent acceptance check should confirm this result: The project board receives evidence that the final products meet agreed acceptance conditions. This check produces evidence before any broad configuration change, avoiding the risky proposal to close the project because the supplier says its final invoice is ready. By contrast, the response tied to this evidence is: Inspect outstanding criteria, quality evidence and authorized acceptance decisions.
Incorrect Answers
A:Inspect planned product dependencies, resource commitments and forecast tolerances. The board can authorize staged delivery against a defensible project baseline. Evidence of the products delivered, not simply a completed activity list. The relevant investigation is: Inspect outstanding criteria, quality evidence and authorized acceptance decisions.
B:Inspect the agreed reporting cadence and quality/dependency evidence. Stage forecasts reflect actual work package progress and risks before failure. Evidence of the products delivered, not simply a completed activity list. The relevant investigation is: Inspect outstanding criteria, quality evidence and authorized acceptance decisions. This check produces evidence before any broad configuration change, avoiding the risky proposal to close the project because the supplier says its final invoice is ready.
D:Compare decision rights and role coverage with business, user and supplier interests. A working board and delivery organization are documented with accountable decisions and checks. Evidence of the products delivered, not simply a completed activity list. The relevant investigation is: Inspect outstanding criteria, quality evidence and authorized acceptance decisions.
Question 968
After a controlled change, the team needs to resolve this report: a hospital communications program finishes deliveries but its final product acceptance record is missing. Which observable result would best establish success? Select ONE answer.
- Teams follow documented methods that produce evidence for board oversight
- A final lessons report has actionable recommendations and accountable dissemination
- A working board and delivery organization are documented with accountable decisions and checks
- The project board receives evidence that the final products meet agreed acceptance conditions
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to retain acceptance artifacts and residual obligations in the closure record. The decisive acceptance evidence is this result: The project board receives evidence that the final products meet agreed acceptance conditions. Project closure requires evidence of the products delivered, not simply a completed activity list. The operating team should diagnose it by checking whether it can inspect outstanding criteria, quality evidence and authorized acceptance decisions, then confirm formal user acceptance against the project product description before recommending closure where justified. By contrast, the response tied to this evidence is: The project board receives evidence that the final products meet agreed acceptance conditions.
Incorrect Answers
A:Teams follow documented methods that produce evidence for board oversight. Coordinated project controls must be established before distributed delivery begins. Evidence of the products delivered, not simply a completed activity list. Success in this case requires: The project board receives evidence that the final products meet agreed acceptance conditions.
B:A final lessons report has actionable recommendations and accountable dissemination. Evidence of the products delivered, not simply a completed activity list. Success in this case requires: The project board receives evidence that the final products meet agreed acceptance conditions.
C:A working board and delivery organization are documented with accountable decisions and checks. Evidence of the products delivered, not simply a completed activity list. Success in this case requires: The project board receives evidence that the final products meet agreed acceptance conditions.
Question 969
A project assurance reviewer sees a pattern in this report: a hospital communications program finishes deliveries but its final product acceptance record is missing. Which recurring safeguard should remain in force? Select ONE answer.
- Retain acceptance artifacts and residual obligations in the closure record
- Replan at stage boundaries using updated evidence
- Follow up on significant lessons through organizational learning arrangements
- Reconsider delivery assumptions if early supplier or technical evidence changes
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to confirm formal user acceptance against the project product description before recommending closure and diagnostic evidence to inspect outstanding criteria, quality evidence and authorized acceptance decisions. Periodic testing should confirm this result: The project board receives evidence that the final products meet agreed acceptance conditions. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to retain acceptance artifacts and residual obligations in the closure record. Project closure requires evidence of the products delivered, not simply a completed activity list. By contrast, the response tied to this evidence is: Retain acceptance artifacts and residual obligations in the closure record.
Incorrect Answers
B:Replan at stage boundaries using updated evidence. The board can authorize staged delivery against a defensible project baseline. Evidence of the products delivered, not simply a completed activity list. To avoid recurrence, retain acceptance artifacts and residual obligations in the closure record.
C:Follow up on significant lessons through organizational learning arrangements. A final lessons report has actionable recommendations and accountable dissemination. Evidence of the products delivered, not simply a completed activity list. To avoid recurrence, retain acceptance artifacts and residual obligations in the closure record. Periodic testing should confirm this result: The project board receives evidence that the final products meet agreed acceptance conditions.
D:Reconsider delivery assumptions if early supplier or technical evidence changes. An early approach decision should be informed rather than prematurely irreversible. Evidence of the products delivered, not simply a completed activity list. To avoid recurrence, retain acceptance artifacts and residual obligations in the closure record.
Question 970
A team wants to simplify its response to this situation: a hospital communications program finishes deliveries but its final product acceptance record is missing. Which shortcut is the LEAST defensible? Select ONE answer.
- Record and assess actual issues and authorize responses within delegated authority or escalate
- Close the project because the supplier says its final invoice is ready
- Provide timely checkpoint progress, issues and forecast updates to the project manager
- Handover operational responsibilities and future benefit reviews to named accountable owners
Explanation
Correct Answer
B:The unsafe shortcut is to close the project because the supplier says its final invoice is ready. Project closure requires evidence of the products delivered, not simply a completed activity list. The defensible response is instead to confirm formal user acceptance against the project product description before recommending closure, using the diagnostic step to inspect outstanding criteria, quality evidence and authorized acceptance decisions before changing settings. Afterward, the team should confirm this result: The project board receives evidence that the final products meet agreed acceptance conditions. It must maintain the safeguard to retain acceptance artifacts and residual obligations in the closure record. By contrast, the response tied to this evidence is: Close the project because the supplier says its final invoice is ready.
Incorrect Answers
A:Record and assess actual issues and authorize responses within delegated authority or escalate. Approved issue actions and escalations remain traceable to the current stage baseline. Evidence of the products delivered, not simply a completed activity list. The shortcut most directly implicated here is: Close the project because the supplier says its final invoice is ready.
C:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. Evidence of the products delivered, not simply a completed activity list. The shortcut most directly implicated here is: Close the project because the supplier says its final invoice is ready.
D:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. Evidence of the products delivered, not simply a completed activity list. The shortcut most directly implicated here is: Close the project because the supplier says its final invoice is ready.