PRINCE2 PRINCE2 7 Practitioner Practice Test 94
Question 930
The service owner is reviewing actions after this report: a regional transport infrastructure project seeks continued funding but has no approved next-stage deliverables. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Authorize a work package with products, acceptance, reporting and agreed constraints
- Start the next stage before its scope and resource baseline are authorized
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
- Submit tested products with required handover evidence and obtain authorized acceptance
Explanation
Correct Answer
B:The unsafe shortcut is to start the next stage before its scope and resource baseline are authorized. Stage boundaries create informed authorization points instead of unconditional funding. The defensible response is instead to prepare a detailed next management stage plan grounded in actual results and current forecasts, using the diagnostic step to review completed product evidence, outstanding issues and assumptions for the upcoming stage before changing settings. Afterward, the team should confirm this result: The board receives a credible next-stage plan with justified commitments and tolerances. It must maintain the safeguard to replan successive stages using lessons and updated risk forecasts. By contrast, the response tied to this evidence is: Start the next stage before its scope and resource baseline are authorized.
Incorrect Answers
A:Authorize a work package with products, acceptance, reporting and agreed constraints. The team manager accepts a clear scope and reports against defined products and tolerances. The board receives a credible next-stage plan with justified commitments and tolerances. The shortcut most directly implicated here is: Start the next stage before its scope and resource baseline are authorized.
C:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. The board receives a credible next-stage plan with justified commitments and tolerances. The shortcut most directly implicated here is: Start the next stage before its scope and resource baseline are authorized.
D:Submit tested products with required handover evidence and obtain authorized acceptance. The receiving authority acknowledges accepted products and remaining obligations. The board receives a credible next-stage plan with justified commitments and tolerances. The shortcut most directly implicated here is: Start the next stage before its scope and resource baseline are authorized.
Question 931
A project sponsor describes this requirement: a housing adaptation program sees projected demand fall sharply during an early management stage. Which step best meets it without creating unnecessary access? Select ONE answer.
- Produce a proportionate project brief and outline business case to support initiation authorization
- Confirm formal user acceptance against the project product description before recommending closure
- Update business justification and project forecasts before recommending continuation
- Handover operational responsibilities and future benefit reviews to named accountable owners
Explanation
Correct Answer
C:First, compare actual stage results and revised future benefits with the current business case. Update business justification and project forecasts before recommending continuation. Stage transitions require reconsidering project viability rather than simply measuring progress. Success means the board decides whether continued investment remains appropriate with transparent tradeoffs. Repeating review justification at future stage boundaries and material external changes helps prevent recurrence.
Incorrect Answers
A:Produce a proportionate project brief and outline business case to support initiation authorization. The board can approve or reject initiation on a coherent brief with clear assumptions. The board decides whether continued investment remains appropriate with transparent tradeoffs.
B:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The board decides whether continued investment remains appropriate with transparent tradeoffs.
D:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. The board decides whether continued investment remains appropriate with transparent tradeoffs.
Question 932
A project manager needs to diagnose this problem: a housing adaptation program sees projected demand fall sharply during an early management stage. Which investigation is the best initial check? Select ONE answer.
- Compare delivery alternatives against expected products, capabilities, constraints and risks
- Review the benefits management approach and operational readiness obligations
- Check evidence for the proposed costs and benefit owners against available options
- Compare actual stage results and revised future benefits with the current business case
Explanation
Correct Answer
D:The strongest first investigation is to compare actual stage results and revised future benefits with the current business case. Stage transitions require reconsidering project viability rather than simply measuring progress. If that evidence confirms the issue, the team should update business justification and project forecasts before recommending continuation. A subsequent acceptance check should confirm this result: The board decides whether continued investment remains appropriate with transparent tradeoffs. This check produces evidence before any broad configuration change, avoiding the risky proposal to renew the same funding automatically because one stage has ended.
Incorrect Answers
A:Compare delivery alternatives against expected products, capabilities, constraints and risks. An early approach decision should be informed rather than prematurely irreversible. The board decides whether continued investment remains appropriate with transparent tradeoffs. The relevant investigation is: Compare actual stage results and revised future benefits with the current business case.
B:Review the benefits management approach and operational readiness obligations. Some benefits mature after project closure and must have real ownership. The board decides whether continued investment remains appropriate with transparent tradeoffs. The relevant investigation is: Compare actual stage results and revised future benefits with the current business case.
C:Check evidence for the proposed costs and benefit owners against available options. The board can assess desirability, viability and achievability before authorizing the project. The board decides whether continued investment remains appropriate with transparent tradeoffs. The relevant investigation is: Compare actual stage results and revised future benefits with the current business case.
Question 933
The project team has corrected a reported weakness: a housing adaptation program sees projected demand fall sharply during an early management stage. Which acceptance result should the owner require? Select ONE answer.
- The board decides whether continued investment remains appropriate with transparent tradeoffs
- The board receives a credible next-stage plan with justified commitments and tolerances
- A working board and delivery organization are documented with accountable decisions and checks
- Receiving managers accept follow-on actions and measurable benefit-review schedules
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to review justification at future stage boundaries and material external changes. The decisive acceptance evidence is this result: The board decides whether continued investment remains appropriate with transparent tradeoffs. Stage transitions require reconsidering project viability rather than simply measuring progress. The operating team should diagnose it by checking whether it can compare actual stage results and revised future benefits with the current business case, then update business justification and project forecasts before recommending continuation where justified.
Incorrect Answers
B:The board receives a credible next-stage plan with justified commitments and tolerances. Stage boundaries create informed authorization points instead of unconditional funding. The board decides whether continued investment remains appropriate with transparent tradeoffs.
C:A working board and delivery organization are documented with accountable decisions and checks. The board decides whether continued investment remains appropriate with transparent tradeoffs.
D:Receiving managers accept follow-on actions and measurable benefit-review schedules. Some benefits mature after project closure and must have real ownership. The board decides whether continued investment remains appropriate with transparent tradeoffs.
Question 934
The team has remediated this situation: a housing adaptation program sees projected demand fall sharply during an early management stage. What maintenance control most directly reduces repeat failures? Select ONE answer.
- Follow up on significant lessons through organizational learning arrangements
- Review justification at future stage boundaries and material external changes
- Assign and verify actions arising from the end-stage lessons report
- Track exception decisions and the approved replacement baseline
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to update business justification and project forecasts before recommending continuation and diagnostic evidence to compare actual stage results and revised future benefits with the current business case. Periodic testing should confirm this result: The board decides whether continued investment remains appropriate with transparent tradeoffs. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to review justification at future stage boundaries and material external changes. Stage transitions require reconsidering project viability rather than simply measuring progress.
Incorrect Answers
A:Follow up on significant lessons through organizational learning arrangements. A final lessons report has actionable recommendations and accountable dissemination. The board decides whether continued investment remains appropriate with transparent tradeoffs. To avoid recurrence, review justification at future stage boundaries and material external changes.
C:Assign and verify actions arising from the end-stage lessons report. The board can see what worked, what failed and how the next stage will improve. The board decides whether continued investment remains appropriate with transparent tradeoffs. To avoid recurrence, review justification at future stage boundaries and material external changes.
D:Track exception decisions and the approved replacement baseline. A documented board decision approves revised tolerances, changes direction or stops the work. The board decides whether continued investment remains appropriate with transparent tradeoffs. To avoid recurrence, review justification at future stage boundaries and material external changes.
Question 935
The service owner is reviewing actions after this report: a housing adaptation program sees projected demand fall sharply during an early management stage. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Collect team checkpoint information and update stage forecasts against approved tolerances
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
- Renew the same funding automatically because one stage has ended
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
Explanation
Correct Answer
C:The unsafe shortcut is to renew the same funding automatically because one stage has ended. Stage transitions require reconsidering project viability rather than simply measuring progress. The defensible response is instead to update business justification and project forecasts before recommending continuation, using the diagnostic step to compare actual stage results and revised future benefits with the current business case before changing settings. Afterward, the team should confirm this result: The board decides whether continued investment remains appropriate with transparent tradeoffs. It must maintain the safeguard to review justification at future stage boundaries and material external changes.
Incorrect Answers
A:Collect team checkpoint information and update stage forecasts against approved tolerances. The project manager knows stage health early enough to take in-tolerance corrective action. The board decides whether continued investment remains appropriate with transparent tradeoffs. The shortcut most directly implicated here is: Renew the same funding automatically because one stage has ended.
B:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. The board decides whether continued investment remains appropriate with transparent tradeoffs. The shortcut most directly implicated here is: Renew the same funding automatically because one stage has ended.
D:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. The board decides whether continued investment remains appropriate with transparent tradeoffs. The shortcut most directly implicated here is: Renew the same funding automatically because one stage has ended.
Question 936
A PRINCE2 project manager receives this situation: a public health platform's supplier cost rises while promised user benefits are delayed. Which targeted corrective action should be chosen? Select ONE answer.
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Have the project board assess the project brief and authorize a bounded initiation stage
- Update business justification and project forecasts before recommending continuation
Explanation
Correct Answer
D:First, compare actual stage results and revised future benefits with the current business case. Update business justification and project forecasts before recommending continuation. Stage transitions require reconsidering project viability rather than simply measuring progress. Success means the board decides whether continued investment remains appropriate with transparent tradeoffs. Repeating review justification at future stage boundaries and material external changes helps prevent recurrence. By contrast, the response tied to this evidence is: Update business justification and project forecasts before recommending continuation.
Incorrect Answers
A:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The board decides whether continued investment remains appropriate with transparent tradeoffs.
B:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. The board decides whether continued investment remains appropriate with transparent tradeoffs.
C:Have the project board assess the project brief and authorize a bounded initiation stage. Initiation expenditure is explicitly authorized without pre-approving the entire project. The board decides whether continued investment remains appropriate with transparent tradeoffs.
Question 937
A support engineer investigates this project governance report: a public health platform's supplier cost rises while promised user benefits are delayed. Which comparison should be made first? Select ONE answer.
- Compare actual stage results and revised future benefits with the current business case
- Inspect the project brief and identify missing organization, quality, risk, issue and progress controls
- Compare the PID, business case, project plan and proposed tolerances with the project brief
- Inspect planned product dependencies, resource commitments and forecast tolerances
Explanation
Correct Answer
A:The strongest first investigation is to compare actual stage results and revised future benefits with the current business case. Stage transitions require reconsidering project viability rather than simply measuring progress. If that evidence confirms the issue, the team should update business justification and project forecasts before recommending continuation. A subsequent acceptance check should confirm this result: The board decides whether continued investment remains appropriate with transparent tradeoffs. This check produces evidence before any broad configuration change, avoiding the risky proposal to renew the same funding automatically because one stage has ended. By contrast, the response tied to this evidence is: Compare actual stage results and revised future benefits with the current business case.
Incorrect Answers
B:Inspect the project brief and identify missing organization, quality, risk, issue and progress controls. The board receives a coherent PID that establishes how the project will be managed and controlled. The board decides whether continued investment remains appropriate with transparent tradeoffs. The relevant investigation is: Compare actual stage results and revised future benefits with the current business case.
C:Compare the PID, business case, project plan and proposed tolerances with the project brief. The project board authorizes the project and first management stage on coherent evidence. The board decides whether continued investment remains appropriate with transparent tradeoffs. The relevant investigation is: Compare actual stage results and revised future benefits with the current business case.
D:Inspect planned product dependencies, resource commitments and forecast tolerances. The board can authorize staged delivery against a defensible project baseline. The board decides whether continued investment remains appropriate with transparent tradeoffs. The relevant investigation is: Compare actual stage results and revised future benefits with the current business case.
Question 938
An auditor asks how to validate resolution of this situation: a public health platform's supplier cost rises while promised user benefits are delayed. Which direct evidence is strongest? Select ONE answer.
- A documented board decision approves revised tolerances, changes direction or stops the work
- The board decides whether continued investment remains appropriate with transparent tradeoffs
- The board can authorize staged delivery against a defensible project baseline
- The project approach is justified and can support realistic initiation planning
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to review justification at future stage boundaries and material external changes. The decisive acceptance evidence is this result: The board decides whether continued investment remains appropriate with transparent tradeoffs. Stage transitions require reconsidering project viability rather than simply measuring progress. The operating team should diagnose it by checking whether it can compare actual stage results and revised future benefits with the current business case, then update business justification and project forecasts before recommending continuation where justified. By contrast, the response tied to this evidence is: The board decides whether continued investment remains appropriate with transparent tradeoffs.
Incorrect Answers
A:A documented board decision approves revised tolerances, changes direction or stops the work. The board decides whether continued investment remains appropriate with transparent tradeoffs.
C:The board can authorize staged delivery against a defensible project baseline. The board decides whether continued investment remains appropriate with transparent tradeoffs.
D:The project approach is justified and can support realistic initiation planning. An early approach decision should be informed rather than prematurely irreversible. The board decides whether continued investment remains appropriate with transparent tradeoffs.
Question 939
The project executive wants lasting assurance after this event: a public health platform's supplier cost rises while promised user benefits are delayed. Which preventive practice should be adopted? Select ONE answer.
- Track transferred actions in operational governance after project closure
- Reconfirm role assignments when partners and project governance change
- Review justification at future stage boundaries and material external changes
- Validate the mandate and named owners when organizational priorities change
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to update business justification and project forecasts before recommending continuation and diagnostic evidence to compare actual stage results and revised future benefits with the current business case. Periodic testing should confirm this result: The board decides whether continued investment remains appropriate with transparent tradeoffs. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to review justification at future stage boundaries and material external changes. Stage transitions require reconsidering project viability rather than simply measuring progress. By contrast, the response tied to this evidence is: Review justification at future stage boundaries and material external changes.
Incorrect Answers
A:Track transferred actions in operational governance after project closure. The board approves closure with clear transfer of every outstanding responsibility. The board decides whether continued investment remains appropriate with transparent tradeoffs. To avoid recurrence, review justification at future stage boundaries and material external changes.
B:Reconfirm role assignments when partners and project governance change. A working board and delivery organization are documented with accountable decisions and checks. The board decides whether continued investment remains appropriate with transparent tradeoffs. To avoid recurrence, review justification at future stage boundaries and material external changes.
D:Validate the mandate and named owners when organizational priorities change. The initiation decision is supported by a credible mandate and defined responsibilities. The board decides whether continued investment remains appropriate with transparent tradeoffs. To avoid recurrence, review justification at future stage boundaries and material external changes.
Question 940
An operator suggests skipping safeguards after this event: a public health platform's supplier cost rises while promised user benefits are delayed. Which action should be ruled out? Select ONE answer.
- Handover operational responsibilities and future benefit reviews to named accountable owners
- Confirm formal user acceptance against the project product description before recommending closure
- Define proportionate agreed approaches for risk, issues, quality, communications, change and project information
- Renew the same funding automatically because one stage has ended
Explanation
Correct Answer
D:The unsafe shortcut is to renew the same funding automatically because one stage has ended. Stage transitions require reconsidering project viability rather than simply measuring progress. The defensible response is instead to update business justification and project forecasts before recommending continuation, using the diagnostic step to compare actual stage results and revised future benefits with the current business case before changing settings. Afterward, the team should confirm this result: The board decides whether continued investment remains appropriate with transparent tradeoffs. It must maintain the safeguard to review justification at future stage boundaries and material external changes. By contrast, the response tied to this evidence is: Renew the same funding automatically because one stage has ended.
Incorrect Answers
A:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. The board decides whether continued investment remains appropriate with transparent tradeoffs. The shortcut most directly implicated here is: Renew the same funding automatically because one stage has ended.
B:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The board decides whether continued investment remains appropriate with transparent tradeoffs. The shortcut most directly implicated here is: Renew the same funding automatically because one stage has ended.
C:Define proportionate agreed approaches for risk, issues, quality, communications, change and project information. Coordinated project controls must be established before distributed delivery begins. The board decides whether continued investment remains appropriate with transparent tradeoffs. The shortcut most directly implicated here is: Renew the same funding automatically because one stage has ended.