PMI CAPM Practice Test 14
Question 130
For an original CAPM project delivery study scenario, consider: A process redesign involves patient representatives but the stakeholder list contains only the IT vendor and sponsor, leaving clinical approvals unresolved. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Change: Select timely communication channels, audiences, owners, cadence and escalation criteria matched to the information's urgency and decision need.
- Check: Review stakeholder mapping, decision authorities, influence, concerns, engagement commitments and actual feedback history.
- Check: Audit agenda-to-outcome mapping, attendance of decision authorities, action owner dates and closure of prior decisions.
- Send one generic announcement to an incomplete contact list and assume unlisted users have given consent.
- Change: Identify internal and external parties, assess interests and influence, and plan appropriately targeted engagement with accountable owners.
Explanation
Correct Answer
B:Stakeholder analysis informs communication and participation; missing affected groups can cause opposition or unvalidated requirements. Required intervention: Identify internal and external parties, assess interests and influence, and plan appropriately targeted engagement with accountable owners.
E:Stakeholder analysis informs communication and participation; missing affected groups can cause opposition or unvalidated requirements. Evidence: Review stakeholder mapping, decision authorities, influence, concerns, engagement commitments and actual feedback history.
Incorrect Answers
A:This option addresses a different CAPM project management topic (Communication channels and escalation) rather than the documented Stakeholder register and engagement decision.
C:Check: Audit agenda-to-outcome mapping, attendance of decision authorities, action owner dates and closure of prior decisions. Stakeholder analysis informs communication and participation; missing affected groups can cause opposition or unvalidated requirements.
D:Stakeholder analysis informs communication and participation; missing affected groups can cause opposition or unvalidated requirements.
Question 131
A CAPM project team analyst is reviewing this delivery scenario: A utility commissioning team disbands after first power-on even though operations lacks maintenance documentation and spare-part responsibilities. An unsafe shortcut would be: Declare closure whenever staff roll off regardless of acceptance, warranty obligations and operational readiness. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Choose a facilitated focus group for shared perceptions, targeted interviews for detailed individual knowledge, and brainstorming for broad idea generation before evaluation.
- Declare closure whenever staff roll off regardless of acceptance, warranty obligations and operational readiness.
- Build a documented estimate and approved cost baseline with identified cost categories and risk-informed contingency under change controls.
- Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records.
Explanation
Correct Answer
D:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Incorrect Answers
A:Choose a facilitated focus group for shared perceptions, targeted interviews for detailed individual knowledge, and brainstorming for broad idea generation before evaluation. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
B:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
C:This option addresses a different CAPM project management topic (Cost estimates and contingency reserve) rather than the documented Closing and operational handover decision.
Question 132
A project delivery review finds: A utility commissioning team disbands after first power-on even though operations lacks maintenance documentation and spare-part responsibilities. The team proposes: Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records. Which project management principle most strongly supports the proposed response? Select ONE best answer.
- Delivering a project output is not equivalent to realizing the expected organizational benefits; users must adopt new capabilities.
- A scope statement defines what completion includes and excludes; ambiguous boundaries invite uncontrolled additional work and missed contractual outcomes.
- Lessons learned are useful when linked to changed practice and accessible organizational knowledge, not just a final celebratory document.
- Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Explanation
Correct Answer
D:Demonstrable success requires: Sponsors accept the intended result, residual commitments have owners, and operations can support the deliverable after team release. This principle explains the proposed project response, which is: Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records.
Incorrect Answers
A:Delivering a project output is not equivalent to realizing the expected organizational benefits; users must adopt new capabilities. A utility commissioning team disbands after first power-on even though operations lacks maintenance documentation and spare-part responsibilities.
B:A scope statement defines what completion includes and excludes; ambiguous boundaries invite uncontrolled additional work and missed contractual outcomes. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
C:Lessons learned are useful when linked to changed practice and accessible organizational knowledge, not just a final celebratory document. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Question 133
The project team has not approved a broad project-plan change. Available evidence indicates: A utility commissioning team disbands after first power-on even though operations lacks maintenance documentation and spare-part responsibilities. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Examine duration estimates, entry and exit criteria, predecessor activities and the milestone baseline in the project schedule.
- Inspect acceptance evidence, open-items disposition, operational readiness, transition training, contracts and lessons-learned archive.
- Compare risk thresholds, selected response cost, trigger, fallback owner and whether residual exposure remains acceptable.
- Inspect quality metrics, sample plans, test coverage, nonconformance logs and independent acceptance evidence against the approved criteria.
Explanation
Correct Answer
B:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Incorrect Answers
A:This option addresses a different CAPM project management topic (Milestones versus task durations) rather than the documented Closing and operational handover decision.
C:Compare risk thresholds, selected response cost, trigger, fallback owner and whether residual exposure remains acceptable. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
D:Inspect quality metrics, sample plans, test coverage, nonconformance logs and independent acceptance evidence against the approved criteria. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Question 134
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: A utility commissioning team disbands after first power-on even though operations lacks maintenance documentation and spare-part responsibilities. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- Sponsors accept the intended result, residual commitments have owners, and operations can support the deliverable after team release.
- Urgent decisions reach accountable people in time and routine updates remain understandable without flooding irrelevant audiences.
- The implementation closes on acceptance and transfers ownership while ongoing customer service is measured and funded as normal operations.
- The chosen approach supplies the needed governance and feedback cadence without either freezing unknown requirements or omitting mandatory compliance baselines.
Explanation
Correct Answer
A:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion. The approved implementation step was: Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records.
Incorrect Answers
B:This option addresses a different CAPM project management topic (Communication channels and escalation) rather than the documented Closing and operational handover decision.
C:This option addresses a different CAPM project management topic (Projects versus routine operations) rather than the documented Closing and operational handover decision.
D:This option addresses a different CAPM project management topic (Predictive versus adaptive uncertainty) rather than the documented Closing and operational handover decision.
Question 135
An implementation sign-off request identifies the following problem: A utility commissioning team disbands after first power-on even though operations lacks maintenance documentation and spare-part responsibilities. Which paired project management action and verification should close the review? Select ONE best answer.
- Change: Estimate resource types, skill constraints and availability by activity and resolve competing allocations before setting a credible date baseline. Verify: Inspect resource calendars, demand by work package, role skills, vendor lead times and contention across concurrent initiatives.
- Change: Document current issues, severity, impact, owner, target resolution and escalation route distinct from preventive future-risk responses. Verify: Review defect evidence, impact on objectives, action log, agreed service response and sponsor escalation triggers.
- Change: Classify a time-bounded outcome as a project, coordinated benefits as a program, and strategic investment selection as a portfolio before setting ownership. Verify: Inspect component charters, cross-project dependencies, shared benefits and strategic prioritization criteria in the governance record.
- Change: Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records. Verify: Inspect acceptance evidence, open-items disposition, operational readiness, transition training, contracts and lessons-learned archive.
Explanation
Correct Answer
D:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Incorrect Answers
A:Change: Estimate resource types, skill constraints and availability by activity and resolve competing allocations before setting a credible date baseline. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
B:Change: Document current issues, severity, impact, owner, target resolution and escalation route distinct from preventive future-risk responses.
C:This option addresses a different CAPM project management topic (Project versus program versus portfolio) rather than the documented Closing and operational handover decision.
Question 136
A CAPM project team analyst is reviewing this delivery scenario: An internal app project meets its budget but closes while an unresolved warranty defect has no owner or final acceptance record. An unsafe shortcut would be: Declare closure whenever staff roll off regardless of acceptance, warranty obligations and operational readiness. What should the project team analyst recommend as the narrowly scoped correction? Select ONE best answer.
- Estimate resource types, skill constraints and availability by activity and resolve competing allocations before setting a credible date baseline.
- Clarify one accountable owner per decision or deliverable with responsible contributors and appropriate consulted and informed parties.
- Declare closure whenever staff roll off regardless of acceptance, warranty obligations and operational readiness.
- Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records.
Explanation
Correct Answer
D:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Incorrect Answers
A:Estimate resource types, skill constraints and availability by activity and resolve competing allocations before setting a credible date baseline. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
B:Clarify one accountable owner per decision or deliverable with responsible contributors and appropriate consulted and informed parties. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
C:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion. Use this instead: Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records.
Question 137
A project delivery review finds: An internal app project meets its budget but closes while an unresolved warranty defect has no owner or final acceptance record. The team proposes: Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records. Which project management principle most strongly supports the proposed response? Select ONE best answer.
- A scope statement defines what completion includes and excludes; ambiguous boundaries invite uncontrolled additional work and missed contractual outcomes.
- Estimates rely on conditions that should be tested; unvalidated assumptions and constraints have different implications for forecast confidence.
- Formal initiation establishes project existence and legitimate resource authority; detailed plans should trace to an approved need and governance channel.
- Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Explanation
Correct Answer
D:Demonstrable success requires: Sponsors accept the intended result, residual commitments have owners, and operations can support the deliverable after team release.
Incorrect Answers
A:A scope statement defines what completion includes and excludes; ambiguous boundaries invite uncontrolled additional work and missed contractual outcomes. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
B:This option addresses a different CAPM project management topic (Assumptions log and estimation uncertainty) rather than the documented Closing and operational handover decision.
C:This option addresses a different CAPM project management topic (Project charter and sponsor authorization) rather than the documented Closing and operational handover decision.
Question 138
The project team has not approved a broad project-plan change. Available evidence indicates: An internal app project meets its budget but closes while an unresolved warranty defect has no owner or final acceptance record. Which evidence best tests the project diagnosis before approving a disruptive change? Select ONE best answer.
- Audit agenda-to-outcome mapping, attendance of decision authorities, action owner dates and closure of prior decisions.
- Inspect acceptance evidence, open-items disposition, operational readiness, transition training, contracts and lessons-learned archive.
- Review stakeholder mapping, decision authorities, influence, concerns, engagement commitments and actual feedback history.
- Compare desired evidence type, participant diversity, facilitator design and how resulting statements are captured without group domination.
Explanation
Correct Answer
B:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Incorrect Answers
A:Audit agenda-to-outcome mapping, attendance of decision authorities, action owner dates and closure of prior decisions. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
C:Review stakeholder mapping, decision authorities, influence, concerns, engagement commitments and actual feedback history. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
D:Compare desired evidence type, participant diversity, facilitator design and how resulting statements are captured without group domination. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Question 139
A candidate project response has been piloted and stakeholders require a post-change acceptance check. Original problem: An internal app project meets its budget but closes while an unresolved warranty defect has no owner or final acceptance record. The accountable project owner requires evidence that outcomes are met without disrupting planned work. Which acceptance result demonstrates that the project response meets the intended outcome? Select ONE best answer.
- The project implements an approved proportionate response and monitors residual risk without confusing insurance with prevention.
- Future teams can retrieve practical guidance and demonstrate reduced recurrence or deliberate reuse of effective methods.
- Sponsors accept the intended result, residual commitments have owners, and operations can support the deliverable after team release.
- Critical measures meet documented tolerances and exceptions are resolved or formally accepted without hiding nonconforming output.
Explanation
Correct Answer
C:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Incorrect Answers
A:The project implements an approved proportionate response and monitors residual risk without confusing insurance with prevention. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
B:Future teams can retrieve practical guidance and demonstrate reduced recurrence or deliberate reuse of effective methods. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
D:Critical measures meet documented tolerances and exceptions are resolved or formally accepted without hiding nonconforming output. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
Question 140
For an original CAPM project delivery study scenario, consider: An internal app project meets its budget but closes while an unresolved warranty defect has no owner or final acceptance record. Select TWO complementary steps: the targeted correction and its strongest prechange validation.
- Change: Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records.
- Change: Identify internal and external parties, assess interests and influence, and plan appropriately targeted engagement with accountable owners.
- Check: Review defect evidence, impact on objectives, action log, agreed service response and sponsor escalation triggers.
- Declare closure whenever staff roll off regardless of acceptance, warranty obligations and operational readiness.
- Check: Inspect acceptance evidence, open-items disposition, operational readiness, transition training, contracts and lessons-learned archive.
Explanation
Correct Answer
A:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion. Acceptance: Sponsors accept the intended result, residual commitments have owners, and operations can support the deliverable after team release.
E:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion. Required intervention: Obtain documented acceptance, transfer supported deliverables and knowledge, resolve remaining obligations and archive lessons and contractual records.
Incorrect Answers
B:Change: Identify internal and external parties, assess interests and influence, and plan appropriately targeted engagement with accountable owners. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
C:Check: Review defect evidence, impact on objectives, action log, agreed service response and sponsor escalation triggers. Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.
D:Closing confirms authorized scope and establishes sustained operational support; project completion cannot be inferred solely from funding exhaustion.