Question 950
An encryption rollout lists the go-live milestone before key-management testing is complete. Before acting, which evidence should the project team examine FIRST to assess the stated need?
Explanation
Correct Answer
Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. This checks the relevant condition before the team intervenes. A milestone is a significant zero-duration checkpoint; tasks consume effort and successors may depend on predecessor completion. The controlled response is: Build a dependency-aware schedule with measurable milestones and realistic predecessor relationships rather than assigning dates independently. Situation: An encryption rollout lists the go-live milestone before key-management testing is complete.
Incorrect Answers
Inspect signed scope, deliverable hierarchy, package completion criteria, missing work, and overlapping assignments. That evidence would investigate Work breakdown structure and scope decomposition, not the main uncertainty in this situation. To decide the current case, examine: Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. Situation: An encryption rollout lists the go-live milestone before key-management testing is complete.
Inspect original acceptance criteria, test results, product owner or sponsor authority, and open defect dispositions. That evidence would investigate Final deliverable acceptance and sponsor signoff, not the main uncertainty in this situation. To decide the current case, examine: Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. Situation: An encryption rollout lists the go-live milestone before key-management testing is complete.
Inspect completed phase deliverables, unresolved severity-one defects, signoff requirements, and dependencies for the next phase. That evidence would investigate Phase gate readiness review, not the main uncertainty in this situation. To decide the current case, examine: Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. Situation: An encryption rollout lists the go-live milestone before key-management testing is complete.