Question 940
A retailer expects rapid experiments in its loyalty app and needs one accountable person to order the backlog. Which project-management response BEST addresses the stated need?
Explanation
Correct Answer
Assign an empowered product owner to prioritize an evolving backlog and review useful increments regularly with users. This targets the specific project decision. Iterative Agile delivery relies on frequent feedback and a prioritized product backlog; product ownership is different from project administrative scheduling. Before committing, assess: Inspect backlog ownership, sprint goals, stakeholder feedback cadence, definition of done, and ability to reorder work. Situation: A retailer expects rapid experiments in its loyalty app and needs one accountable person to order the backlog.
Incorrect Answers
Select a sequential Waterfall approach with formally approved requirements and stage gates when deliverables and acceptance criteria must remain stable. That response is associated with Waterfall for fixed regulatory requirements and does not directly settle this case. Its relevant principle is: Waterfall fits stable, extensively specified work with gated handoffs; Agile better accommodates iterative discovery when change is expected. The stated case instead calls for: Assign an empowered product owner to prioritize an evolving backlog and review useful increments regularly with users. Situation: A retailer expects rapid experiments in its loyalty app and needs one accountable person to order the backlog.
Map task precedence and identify the longest dependency path to forecast the earliest achievable finish before compressing work. That response is associated with Critical path and hard dependencies and does not directly settle this case. Its relevant principle is: The critical path is the longest duration path through dependent tasks; delaying a critical task can delay completion even if other tasks have slack. The stated case instead calls for: Assign an empowered product owner to prioritize an evolving backlog and review useful increments regularly with users. Situation: A retailer expects rapid experiments in its loyalty app and needs one accountable person to order the backlog.
Create a communication plan matching each stakeholder group's decision needs, channel, detail level, owner, and reporting cadence. That response is associated with Stakeholder communication plan tailoring and does not directly settle this case. Its relevant principle is: Effective project communication is tailored to audience and timing; giving everyone the same raw data is not equivalent to keeping them informed. The stated case instead calls for: Assign an empowered product owner to prioritize an evolving backlog and review useful increments regularly with users. Situation: A retailer expects rapid experiments in its loyalty app and needs one accountable person to order the backlog.