Question 800
A Scrum team closes 20 story points but adds 30 points of scope, making the remaining work rise. Which TWO complementary steps provide the best response AND its necessary supporting assessment? Select TWO.
Explanation
Correct Answers
Inspect completed work, remaining backlog, added scope, sprint boundaries, and historical throughput. This checks the relevant condition before the team intervenes. Burndown tracks work remaining and burnup tracks delivered work versus total scope; velocity describes prior throughput, not a guaranteed future commitment. The controlled response is: Use a burndown or burnup chart and past delivery velocity to forecast remaining work while accounting for changing scope. It complements the associated implementation step. Situation: A Scrum team closes 20 story points but adds 30 points of scope, making the remaining work rise.
Use a burndown or burnup chart and past delivery velocity to forecast remaining work while accounting for changing scope. This targets the specific project decision. Burndown tracks work remaining and burnup tracks delivered work versus total scope; velocity describes prior throughput, not a guaranteed future commitment. Before committing, assess: Inspect completed work, remaining backlog, added scope, sprint boundaries, and historical throughput. It complements the associated assessment evidence. Situation: A Scrum team closes 20 story points but adds 30 points of scope, making the remaining work rise.
Incorrect Answers
Create a Pareto chart grouping recurring issue categories by frequency or impact to focus improvement on the largest contributors. This is useful for Pareto chart defect prioritization but is not one of the complementary steps for this case. The appropriate paired decision combines: Use a burndown or burnup chart and past delivery velocity to forecast remaining work while accounting for changing scope. and Inspect completed work, remaining backlog, added scope, sprint boundaries, and historical throughput. Situation: A Scrum team closes 20 story points but adds 30 points of scope, making the remaining work rise.
Future threats retain planned responses while occurring problems receive immediate ownership and tracked resolution. This is useful for Risk register versus issue log but is not one of the complementary steps for this case. The appropriate paired decision combines: Use a burndown or burnup chart and past delivery velocity to forecast remaining work while accounting for changing scope. and Inspect completed work, remaining backlog, added scope, sprint boundaries, and historical throughput. Situation: A Scrum team closes 20 story points but adds 30 points of scope, making the remaining work rise.
Inspect approved budget, expenses to date, purchase-order commitments, forecast-to-complete, and chart reporting period. This is useful for Budget burndown and progress dashboard but is not one of the complementary steps for this case. The appropriate paired decision combines: Use a burndown or burnup chart and past delivery velocity to forecast remaining work while accounting for changing scope. and Inspect completed work, remaining backlog, added scope, sprint boundaries, and historical throughput. Situation: A Scrum team closes 20 story points but adds 30 points of scope, making the remaining work rise.