Question 820
An IT director wants to separate a six-month data center move from the ongoing monitoring of the new facility. Which result BEST demonstrates that the project-management response met the stated need?
Explanation
Correct Answer
The new capability is formally accepted and transferred to a continuing operations team instead of keeping a perpetual project open. This is an observable measure of the intended outcome, not just evidence that a meeting or configuration occurred. Projects create unique outcomes for a limited period; recurring routine services are operations even when they use project tools. Situation: An IT director wants to separate a six-month data center move from the ongoing monitoring of the new facility.
Incorrect Answers
The sprint goal fits actual capacity and accepted stories meet the definition of done rather than being counted merely because started. That outcome tests Sprint estimation and backlog prioritization; it is not proof of this particular requirement. The more specific validation is: The new capability is formally accepted and transferred to a continuing operations team instead of keeping a perpetual project open. Situation: An IT director wants to separate a six-month data center move from the ongoing monitoring of the new facility.
Incoming tasks move through visible states without overloaded in-progress columns and flow time becomes more predictable. That outcome tests Kanban flow versus sprint commitments; it is not proof of this particular requirement. The more specific validation is: The new capability is formally accepted and transferred to a continuing operations team instead of keeping a perpetual project open. Situation: An IT director wants to separate a six-month data center move from the ongoing monitoring of the new facility.
The proper authority approves, rejects, or defers the request and the log and project plan reflect the same decision. That outcome tests Change control board decision authority; it is not proof of this particular requirement. The more specific validation is: The new capability is formally accepted and transferred to a continuing operations team instead of keeping a perpetual project open. Situation: An IT director wants to separate a six-month data center move from the ongoing monitoring of the new facility.