Question 780
An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget. Which result BEST demonstrates that the project-management response met the stated need?
Explanation
Correct Answer
Only approved extensions appear in the work plan, while rejected or deferred requests remain visible but uncommitted. This is an observable measure of the intended outcome, not just evidence that a meeting or configuration occurred. Scope creep is uncontrolled growth of work; a legitimate scope change requires assessment and authorized baseline updates. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.
Incorrect Answers
A status report correctly identifies schedule or cost underperformance and proposes a proportionate corrective response. That outcome tests Schedule and cost variance measurement; it is not proof of this particular requirement. The more specific validation is: Only approved extensions appear in the work plan, while rejected or deferred requests remain visible but uncommitted. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.
A deliberately vulnerable dependency stops the release before production and its remediation is traceable to a team owner. That outcome tests DevSecOps security in delivery; it is not proof of this particular requirement. The more specific validation is: Only approved extensions appear in the work plan, while rejected or deferred requests remain visible but uncommitted. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.
The decision authority receives documented alternatives and impacts, and the request is not implemented while undecided. That outcome tests Change request impact assessment; it is not proof of this particular requirement. The more specific validation is: Only approved extensions appear in the work plan, while rejected or deferred requests remain visible but uncommitted. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.