Question 770
A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast. Which project-management response BEST addresses the stated need?
Explanation
Correct Answer
Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. This targets the specific project decision. Story points reflect relative complexity or effort rather than guaranteed hours, and an epic is too broad to treat as one small task. Before committing, assess: Inspect current priorities, acceptance criteria, team velocity, dependencies, and historical size of completed work. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Incorrect Answers
Use approved contingency buffer for anticipated uncertainty and rebaseline only after an authorized material change rather than hiding every schedule slip. That response is associated with Schedule buffer and controlled rebaseline and does not directly settle this case. Its relevant principle is: Updating a forecast reflects current expectations; replacing the official baseline requires formal authorization and should not erase performance history. The stated case instead calls for: Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Assign an empowered product owner to prioritize an evolving backlog and review useful increments regularly with users. That response is associated with Agile feedback and product ownership and does not directly settle this case. Its relevant principle is: Iterative Agile delivery relies on frequent feedback and a prioritized product backlog; product ownership is different from project administrative scheduling. The stated case instead calls for: Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Publish a focused agenda, assign facilitator and scribe, timebox discussion, and capture decisions with owners and due dates. That response is associated with Timeboxed effective project meetings and does not directly settle this case. Its relevant principle is: Meeting effectiveness depends on outcomes and follow-through, not on attendance or duration alone. The stated case instead calls for: Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.