Question 400
An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget. Which TWO complementary steps provide the best response AND its necessary supporting assessment? Select TWO.
Explanation
Correct Answers
Compare requested work to the approved scope statement and process additions through formal control while preventing unapproved scope expansion. This targets the specific project decision. Scope creep is uncontrolled growth of work; a legitimate scope change requires assessment and authorized baseline updates. Before committing, assess: Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. It complements the associated assessment evidence. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.
Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. This checks the relevant condition before the team intervenes. Scope creep is uncontrolled growth of work; a legitimate scope change requires assessment and authorized baseline updates. The controlled response is: Compare requested work to the approved scope statement and process additions through formal control while preventing unapproved scope expansion. It complements the associated implementation step. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.
Incorrect Answers
Each project has approved resource availability and staffing conflicts no longer appear as unexplained missed tasks. This is useful for Matrix organization and resource conflicts but is not one of the complementary steps for this case. The appropriate paired decision combines: Compare requested work to the approved scope statement and process additions through formal control while preventing unapproved scope expansion. and Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.
Review recipient access, sensitive attachments, meeting availability, archived decisions, and channel security requirements. This is useful for Secure asynchronous project communications but is not one of the complementary steps for this case. The appropriate paired decision combines: Compare requested work to the approved scope statement and process additions through formal control while preventing unapproved scope expansion. and Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.
Route material changes to the approved change control board or delegated decision maker and record the final disposition before updating authorized plans. This is useful for Change control board decision authority but is not one of the complementary steps for this case. The appropriate paired decision combines: Compare requested work to the approved scope statement and process additions through formal control while preventing unapproved scope expansion. and Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. Situation: An ERP team repeatedly accepts minor interface requests until deployment work no longer fits the approved budget.