Question 380
A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast. Which TWO complementary steps provide the best response AND its necessary supporting assessment? Select TWO.
Explanation
Correct Answers
Inspect current priorities, acceptance criteria, team velocity, dependencies, and historical size of completed work. This checks the relevant condition before the team intervenes. Story points reflect relative complexity or effort rather than guaranteed hours, and an epic is too broad to treat as one small task. The controlled response is: Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. It complements the associated implementation step. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. This targets the specific project decision. Story points reflect relative complexity or effort rather than guaranteed hours, and an epic is too broad to treat as one small task. Before committing, assess: Inspect current priorities, acceptance criteria, team velocity, dependencies, and historical size of completed work. It complements the associated assessment evidence. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Incorrect Answers
Use approved contingency buffer for anticipated uncertainty and rebaseline only after an authorized material change rather than hiding every schedule slip. This is useful for Schedule buffer and controlled rebaseline but is not one of the complementary steps for this case. The appropriate paired decision combines: Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. and Inspect current priorities, acceptance criteria, team velocity, dependencies, and historical size of completed work. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
The selected treatment is documented, funded when required, and the remaining exposure is accepted by an authorized owner. This is useful for Negative risk response selection but is not one of the complementary steps for this case. The appropriate paired decision combines: Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. and Inspect current priorities, acceptance criteria, team velocity, dependencies, and historical size of completed work. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.
Review whether the request has a distinctive outcome, funded start and end, acceptance conditions, and a designated operational owner after handoff. This is useful for Project versus ongoing operations but is not one of the complementary steps for this case. The appropriate paired decision combines: Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. and Inspect current priorities, acceptance criteria, team velocity, dependencies, and historical size of completed work. Situation: A sprint planner needs a coherent goal and stable high-priority items after the previous sprint missed its forecast.