Question 360
A supplier deliverable arrives late but the plan fails to update tasks that cannot begin without it. Before acting, which evidence should the project team examine FIRST to assess the stated need?
Explanation
Correct Answer
Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. This checks the relevant condition before the team intervenes. A milestone is a significant zero-duration checkpoint; tasks consume effort and successors may depend on predecessor completion. The controlled response is: Build a dependency-aware schedule with measurable milestones and realistic predecessor relationships rather than assigning dates independently. Situation: A supplier deliverable arrives late but the plan fails to update tasks that cannot begin without it.
Incorrect Answers
Review sponsor-approved charter, preliminary milestones, stakeholder list, team assignments, and decision protocol. That evidence would investigate Kickoff and shared project expectations, not the main uncertainty in this situation. To decide the current case, examine: Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. Situation: A supplier deliverable arrives late but the plan fails to update tasks that cannot begin without it.
Inspect labor effort estimates, hardware procurement, licensing renewals, contingency assumptions, and funding authority. That evidence would investigate Budget baseline and funding allocation, not the main uncertainty in this situation. To decide the current case, examine: Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. Situation: A supplier deliverable arrives late but the plan fails to update tasks that cannot begin without it.
Inspect incident and change histories, financial reconciliation, feedback, decision logs, and archival policy. That evidence would investigate Lessons learned and archive preservation, not the main uncertainty in this situation. To decide the current case, examine: Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. Situation: A supplier deliverable arrives late but the plan fails to update tasks that cannot begin without it.


