Question 200
A team burns its entire risk buffer early but reports all remaining schedule dates unchanged without analysis. Which TWO complementary steps provide the best response AND its necessary supporting assessment? Select TWO.
Explanation
Correct Answers
Use approved contingency buffer for anticipated uncertainty and rebaseline only after an authorized material change rather than hiding every schedule slip. This targets the specific project decision. Updating a forecast reflects current expectations; replacing the official baseline requires formal authorization and should not erase performance history. Before committing, assess: Review baseline dates, schedule variance, buffer remaining, dependent activities, risk triggers, and approval authority. It complements the associated assessment evidence. Situation: A team burns its entire risk buffer early but reports all remaining schedule dates unchanged without analysis.
Review baseline dates, schedule variance, buffer remaining, dependent activities, risk triggers, and approval authority. This checks the relevant condition before the team intervenes. Updating a forecast reflects current expectations; replacing the official baseline requires formal authorization and should not erase performance history. The controlled response is: Use approved contingency buffer for anticipated uncertainty and rebaseline only after an authorized material change rather than hiding every schedule slip. It complements the associated implementation step. Situation: A team burns its entire risk buffer early but reports all remaining schedule dates unchanged without analysis.
Incorrect Answers
Inspect incident timeline, reproducing conditions, logs, workaround limitations, related change requests, and recurrence data. This is useful for Root cause analysis and safe workaround but is not one of the complementary steps for this case. The appropriate paired decision combines: Use approved contingency buffer for anticipated uncertainty and rebaseline only after an authorized material change rather than hiding every schedule slip. and Review baseline dates, schedule variance, buffer remaining, dependent activities, risk triggers, and approval authority. Situation: A team burns its entire risk buffer early but reports all remaining schedule dates unchanged without analysis.
Break an epic into well-scoped backlog items, estimate relative effort with the team, and select a realistic sprint goal using proven capacity. This is useful for Sprint estimation and backlog prioritization but is not one of the complementary steps for this case. The appropriate paired decision combines: Use approved contingency buffer for anticipated uncertainty and rebaseline only after an authorized material change rather than hiding every schedule slip. and Review baseline dates, schedule variance, buffer remaining, dependent activities, risk triggers, and approval authority. Situation: A team burns its entire risk buffer early but reports all remaining schedule dates unchanged without analysis.
High-priority user feedback changes upcoming backlog order without silently changing completed accepted scope or bypassing quality gates. This is useful for Agile feedback and product ownership but is not one of the complementary steps for this case. The appropriate paired decision combines: Use approved contingency buffer for anticipated uncertainty and rebaseline only after an authorized material change rather than hiding every schedule slip. and Review baseline dates, schedule variance, buffer remaining, dependent activities, risk triggers, and approval authority. Situation: A team burns its entire risk buffer early but reports all remaining schedule dates unchanged without analysis.