Question 190
A software vendor adds custom reports during user workshops although the contract explicitly excludes them. Before acting, which evidence should the project team examine FIRST to assess the stated need?
Explanation
Correct Answer
Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. This checks the relevant condition before the team intervenes. Scope creep is uncontrolled growth of work; a legitimate scope change requires assessment and authorized baseline updates. The controlled response is: Compare requested work to the approved scope statement and process additions through formal control while preventing unapproved scope expansion. Situation: A software vendor adds custom reports during user workshops although the contract explicitly excludes them.
Incorrect Answers
Review the charter's authority thresholds, CCB membership, change log status, stakeholder consultation, and approval evidence. That evidence would investigate Change control board decision authority, not the main uncertainty in this situation. To decide the current case, examine: Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. Situation: A software vendor adds custom reports during user workshops although the contract explicitly excludes them.
Inspect pipeline stages, threat and dependency scans, ownership of findings, exception records, and promotion gates. That evidence would investigate DevSecOps security in delivery, not the main uncertainty in this situation. To decide the current case, examine: Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. Situation: A software vendor adds custom reports during user workshops although the contract explicitly excludes them.
Review recipient access, sensitive attachments, meeting availability, archived decisions, and channel security requirements. That evidence would investigate Secure asynchronous project communications, not the main uncertainty in this situation. To decide the current case, examine: Inspect signed scope exclusions, deliverable acceptance conditions, backlog additions, change log, and schedule/cost baselines. Situation: A software vendor adds custom reports during user workshops although the contract explicitly excludes them.