Question 180
An IT vendor provides a final invoice but cannot show signed acceptance of the agreed system integration deliverables. Before acting, which evidence should the project team examine FIRST to assess the stated need?
Explanation
Correct Answer
Inspect original acceptance criteria, test results, product owner or sponsor authority, and open defect dispositions. This checks the relevant condition before the team intervenes. Formal project closure follows validated deliverables and authorized acceptance; declaring tasks complete in a tracker does not equal signoff. The controlled response is: Confirm agreed acceptance tests and contractual deliverables, obtain authorized signoff, and document any approved outstanding items. Situation: An IT vendor provides a final invoice but cannot show signed acceptance of the agreed system integration deliverables.
Incorrect Answers
Inspect estimated task duration, external deliverables, technical sequence, resource availability, and milestone acceptance criteria. That evidence would investigate Planning milestones and predecessor sequencing, not the main uncertainty in this situation. To decide the current case, examine: Inspect original acceptance criteria, test results, product owner or sponsor authority, and open defect dispositions. Situation: An IT vendor provides a final invoice but cannot show signed acceptance of the agreed system integration deliverables.
Inspect completed purchase orders, warranties, unpaid invoices, administrative credentials, and open contractual claims. That evidence would investigate Vendor contract closeout and resource release, not the main uncertainty in this situation. To decide the current case, examine: Inspect original acceptance criteria, test results, product owner or sponsor authority, and open defect dispositions. Situation: An IT vendor provides a final invoice but cannot show signed acceptance of the agreed system integration deliverables.
Inspect organizational groups, decision rights, business concerns, communication needs, and stakeholder influence. That evidence would investigate Stakeholder analysis and engagement, not the main uncertainty in this situation. To decide the current case, examine: Inspect original acceptance criteria, test results, product owner or sponsor authority, and open defect dispositions. Situation: An IT vendor provides a final invoice but cannot show signed acceptance of the agreed system integration deliverables.


