Question 140
A manufacturing client asks to add plant locations after a signed network rollout plan is baselined. Which project-management response BEST addresses the stated need?
Explanation
Correct Answer
Log a proposed project change and assess its effect on scope, cost, schedule, resources, and risk before seeking an approval decision. This targets the specific project decision. A formal project change starts with a recorded request and impact assessment, not an immediate undocumented edit to the baseline. Before committing, assess: Inspect original baseline, submitted request, affected deliverables, schedule dependencies, cost forecast, and impact analysis. Situation: A manufacturing client asks to add plant locations after a signed network rollout plan is baselined.
Incorrect Answers
Route material changes to the approved change control board or delegated decision maker and record the final disposition before updating authorized plans. That response is associated with Change control board decision authority and does not directly settle this case. Its relevant principle is: Project change approval belongs to the defined authority; an engineer or requester cannot approve their own material scope change merely by agreeing verbally. The stated case instead calls for: Log a proposed project change and assess its effect on scope, cost, schedule, resources, and risk before seeking an approval decision. Situation: A manufacturing client asks to add plant locations after a signed network rollout plan is baselined.
Publish a focused agenda, assign facilitator and scribe, timebox discussion, and capture decisions with owners and due dates. That response is associated with Timeboxed effective project meetings and does not directly settle this case. Its relevant principle is: Meeting effectiveness depends on outcomes and follow-through, not on attendance or duration alone. The stated case instead calls for: Log a proposed project change and assess its effect on scope, cost, schedule, resources, and risk before seeking an approval decision. Situation: A manufacturing client asks to add plant locations after a signed network rollout plan is baselined.
Use approved contingency buffer for anticipated uncertainty and rebaseline only after an authorized material change rather than hiding every schedule slip. That response is associated with Schedule buffer and controlled rebaseline and does not directly settle this case. Its relevant principle is: Updating a forecast reflects current expectations; replacing the official baseline requires formal authorization and should not erase performance history. The stated case instead calls for: Log a proposed project change and assess its effect on scope, cost, schedule, resources, and risk before seeking an approval decision. Situation: A manufacturing client asks to add plant locations after a signed network rollout plan is baselined.