CompTIA N10-009 Practice Test 11
Question 100
A server and switch share a rack and need a supported 25-gigabit copper interconnect only two meters long. Which THREE entries correctly identify the applicable control, its technical principle, and a direct validation observation? (Select THREE.)
- Choose single-mode fiber and compatible long-distance transceivers within optical budget.
- Use an RJ11 telephone patch cord as a 25G Ethernet uplink.
- Short twinax DAC links can avoid optical modules for supported short distances.
- Replace DAC with distance-appropriate fiber transceivers and tested fiber plant.
- Use a vendor-supported 25G SFP28 direct attach cable meeting host port specifications.
- The negotiated rate and error counters match the supported DAC link characteristics.
Explanation
Correct Answers
C:Correct principle. Short twinax DAC links can avoid optical modules for supported short distances. This is the justification for the selected network control: Use a vendor-supported 25G SFP28 direct attach cable meeting host port specifications.
E:Correct control. Short twinax DAC links can avoid optical modules for supported short distances. It is the recommended implementation for this case.
F:Correct validation. The negotiated rate and error counters match the supported DAC link characteristics. This is the directly measurable result of the control.
Incorrect Answers
A:This is another scenario's control in the same domain: A carrier link crosses several kilometers between buildings, beyond the usual reach of multimode optics. It is not the best action for this case.
B:This control is invalid here. RJ11 wiring and interface specifications do not support a 25G server uplink. It does not meet the specified requirement.
D:This belongs to the changed condition, not the current three-part answer: The server moves to a different building hundreds of meters away. DAC range is too short for inter-building connectivity.
Question 101
A 100-gigabit backbone upgrade requires the correct optical module form factor for high-density aggregation ports. Which action MOST directly meets the stated networking requirement?
- Insert an arbitrary low-speed SFP module without checking aggregation port support.
- Choose compatible 10G short-range optical transceivers and multimode cabling.
- Use compatible QSFP-class modules and verify lane count, reach and connector type.
- Use supported MPO/MTP-style multifiber connections where optics specify them.
Explanation
Correct Answer
C:QSFP families commonly support high-speed multi-lane uplinks when ports and optics match. This specifically resolves: A 100-gigabit backbone upgrade requires the correct optical module form factor for high-density aggregation ports.
Incorrect Answers
A:Port form factor and electrical compatibility cannot be assumed interchangeable. The suggested approach is: Insert an arbitrary low-speed SFP module without checking aggregation port support.
B:This addresses another problem in objective 1.5: An access switch needs a 10-gigabit uplink over a short multimode fiber run inside a building.
D:This action responds to a later condition: The deployment adds many-fiber trunks into a patch cabinet. Multifiber optics require matching lane-to-fiber connector topology.
Question 102
A 100-gigabit backbone upgrade requires the correct optical module form factor for high-density aggregation ports. A colleague instead suggests: Insert an arbitrary low-speed SFP module without checking aggregation port support. Which finding MOST specifically explains why that suggestion is unsuitable?
- Port form factor and electrical compatibility cannot be assumed interchangeable.
- Incompatible modules or wavelengths may prevent the optical link from forming.
- Multifiber optics require matching lane-to-fiber connector topology.
- QSFP families commonly support high-speed multi-lane uplinks when ports and optics match.
Explanation
Correct Answer
A:Port form factor and electrical compatibility cannot be assumed interchangeable. This flaw directly concerns the proposed action: Insert an arbitrary low-speed SFP module without checking aggregation port support.
Incorrect Answers
B:This flaw concerns a different case in objective 1.5: An access switch needs a 10-gigabit uplink over a short multimode fiber run inside a building. The current rejected proposal is: Insert an arbitrary low-speed SFP module without checking aggregation port support.
C:This rationale belongs to a later changed condition: The deployment adds many-fiber trunks into a patch cabinet.
D:This explains why the recommended control works: Use compatible QSFP-class modules and verify lane count, reach and connector type.
Question 103
A 100-gigabit backbone upgrade requires the correct optical module form factor for high-density aggregation ports. After applying the solution 'Use compatible QSFP-class modules and verify lane count, reach and connector type.', which observation MOST directly proves that the requirement was met?
- Both ends establish the intended rate with acceptable optical levels and CRC counts.
- Approval is recorded for 'Use compatible QSFP-class modules and verify lane count, reach and connector type.' but no operational validation is performed.
- Inventory and interface diagnostics agree on module identity, speed and optical status.
- Installation inspection confirms required markings and compliant cable routing.
Explanation
Correct Answer
C:Inventory and interface diagnostics agree on module identity, speed and optical status. It tests the intended outcome because qsfp families commonly support high-speed multi-lane uplinks when ports and optics match.
Incorrect Answers
A:This observation is for a different condition: An access switch needs a 10-gigabit uplink over a short multimode fiber run inside a building. It does not directly test the target outcome: A 100-gigabit backbone upgrade requires the correct optical module form factor for high-density aggregation ports.
B:The missing direct test is: Inventory and interface diagnostics agree on module identity, speed and optical status.
D:This test addresses a separate problem: New cabling must run through an air-handling ceiling subject to local fire codes.
Question 104
The original case was: A 100-gigabit backbone upgrade requires the correct optical module form factor for high-density aggregation ports. The requirement then changes: The deployment adds many-fiber trunks into a patch cabinet. Which revised action BEST meets this new condition?
- Use compatible QSFP-class modules and verify lane count, reach and connector type.
- Use supported MPO/MTP-style multifiber connections where optics specify them.
- Insert an arbitrary low-speed SFP module without checking aggregation port support.
- Inventory and interface diagnostics agree on module identity, speed and optical status.
Explanation
Correct Answer
B:Multifiber optics require matching lane-to-fiber connector topology. The revised requirement is: The deployment adds many-fiber trunks into a patch cabinet. The appropriate action is: Use supported MPO/MTP-style multifiber connections where optics specify them.
Incorrect Answers
A:This is the original control. QSFP families commonly support high-speed multi-lane uplinks when ports and optics match. It does not directly satisfy the revised requirement: The deployment adds many-fiber trunks into a patch cabinet.
C:Port form factor and electrical compatibility cannot be assumed interchangeable. It remains inappropriate in the revised context.
D:Inventory and interface diagnostics agree on module identity, speed and optical status. The current requirement is: The deployment adds many-fiber trunks into a patch cabinet.
Question 105
A datacenter needs predictable east-west server connectivity with multiple equal-cost paths between racks. Which action MOST directly meets the stated networking requirement?
- Use a hub-and-spoke WAN with resilient hub connectivity and controlled routes.
- Use a leaf-spine fabric with appropriate routing and equal-cost multipath.
- Consider a collapsed-core design where scale and resilience allow it.
- Use one chained daisy-link switch path for all east-west traffic.
Explanation
Correct Answer
B:Leaf-spine reduces variable hop count between hosts and offers multiple fabric paths. This specifically resolves: A datacenter needs predictable east-west server connectivity with multiple equal-cost paths between racks.
Incorrect Answers
A:This addresses another problem in objective 1.6: Six remote offices need connectivity to a central ERP application and central security inspection.
C:This action responds to a later condition: The project changes to a small campus with limited distribution-switch budget. A small campus may consolidate core and distribution functions.
D:A linear chain adds hops and single points of failure. The suggested approach is: Use one chained daisy-link switch path for all east-west traffic.
Question 106
A datacenter needs predictable east-west server connectivity with multiple equal-cost paths between racks. A colleague instead suggests: Use one chained daisy-link switch path for all east-west traffic. Which finding MOST specifically explains why that suggestion is unsuitable?
- Leaf-spine reduces variable hop count between hosts and offers multiple fabric paths.
- A small campus may consolidate core and distribution functions.
- A full mesh increases connections and operational complexity unnecessarily.
- A linear chain adds hops and single points of failure.
Explanation
Correct Answer
D:A linear chain adds hops and single points of failure. This flaw directly concerns the proposed action: Use one chained daisy-link switch path for all east-west traffic.
Incorrect Answers
A:This explains why the recommended control works: Use a leaf-spine fabric with appropriate routing and equal-cost multipath.
B:This rationale belongs to a later changed condition: The project changes to a small campus with limited distribution-switch budget.
C:This flaw concerns a different case in objective 1.6: Six remote offices need connectivity to a central ERP application and central security inspection. The current rejected proposal is: Use one chained daisy-link switch path for all east-west traffic.
Question 107
A datacenter needs predictable east-west server connectivity with multiple equal-cost paths between racks. After applying the solution 'Use a leaf-spine fabric with appropriate routing and equal-cost multipath.', which observation MOST directly proves that the requirement was met?
- Path testing shows ECMP distribution and consistent rack-to-rack reachability.
- Disruption tests confirm traffic reroutes through remaining mesh paths.
- Route verification shows each branch reaches central services and unnecessary branch paths are blocked.
- Approval is recorded for 'Use a leaf-spine fabric with appropriate routing and equal-cost multipath.' but no operational validation is performed.
Explanation
Correct Answer
A:Path testing shows ECMP distribution and consistent rack-to-rack reachability. It tests the intended outcome because leaf-spine reduces variable hop count between hosts and offers multiple fabric paths.
Incorrect Answers
B:This test addresses a separate problem: A research backbone must maintain peer reachability after losing any one of several inter-site links.
C:This observation is for a different condition: Six remote offices need connectivity to a central ERP application and central security inspection. It does not directly test the target outcome: A datacenter needs predictable east-west server connectivity with multiple equal-cost paths between racks.
D:The missing direct test is: Path testing shows ECMP distribution and consistent rack-to-rack reachability.
Question 108
The original case was: A datacenter needs predictable east-west server connectivity with multiple equal-cost paths between racks. The requirement then changes: The project changes to a small campus with limited distribution-switch budget. Which revised action BEST meets this new condition?
- Consider a collapsed-core design where scale and resilience allow it.
- Path testing shows ECMP distribution and consistent rack-to-rack reachability.
- Use one chained daisy-link switch path for all east-west traffic.
- Use a leaf-spine fabric with appropriate routing and equal-cost multipath.
Explanation
Correct Answer
A:A small campus may consolidate core and distribution functions. The revised requirement is: The project changes to a small campus with limited distribution-switch budget. The appropriate action is: Consider a collapsed-core design where scale and resilience allow it.
Incorrect Answers
B:Path testing shows ECMP distribution and consistent rack-to-rack reachability. The current requirement is: The project changes to a small campus with limited distribution-switch budget.
C:A linear chain adds hops and single points of failure. It remains inappropriate in the revised context.
D:This is the original control. Leaf-spine reduces variable hop count between hosts and offers multiple fabric paths. It does not directly satisfy the revised requirement: The project changes to a small campus with limited distribution-switch budget.
Question 109
A university wants separate access, distribution and core roles for a growing campus. Which action MOST directly meets the stated networking requirement?
- Give every access switch an independent internet route with no distribution structure.
- Implement a three-tier hierarchical design with redundant uplinks at each role.
- Use a scaled-down collapsed core with appropriately managed redundancy.
- Design redundant mesh paths with tested routing convergence.
Explanation
Correct Answer
B:Layered roles help scale policy, aggregation and backbone transport. This specifically resolves: A university wants separate access, distribution and core roles for a growing campus.
Incorrect Answers
A:Flat unmanaged design complicates segmentation and operational control. The suggested approach is: Give every access switch an independent internet route with no distribution structure.
C:This action responds to a later condition: A small branch only needs two layers and a few switches. Simpler campus size can justify fewer hierarchical layers.
D:This addresses another problem in objective 1.6: A research backbone must maintain peer reachability after losing any one of several inter-site links.
Question 110
A university wants separate access, distribution and core roles for a growing campus. A colleague instead suggests: Give every access switch an independent internet route with no distribution structure. Which finding MOST specifically explains why that suggestion is unsuitable?
- Simpler campus size can justify fewer hierarchical layers.
- Layered roles help scale policy, aggregation and backbone transport.
- Flat unmanaged design complicates segmentation and operational control.
- A single hub or circuit becomes a common point of failure.
Explanation
Correct Answer
C:Flat unmanaged design complicates segmentation and operational control. This flaw directly concerns the proposed action: Give every access switch an independent internet route with no distribution structure.
Incorrect Answers
A:This rationale belongs to a later changed condition: A small branch only needs two layers and a few switches.
B:This explains why the recommended control works: Implement a three-tier hierarchical design with redundant uplinks at each role.
D:This flaw concerns a different case in objective 1.6: A research backbone must maintain peer reachability after losing any one of several inter-site links. The current rejected proposal is: Give every access switch an independent internet route with no distribution structure.