PRINCE2 PRINCE2 7 Practitioner Practice Test 89
Question 880
The service owner is reviewing actions after this report: a flood warning system predicts acceptance delays beyond the delegated stage time limit. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Submit the completed initiation documentation and initial stage plan for formal board authorization
- Produce a proportionate project brief and outline business case to support initiation authorization
- Execute the agreed work package and its quality activities under team management control
- Conceal the forecast and wait until tolerance is actually breached
Explanation
Correct Answer
D:The unsafe shortcut is to conceal the forecast and wait until tolerance is actually breached. Exception management is based on forecast tolerance breaches and decision rights. The defensible response is instead to produce an exception report and escalate the forecast to the project board promptly, using the diagnostic step to compare predicted final stage outcome with approved time, cost, scope and quality tolerances before changing settings. Afterward, the team should confirm this result: Board-level direction is requested before continuing work beyond delegated limits. It must maintain the safeguard to refresh tolerance forecasts as corrective actions or risk assumptions change. By contrast, the response tied to this evidence is: Conceal the forecast and wait until tolerance is actually breached.
Incorrect Answers
A:Submit the completed initiation documentation and initial stage plan for formal board authorization. The project board authorizes the project and first management stage on coherent evidence. Board-level direction is requested before continuing work beyond delegated limits. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.
B:Produce a proportionate project brief and outline business case to support initiation authorization. The board can approve or reject initiation on a coherent brief with clear assumptions. Board-level direction is requested before continuing work beyond delegated limits. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.
C:Execute the agreed work package and its quality activities under team management control. The team produces quality-verified deliverables that can be formally handed over. Board-level direction is requested before continuing work beyond delegated limits. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.
Question 881
A project sponsor describes this requirement: a supplier team receives a complex integration request but begins work without agreeing quality tests. Which step best meets it without creating unnecessary access? Select ONE answer.
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Define proportionate agreed approaches for risk, issues, quality, communications, change and project information
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Submit tested products with required handover evidence and obtain authorized acceptance
Explanation
Correct Answer
A:First, review the authorized work package for capacity, dependencies and acceptance conditions. Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Managing product delivery starts with clear agreement on delegated work. Success requires: Team and project manager share an agreed deliverable commitment before work starts. Repeating reconfirm package acceptance when authorized changes alter the delivery obligation helps prevent recurrence.
Incorrect Answers
B:Define proportionate agreed approaches for risk, issues, quality, communications, change and project information. Coordinated project controls must be established before distributed delivery begins. Team and project manager share an agreed deliverable commitment before work starts.
C:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. Team and project manager share an agreed deliverable commitment before work starts.
D:Submit tested products with required handover evidence and obtain authorized acceptance. The receiving authority acknowledges accepted products and remaining obligations. Team and project manager share an agreed deliverable commitment before work starts.
Question 882
A project manager needs to diagnose this problem: a supplier team receives a complex integration request but begins work without agreeing quality tests. Which investigation is the best initial check? Select ONE answer.
- Compare planned and actual project outcomes to identify causes and reusable practices
- Review the authorized work package for capacity, dependencies and acceptance conditions
- Compare issue effects on product descriptions, stage forecasts and decision limits
- Inspect the project brief and identify missing organization, quality, risk, issue and progress controls
Explanation
Correct Answer
B:The strongest first investigation is to review the authorized work package for capacity, dependencies and acceptance conditions. Managing product delivery starts with clear agreement on delegated work. If that evidence confirms the issue, the team should negotiate and accept the work package with realistic scope, interfaces and quality criteria. A subsequent acceptance check should confirm this result: Team and project manager share an agreed deliverable commitment before work starts. This check produces evidence before any broad configuration change, avoiding the risky proposal to start any requested work immediately and negotiate acceptance only after it is built.
Incorrect Answers
A:Compare planned and actual project outcomes to identify causes and reusable practices. A final lessons report has actionable recommendations and accountable dissemination. Team and project manager share an agreed deliverable commitment before work starts. The relevant investigation is: Review the authorized work package for capacity, dependencies and acceptance conditions.
C:Compare issue effects on product descriptions, stage forecasts and decision limits. Approved issue actions and escalations remain traceable to the current stage baseline. Team and project manager share an agreed deliverable commitment before work starts. The relevant investigation is: Review the authorized work package for capacity, dependencies and acceptance conditions.
D:Inspect the project brief and identify missing organization, quality, risk, issue and progress controls. The board receives a coherent PID that establishes how the project will be managed and controlled. Team and project manager share an agreed deliverable commitment before work starts. The relevant investigation is: Review the authorized work package for capacity, dependencies and acceptance conditions.
Question 883
The project team has corrected a reported weakness: a supplier team receives a complex integration request but begins work without agreeing quality tests. Which acceptance result should the owner require? Select ONE answer.
- The board can assess desirability, viability and achievability before authorizing the project
- A final lessons report has actionable recommendations and accountable dissemination
- Team and project manager share an agreed deliverable commitment before work starts
- Recovery actions improve the forecast without changing unauthorized baselines
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to reconfirm package acceptance when authorized changes alter the delivery obligation. The decisive acceptance evidence is this result: Team and project manager share an agreed deliverable commitment before work starts. Managing product delivery starts with clear agreement on delegated work. The operating team should diagnose it by checking whether it can review the authorized work package for capacity, dependencies and acceptance conditions, then negotiate and accept the work package with realistic scope, interfaces and quality criteria where justified.
Incorrect Answers
A:The board can assess desirability, viability and achievability before authorizing the project. Team and project manager share an agreed deliverable commitment before work starts.
B:A final lessons report has actionable recommendations and accountable dissemination. Team and project manager share an agreed deliverable commitment before work starts.
D:Recovery actions improve the forecast without changing unauthorized baselines. Team and project manager share an agreed deliverable commitment before work starts.
Question 884
The team has remediated this situation: a supplier team receives a complex integration request but begins work without agreeing quality tests. What maintenance control most directly reduces repeat failures? Select ONE answer.
- Monitor corrective-action effects on cost, quality and dependencies
- Replan at stage boundaries using updated evidence
- Conduct planned post-project reviews outside the closed delivery project
- Reconfirm package acceptance when authorized changes alter the delivery obligation
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to negotiate and accept the work package with realistic scope, interfaces and quality criteria and diagnostic evidence to review the authorized work package for capacity, dependencies and acceptance conditions. Periodic testing should confirm this result: Team and project manager share an agreed deliverable commitment before work starts. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to reconfirm package acceptance when authorized changes alter the delivery obligation. Managing product delivery starts with clear agreement on delegated work.
Incorrect Answers
A:Monitor corrective-action effects on cost, quality and dependencies. Recovery actions improve the forecast without changing unauthorized baselines. Team and project manager share an agreed deliverable commitment before work starts. To avoid recurrence, reconfirm package acceptance when authorized changes alter the delivery obligation.
B:Replan at stage boundaries using updated evidence. The board can authorize staged delivery against a defensible project baseline. Team and project manager share an agreed deliverable commitment before work starts. To avoid recurrence, reconfirm package acceptance when authorized changes alter the delivery obligation.
C:Conduct planned post-project reviews outside the closed delivery project. Some benefits mature after project closure and must have real ownership. Team and project manager share an agreed deliverable commitment before work starts. To avoid recurrence, reconfirm package acceptance when authorized changes alter the delivery obligation.
Question 885
The service owner is reviewing actions after this report: a supplier team receives a complex integration request but begins work without agreeing quality tests. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Start any requested work immediately and negotiate acceptance only after it is built
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Record residual issues, ownership, due dates and follow-on recommendations before closing
- Execute the agreed work package and its quality activities under team management control
Explanation
Correct Answer
A:The unsafe shortcut is to start any requested work immediately and negotiate acceptance only after it is built. Managing product delivery starts with clear agreement on delegated work. The defensible response is instead to negotiate and accept the work package with realistic scope, interfaces and quality criteria, using the diagnostic step to review the authorized work package for capacity, dependencies and acceptance conditions before changing settings. Afterward, the team should confirm this result: Team and project manager share an agreed deliverable commitment before work starts. It must maintain the safeguard to reconfirm package acceptance when authorized changes alter the delivery obligation.
Incorrect Answers
B:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. Team and project manager share an agreed deliverable commitment before work starts. The shortcut most directly implicated here is: Start any requested work immediately and negotiate acceptance only after it is built.
C:Record residual issues, ownership, due dates and follow-on recommendations before closing. The board approves closure with clear transfer of every outstanding responsibility. Team and project manager share an agreed deliverable commitment before work starts. The shortcut most directly implicated here is: Start any requested work immediately and negotiate acceptance only after it is built.
D:Execute the agreed work package and its quality activities under team management control. The team produces quality-verified deliverables that can be formally handed over. Team and project manager share an agreed deliverable commitment before work starts. The shortcut most directly implicated here is: Start any requested work immediately and negotiate acceptance only after it is built.
Question 886
A PRINCE2 project manager receives this situation: a research analytics subcontractor is asked to deliver a report with an unclear owner and no acceptance deadline. Which targeted corrective action should be chosen? Select ONE answer.
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Submit tested products with required handover evidence and obtain authorized acceptance
- Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure
Explanation
Correct Answer
B:First, review the authorized work package for capacity, dependencies and acceptance conditions. Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Managing product delivery starts with clear agreement on delegated work. Success requires: Team and project manager share an agreed deliverable commitment before work starts. Repeating reconfirm package acceptance when authorized changes alter the delivery obligation helps prevent recurrence. By contrast, the response tied to this evidence is: Negotiate and accept the work package with realistic scope, interfaces and quality criteria.
Incorrect Answers
A:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. Team and project manager share an agreed deliverable commitment before work starts.
C:Submit tested products with required handover evidence and obtain authorized acceptance. The receiving authority acknowledges accepted products and remaining obligations. Team and project manager share an agreed deliverable commitment before work starts. By contrast, the response tied to this evidence is: Negotiate and accept the work package with realistic scope, interfaces and quality criteria.
D:Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. Project closure is a governance decision informed by benefits and operational readiness. Team and project manager share an agreed deliverable commitment before work starts.
Question 887
A support engineer investigates this project governance report: a research analytics subcontractor is asked to deliver a report with an unclear owner and no acceptance deadline. Which comparison should be made first? Select ONE answer.
- Compare delivery evidence and unresolved findings with the agreed work package description
- Review relevant lesson evidence and the proposed governance arrangement
- Review the authorized work package for capacity, dependencies and acceptance conditions
- Inspect the project brief and identify missing organization, quality, risk, issue and progress controls
Explanation
Correct Answer
C:The strongest first investigation is to review the authorized work package for capacity, dependencies and acceptance conditions. Managing product delivery starts with clear agreement on delegated work. If that evidence confirms the issue, the team should negotiate and accept the work package with realistic scope, interfaces and quality criteria. A subsequent acceptance check should confirm this result: Team and project manager share an agreed deliverable commitment before work starts. This check produces evidence before any broad configuration change, avoiding the risky proposal to start any requested work immediately and negotiate acceptance only after it is built. By contrast, the response tied to this evidence is: Review the authorized work package for capacity, dependencies and acceptance conditions.
Incorrect Answers
A:Compare delivery evidence and unresolved findings with the agreed work package description. The receiving authority acknowledges accepted products and remaining obligations. Team and project manager share an agreed deliverable commitment before work starts. The relevant investigation is: Review the authorized work package for capacity, dependencies and acceptance conditions.
B:Review relevant lesson evidence and the proposed governance arrangement. The start-up documentation demonstrates applied learning and workable responsibilities. Team and project manager share an agreed deliverable commitment before work starts. The relevant investigation is: Review the authorized work package for capacity, dependencies and acceptance conditions.
D:Inspect the project brief and identify missing organization, quality, risk, issue and progress controls. The board receives a coherent PID that establishes how the project will be managed and controlled. Team and project manager share an agreed deliverable commitment before work starts. The relevant investigation is: Review the authorized work package for capacity, dependencies and acceptance conditions. This check produces evidence before any broad configuration change, avoiding the risky proposal to start any requested work immediately and negotiate acceptance only after it is built.
Question 888
An auditor asks how to validate resolution of this situation: a research analytics subcontractor is asked to deliver a report with an unclear owner and no acceptance deadline. Which direct evidence is strongest? Select ONE answer.
- A final lessons report has actionable recommendations and accountable dissemination
- The board can see what worked, what failed and how the next stage will improve
- The project approach is justified and can support realistic initiation planning
- Team and project manager share an agreed deliverable commitment before work starts
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to reconfirm package acceptance when authorized changes alter the delivery obligation. The decisive acceptance evidence is this result: Team and project manager share an agreed deliverable commitment before work starts. Managing product delivery starts with clear agreement on delegated work. The operating team should diagnose it by checking whether it can review the authorized work package for capacity, dependencies and acceptance conditions, then negotiate and accept the work package with realistic scope, interfaces and quality criteria where justified. By contrast, the response tied to this evidence is: Team and project manager share an agreed deliverable commitment before work starts.
Incorrect Answers
A:A final lessons report has actionable recommendations and accountable dissemination. Team and project manager share an agreed deliverable commitment before work starts. The operating team should diagnose it by checking whether it can review the authorized work package for capacity, dependencies and acceptance conditions, then negotiate and accept the work package with realistic scope, interfaces and quality criteria where justified.
B:The board can see what worked, what failed and how the next stage will improve. Team and project manager share an agreed deliverable commitment before work starts.
C:The project approach is justified and can support realistic initiation planning. An early approach decision should be informed rather than prematurely irreversible. Team and project manager share an agreed deliverable commitment before work starts.
Question 889
The project executive wants lasting assurance after this event: a research analytics subcontractor is asked to deliver a report with an unclear owner and no acceptance deadline. Which preventive practice should be adopted? Select ONE answer.
- Reconfirm package acceptance when authorized changes alter the delivery obligation
- Review work package interfaces when dependencies or product criteria change
- Replan successive stages using lessons and updated risk forecasts
- Replan at stage boundaries using updated evidence
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to negotiate and accept the work package with realistic scope, interfaces and quality criteria and diagnostic evidence to review the authorized work package for capacity, dependencies and acceptance conditions. Periodic testing should confirm this result: Team and project manager share an agreed deliverable commitment before work starts. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to reconfirm package acceptance when authorized changes alter the delivery obligation. Managing product delivery starts with clear agreement on delegated work. By contrast, the response tied to this evidence is: Reconfirm package acceptance when authorized changes alter the delivery obligation.
Incorrect Answers
B:Review work package interfaces when dependencies or product criteria change. The team manager accepts a clear scope and reports against defined products and tolerances. Team and project manager share an agreed deliverable commitment before work starts. To avoid recurrence, reconfirm package acceptance when authorized changes alter the delivery obligation.
C:Replan successive stages using lessons and updated risk forecasts. Stage boundaries create informed authorization points instead of unconditional funding. Team and project manager share an agreed deliverable commitment before work starts. To avoid recurrence, reconfirm package acceptance when authorized changes alter the delivery obligation.
D:Replan at stage boundaries using updated evidence. The board can authorize staged delivery against a defensible project baseline. Team and project manager share an agreed deliverable commitment before work starts. To avoid recurrence, reconfirm package acceptance when authorized changes alter the delivery obligation. Periodic testing should confirm this result: Team and project manager share an agreed deliverable commitment before work starts.
Question 890
An operator suggests skipping safeguards after this event: a research analytics subcontractor is asked to deliver a report with an unclear owner and no acceptance deadline. Which action should be ruled out? Select ONE answer.
- Present the exception and alternatives for an authorized project board decision
- Start any requested work immediately and negotiate acceptance only after it is built
- Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions
- Produce an exception report and escalate the forecast to the project board promptly
Explanation
Correct Answer
B:The unsafe shortcut is to start any requested work immediately and negotiate acceptance only after it is built. Managing product delivery starts with clear agreement on delegated work. The defensible response is instead to negotiate and accept the work package with realistic scope, interfaces and quality criteria, using the diagnostic step to review the authorized work package for capacity, dependencies and acceptance conditions before changing settings. Afterward, the team should confirm this result: Team and project manager share an agreed deliverable commitment before work starts. It must maintain the safeguard to reconfirm package acceptance when authorized changes alter the delivery obligation. By contrast, the response tied to this evidence is: Start any requested work immediately and negotiate acceptance only after it is built.
Incorrect Answers
A:Present the exception and alternatives for an authorized project board decision. A documented board decision approves revised tolerances, changes direction or stops the work. Team and project manager share an agreed deliverable commitment before work starts. The shortcut most directly implicated here is: Start any requested work immediately and negotiate acceptance only after it is built.
C:Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. The board can authorize staged delivery against a defensible project baseline. Team and project manager share an agreed deliverable commitment before work starts. The shortcut most directly implicated here is: Start any requested work immediately and negotiate acceptance only after it is built.
D:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. Team and project manager share an agreed deliverable commitment before work starts. The shortcut most directly implicated here is: Start any requested work immediately and negotiate acceptance only after it is built.