PRINCE2 PRINCE2 7 Practitioner Practice Test 88
Question 870
A team wants to simplify its response to this situation: a regional ferry software pilot has a quality delay that can be recovered using existing contingency. Which shortcut is the LEAST defensible? Select ONE answer.
- Provide timely checkpoint progress, issues and forecast updates to the project manager
- Request emergency board permission for every minor in-tolerance scheduling adjustment
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions
Explanation
Correct Answer
B:The unsafe shortcut is to request emergency board permission for every minor in-tolerance scheduling adjustment. The project manager should manage in-tolerance deviations rather than escalate every task problem. The defensible response is instead to select and authorize proportionate corrective action within the project manager's delegated authority, using the diagnostic step to inspect the stage plan, forecast and available recovery options before adjusting work before changing settings. Afterward, the team should confirm this result: Recovery actions improve the forecast without changing unauthorized baselines. It must maintain the safeguard to monitor corrective-action effects on cost, quality and dependencies. By contrast, the response tied to this evidence is: Request emergency board permission for every minor in-tolerance scheduling adjustment.
Incorrect Answers
A:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. The project manager should manage in-tolerance deviations rather than escalate every task problem. The shortcut most directly implicated here is: Request emergency board permission for every minor in-tolerance scheduling adjustment.
C:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. The project manager should manage in-tolerance deviations rather than escalate every task problem. The shortcut most directly implicated here is: Request emergency board permission for every minor in-tolerance scheduling adjustment.
D:Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. The board can authorize staged delivery against a defensible project baseline. The project manager should manage in-tolerance deviations rather than escalate every task problem. The shortcut most directly implicated here is: Request emergency board permission for every minor in-tolerance scheduling adjustment.
Question 871
A project delivery team reports that a national passport services rollout forecasts expenditure outside stage cost tolerance. Which action directly addresses the issue? Select ONE answer.
- Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure
- Present the exception and alternatives for an authorized project board decision
- Produce an exception report and escalate the forecast to the project board promptly
- Record residual issues, ownership, due dates and follow-on recommendations before closing
Explanation
Correct Answer
C:First, compare predicted final stage outcome with approved time, cost, scope and quality tolerances. Produce an exception report and escalate the forecast to the project board promptly. The reported operational condition is that a national passport services rollout forecasts expenditure outside stage cost tolerance. Exception management is based on forecast tolerance breaches and decision rights. Success requires: Board-level direction is requested before continuing work beyond delegated limits. Repeating refresh tolerance forecasts as corrective actions or risk assumptions change helps prevent recurrence.
Incorrect Answers
A:Give the project board evidence of acceptance, remaining issues, lessons and benefits arrangements before requesting closure. Project closure is a governance decision informed by benefits and operational readiness. Exception management is based on forecast tolerance breaches and decision rights.
B:Present the exception and alternatives for an authorized project board decision. A documented board decision approves revised tolerances, changes direction or stops the work. Exception management is based on forecast tolerance breaches and decision rights.
D:Record residual issues, ownership, due dates and follow-on recommendations before closing. The board approves closure with clear transfer of every outstanding responsibility. Exception management is based on forecast tolerance breaches and decision rights.
Question 872
An administrator wants to identify the failure before making a change: a national passport services rollout forecasts expenditure outside stage cost tolerance. Which inspection is the most informative? Select ONE answer.
- Inspect remaining defects, contracts and operational obligations against handover acceptance
- Compare preliminary user objectives, constraints, risks and known delivery options
- Review relevant lesson evidence and the proposed governance arrangement
- Compare predicted final stage outcome with approved time, cost, scope and quality tolerances
Explanation
Correct Answer
D:The strongest first investigation is to compare predicted final stage outcome with approved time, cost, scope and quality tolerances. Exception management is based on forecast tolerance breaches and decision rights. If that evidence confirms the issue, the team should produce an exception report and escalate the forecast to the project board promptly. A subsequent acceptance check should confirm this result: Board-level direction is requested before continuing work beyond delegated limits. This check produces evidence before any broad configuration change, avoiding the risky proposal to conceal the forecast and wait until tolerance is actually breached.
Incorrect Answers
A:Inspect remaining defects, contracts and operational obligations against handover acceptance. The board approves closure with clear transfer of every outstanding responsibility. Exception management is based on forecast tolerance breaches and decision rights. The relevant investigation is: Compare predicted final stage outcome with approved time, cost, scope and quality tolerances.
B:Compare preliminary user objectives, constraints, risks and known delivery options. The board can approve or reject initiation on a coherent brief with clear assumptions. Exception management is based on forecast tolerance breaches and decision rights. The relevant investigation is: Compare predicted final stage outcome with approved time, cost, scope and quality tolerances.
C:Review relevant lesson evidence and the proposed governance arrangement. The start-up documentation demonstrates applied learning and workable responsibilities. Exception management is based on forecast tolerance breaches and decision rights. The relevant investigation is: Compare predicted final stage outcome with approved time, cost, scope and quality tolerances.
Question 873
After a controlled change, the team needs to resolve this report: a national passport services rollout forecasts expenditure outside stage cost tolerance. Which observable result would best establish success? Select ONE answer.
- Board-level direction is requested before continuing work beyond delegated limits
- The board decides whether continued investment remains appropriate with transparent tradeoffs
- The team produces quality-verified deliverables that can be formally handed over
- A working board and delivery organization are documented with accountable decisions and checks
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to refresh tolerance forecasts as corrective actions or risk assumptions change. The decisive acceptance evidence is this result: Board-level direction is requested before continuing work beyond delegated limits. Exception management is based on forecast tolerance breaches and decision rights. The operating team should diagnose it by checking whether it can compare predicted final stage outcome with approved time, cost, scope and quality tolerances, then produce an exception report and escalate the forecast to the project board promptly where justified.
Incorrect Answers
B:The board decides whether continued investment remains appropriate with transparent tradeoffs. Exception management is based on forecast tolerance breaches and decision rights. Success in this case requires: Board-level direction is requested before continuing work beyond delegated limits.
C:The team produces quality-verified deliverables that can be formally handed over. Exception management is based on forecast tolerance breaches and decision rights. Success in this case requires: Board-level direction is requested before continuing work beyond delegated limits.
D:A working board and delivery organization are documented with accountable decisions and checks. Exception management is based on forecast tolerance breaches and decision rights. Success in this case requires: Board-level direction is requested before continuing work beyond delegated limits.
Question 874
A project assurance reviewer sees a pattern in this report: a national passport services rollout forecasts expenditure outside stage cost tolerance. Which recurring safeguard should remain in force? Select ONE answer.
- Track transferred actions in operational governance after project closure
- Refresh tolerance forecasts as corrective actions or risk assumptions change
- Reconfirm package acceptance when authorized changes alter the delivery obligation
- Reconfirm role assignments when partners and project governance change
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to produce an exception report and escalate the forecast to the project board promptly and diagnostic evidence to compare predicted final stage outcome with approved time, cost, scope and quality tolerances. Periodic testing should confirm this result: Board-level direction is requested before continuing work beyond delegated limits. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to refresh tolerance forecasts as corrective actions or risk assumptions change. Exception management is based on forecast tolerance breaches and decision rights.
Incorrect Answers
A:Track transferred actions in operational governance after project closure. The board approves closure with clear transfer of every outstanding responsibility. Exception management is based on forecast tolerance breaches and decision rights. To avoid recurrence, refresh tolerance forecasts as corrective actions or risk assumptions change.
C:Reconfirm package acceptance when authorized changes alter the delivery obligation. Team and project manager share an agreed deliverable commitment before work starts. Exception management is based on forecast tolerance breaches and decision rights. To avoid recurrence, refresh tolerance forecasts as corrective actions or risk assumptions change.
D:Reconfirm role assignments when partners and project governance change. A working board and delivery organization are documented with accountable decisions and checks. Exception management is based on forecast tolerance breaches and decision rights. To avoid recurrence, refresh tolerance forecasts as corrective actions or risk assumptions change.
Question 875
A team wants to simplify its response to this situation: a national passport services rollout forecasts expenditure outside stage cost tolerance. Which shortcut is the LEAST defensible? Select ONE answer.
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
- Present the exception and alternatives for an authorized project board decision
- Conceal the forecast and wait until tolerance is actually breached
- Submit tested products with required handover evidence and obtain authorized acceptance
Explanation
Correct Answer
C:The unsafe shortcut is to conceal the forecast and wait until tolerance is actually breached. Exception management is based on forecast tolerance breaches and decision rights. The defensible response is instead to produce an exception report and escalate the forecast to the project board promptly, using the diagnostic step to compare predicted final stage outcome with approved time, cost, scope and quality tolerances before changing settings. Afterward, the team should confirm this result: Board-level direction is requested before continuing work beyond delegated limits. It must maintain the safeguard to refresh tolerance forecasts as corrective actions or risk assumptions change.
Incorrect Answers
A:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. Exception management is based on forecast tolerance breaches and decision rights. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.
B:Present the exception and alternatives for an authorized project board decision. A documented board decision approves revised tolerances, changes direction or stops the work. Exception management is based on forecast tolerance breaches and decision rights. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.
D:Submit tested products with required handover evidence and obtain authorized acceptance. The receiving authority acknowledges accepted products and remaining obligations. Exception management is based on forecast tolerance breaches and decision rights. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.
Question 876
A project sponsor describes this requirement: a flood warning system predicts acceptance delays beyond the delegated stage time limit. Which step best meets it without creating unnecessary access? Select ONE answer.
- Authorize a work package with products, acceptance, reporting and agreed constraints
- Prepare and seek approval of an exception plan that replaces the relevant affected plan
- Have the project board assess the project brief and authorize a bounded initiation stage
- Produce an exception report and escalate the forecast to the project board promptly
Explanation
Correct Answer
D:First, compare predicted final stage outcome with approved time, cost, scope and quality tolerances. Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. Success requires: Board-level direction is requested before continuing work beyond delegated limits. Repeating refresh tolerance forecasts as corrective actions or risk assumptions change helps prevent recurrence.
Incorrect Answers
A:Authorize a work package with products, acceptance, reporting and agreed constraints. The team manager accepts a clear scope and reports against defined products and tolerances. Board-level direction is requested before continuing work beyond delegated limits.
B:Prepare and seek approval of an exception plan that replaces the relevant affected plan. The revised plan is explicitly approved with renewed tolerances and managed dependencies. Board-level direction is requested before continuing work beyond delegated limits.
C:Have the project board assess the project brief and authorize a bounded initiation stage. Initiation expenditure is explicitly authorized without pre-approving the entire project. Board-level direction is requested before continuing work beyond delegated limits.
Question 877
A project manager needs to diagnose this problem: a flood warning system predicts acceptance delays beyond the delegated stage time limit. Which investigation is the best initial check? Select ONE answer.
- Compare predicted final stage outcome with approved time, cost, scope and quality tolerances
- Compare completed products and test evidence with the package's acceptance criteria
- Compare decision rights and role coverage with business, user and supplier interests
- Inspect the agreed reporting cadence and quality/dependency evidence
Explanation
Correct Answer
A:The strongest first investigation is to compare predicted final stage outcome with approved time, cost, scope and quality tolerances. Exception management is based on forecast tolerance breaches and decision rights. If that evidence confirms the issue, the team should produce an exception report and escalate the forecast to the project board promptly. A subsequent acceptance check should confirm this result: Board-level direction is requested before continuing work beyond delegated limits. This check produces evidence before any broad configuration change, avoiding the risky proposal to conceal the forecast and wait until tolerance is actually breached. By contrast, the response tied to this evidence is: Compare predicted final stage outcome with approved time, cost, scope and quality tolerances.
Incorrect Answers
B:Compare completed products and test evidence with the package's acceptance criteria. The team produces quality-verified deliverables that can be formally handed over. Board-level direction is requested before continuing work beyond delegated limits. The relevant investigation is: Compare predicted final stage outcome with approved time, cost, scope and quality tolerances.
C:Compare decision rights and role coverage with business, user and supplier interests. A working board and delivery organization are documented with accountable decisions and checks. Board-level direction is requested before continuing work beyond delegated limits. The relevant investigation is: Compare predicted final stage outcome with approved time, cost, scope and quality tolerances.
D:Inspect the agreed reporting cadence and quality/dependency evidence. Stage forecasts reflect actual work package progress and risks before failure. Board-level direction is requested before continuing work beyond delegated limits. The relevant investigation is: Compare predicted final stage outcome with approved time, cost, scope and quality tolerances.
Question 878
The project team has corrected a reported weakness: a flood warning system predicts acceptance delays beyond the delegated stage time limit. Which acceptance result should the owner require? Select ONE answer.
- Approved issue actions and escalations remain traceable to the current stage baseline
- Board-level direction is requested before continuing work beyond delegated limits
- The board receives a credible next-stage plan with justified commitments and tolerances
- The board receives a coherent PID that establishes how the project will be managed and controlled
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to refresh tolerance forecasts as corrective actions or risk assumptions change. The decisive acceptance evidence is this result: Board-level direction is requested before continuing work beyond delegated limits. Exception management is based on forecast tolerance breaches and decision rights. The operating team should diagnose it by checking whether it can compare predicted final stage outcome with approved time, cost, scope and quality tolerances, then produce an exception report and escalate the forecast to the project board promptly where justified. By contrast, the response tied to this evidence is: Board-level direction is requested before continuing work beyond delegated limits.
Incorrect Answers
A:Approved issue actions and escalations remain traceable to the current stage baseline. Board-level direction is requested before continuing work beyond delegated limits.
C:The board receives a credible next-stage plan with justified commitments and tolerances. Stage boundaries create informed authorization points instead of unconditional funding. Board-level direction is requested before continuing work beyond delegated limits.
D:The board receives a coherent PID that establishes how the project will be managed and controlled. Board-level direction is requested before continuing work beyond delegated limits.
Question 879
The team has remediated this situation: a flood warning system predicts acceptance delays beyond the delegated stage time limit. What maintenance control most directly reduces repeat failures? Select ONE answer.
- Track exception decisions and the approved replacement baseline
- Reconfirm role assignments when partners and project governance change
- Refresh tolerance forecasts as corrective actions or risk assumptions change
- Track transferred actions in operational governance after project closure
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to produce an exception report and escalate the forecast to the project board promptly and diagnostic evidence to compare predicted final stage outcome with approved time, cost, scope and quality tolerances. Periodic testing should confirm this result: Board-level direction is requested before continuing work beyond delegated limits. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to refresh tolerance forecasts as corrective actions or risk assumptions change. Exception management is based on forecast tolerance breaches and decision rights. By contrast, the response tied to this evidence is: Refresh tolerance forecasts as corrective actions or risk assumptions change.
Incorrect Answers
A:Track exception decisions and the approved replacement baseline. A documented board decision approves revised tolerances, changes direction or stops the work. Board-level direction is requested before continuing work beyond delegated limits. To avoid recurrence, refresh tolerance forecasts as corrective actions or risk assumptions change.
B:Reconfirm role assignments when partners and project governance change. A working board and delivery organization are documented with accountable decisions and checks. Board-level direction is requested before continuing work beyond delegated limits. To avoid recurrence, refresh tolerance forecasts as corrective actions or risk assumptions change.
D:Track transferred actions in operational governance after project closure. The board approves closure with clear transfer of every outstanding responsibility. Board-level direction is requested before continuing work beyond delegated limits. To avoid recurrence, refresh tolerance forecasts as corrective actions or risk assumptions change.
Question 880
The service owner is reviewing actions after this report: a flood warning system predicts acceptance delays beyond the delegated stage time limit. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Submit the completed initiation documentation and initial stage plan for formal board authorization
- Produce a proportionate project brief and outline business case to support initiation authorization
- Execute the agreed work package and its quality activities under team management control
- Conceal the forecast and wait until tolerance is actually breached
Explanation
Correct Answer
D:The unsafe shortcut is to conceal the forecast and wait until tolerance is actually breached. Exception management is based on forecast tolerance breaches and decision rights. The defensible response is instead to produce an exception report and escalate the forecast to the project board promptly, using the diagnostic step to compare predicted final stage outcome with approved time, cost, scope and quality tolerances before changing settings. Afterward, the team should confirm this result: Board-level direction is requested before continuing work beyond delegated limits. It must maintain the safeguard to refresh tolerance forecasts as corrective actions or risk assumptions change. By contrast, the response tied to this evidence is: Conceal the forecast and wait until tolerance is actually breached.
Incorrect Answers
A:Submit the completed initiation documentation and initial stage plan for formal board authorization. The project board authorizes the project and first management stage on coherent evidence. Board-level direction is requested before continuing work beyond delegated limits. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.
B:Produce a proportionate project brief and outline business case to support initiation authorization. The board can approve or reject initiation on a coherent brief with clear assumptions. Board-level direction is requested before continuing work beyond delegated limits. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.
C:Execute the agreed work package and its quality activities under team management control. The team produces quality-verified deliverables that can be formally handed over. Board-level direction is requested before continuing work beyond delegated limits. The shortcut most directly implicated here is: Conceal the forecast and wait until tolerance is actually breached.