PRINCE2 PRINCE2 7 Practitioner Practice Test 27
Question 260
A project manager is under pressure to address the following issue quickly: a renewable energy project has a vague project brief whose mandate cannot support an initiation decision. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Agree operational benefit owners and post-closure measurement arrangements before handover
- Specify measurable product quality criteria, methods and responsibilities before acceptance
- Assign accountable risk ownership and specific response action ownership with suitable authority
- Commit the full delivery budget based only on an untested preliminary project brief
Explanation
Correct Answer
D:The unsafe shortcut is to commit the full delivery budget based only on an untested preliminary project brief. Early governance should be proportionate to uncertainty and decision maturity. The defensible response is instead to use a proportionate outline business case and project brief to support initiation, then develop the full justification, using the diagnostic step to check the mandate, initial scope, constraints and preliminary benefit assumptions before changing settings. Afterward, the team should confirm this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. It must maintain the safeguard to refine justification and mandate traceability when initiating a project. By contrast, the response tied to this evidence is: Commit the full delivery budget based only on an untested preliminary project brief.
Incorrect Answers
A:Agree operational benefit owners and post-closure measurement arrangements before handover. Handover records identify accountable owners and scheduled benefit reviews after closure. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.
B:Specify measurable product quality criteria, methods and responsibilities before acceptance. Quality expectations must become testable acceptance evidence. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.
C:Assign accountable risk ownership and specific response action ownership with suitable authority. Material responses are implemented and monitored by identifiable responsible people. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.
Question 261
During a PRINCE2 management-stage review, the team encounters this situation: a local clinic opens a new appointment service but the operational sponsor declines responsibility for measuring wait-time reductions. What is the most appropriate controlled response? Select ONE answer.
- Agree operational benefit owners and post-closure measurement arrangements before handover
- Develop a product breakdown and product flow before deriving activities and resources
- Include measurable sustainability outcomes and material impacts in investment options and evaluation
- Reassess continuing desirability, viability and achievability before approval of the changed commitment
Explanation
Correct Answer
A:First, inspect acceptance records, benefits plan baselines and responsible business roles. Agree operational benefit owners and post-closure measurement arrangements before handover. The project manager does not personally realize every future operational benefit. Success requires: Handover records identify accountable owners and scheduled benefit reviews after closure. Repeating confirm operational ownership as part of closeout and business case updates helps prevent recurrence.
Incorrect Answers
B:Develop a product breakdown and product flow before deriving activities and resources. The plan covers required products in a logical sequence with explicit quality expectations. Handover records identify accountable owners and scheduled benefit reviews after closure.
C:Include measurable sustainability outcomes and material impacts in investment options and evaluation. The approved justification includes monitored sustainability indicators and credible tradeoffs. Handover records identify accountable owners and scheduled benefit reviews after closure.
D:Reassess continuing desirability, viability and achievability before approval of the changed commitment. A formal continue, adjust or stop decision is backed by the current business case. Handover records identify accountable owners and scheduled benefit reviews after closure.
Question 262
The project management team is troubleshooting this situation: a local clinic opens a new appointment service but the operational sponsor declines responsibility for measuring wait-time reductions. Which check isolates the likely operating dependency? Select ONE answer.
- Trace issue decisions through product descriptions, version records and acceptance evidence
- Inspect acceptance records, benefits plan baselines and responsible business roles
- Inspect stage product dependencies, assumptions, resource estimates and tolerances
- Compare available delivery capability against product requirements and supplier commitments
Explanation
Correct Answer
B:The strongest first investigation is to inspect acceptance records, benefits plan baselines and responsible business roles. The project manager does not personally realize every future operational benefit. If that evidence confirms the issue, the team should agree operational benefit owners and post-closure measurement arrangements before handover. A subsequent acceptance check should confirm this result: Handover records identify accountable owners and scheduled benefit reviews after closure. This check produces evidence before any broad configuration change, avoiding the risky proposal to close the benefits plan when the final software feature is deployed.
Incorrect Answers
A:Trace issue decisions through product descriptions, version records and acceptance evidence. Delivered and tested products correspond to the latest authorized baselines. Handover records identify accountable owners and scheduled benefit reviews after closure. The relevant investigation is: Inspect acceptance records, benefits plan baselines and responsible business roles.
C:Inspect stage product dependencies, assumptions, resource estimates and tolerances. The next stage has a realistic plan approved by the appropriate authority. Handover records identify accountable owners and scheduled benefit reviews after closure. The relevant investigation is: Inspect acceptance records, benefits plan baselines and responsible business roles.
D:Compare available delivery capability against product requirements and supplier commitments. Technical resource gaps are escalated through appropriate supplier governance. Handover records identify accountable owners and scheduled benefit reviews after closure. The relevant investigation is: Inspect acceptance records, benefits plan baselines and responsible business roles.
Question 263
An administrator claims the following problem is resolved: a local clinic opens a new appointment service but the operational sponsor declines responsibility for measuring wait-time reductions. Which measured outcome confirms that claim? Select ONE answer.
- The plan shows defensible estimates and tolerances consistent with identified uncertainty
- The issue log links each closure to objective evidence and the approved disposition
- Handover records identify accountable owners and scheduled benefit reviews after closure
- Reporting is proportionate yet produces reliable forecasts and clear authority decisions
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to confirm operational ownership as part of closeout and business case updates. The decisive acceptance evidence is this result: Handover records identify accountable owners and scheduled benefit reviews after closure. The project manager does not personally realize every future operational benefit. The operating team should diagnose it by checking whether it can inspect acceptance records, benefits plan baselines and responsible business roles, then agree operational benefit owners and post-closure measurement arrangements before handover where justified.
Incorrect Answers
A:The plan shows defensible estimates and tolerances consistent with identified uncertainty. Handover records identify accountable owners and scheduled benefit reviews after closure.
B:The issue log links each closure to objective evidence and the approved disposition. Decision approval and implemented resolution are different stages of issue management. Handover records identify accountable owners and scheduled benefit reviews after closure.
D:Reporting is proportionate yet produces reliable forecasts and clear authority decisions. Handover records identify accountable owners and scheduled benefit reviews after closure.
Question 264
After resolving the following issue, the operations team wants to prevent a recurrence: a local clinic opens a new appointment service but the operational sponsor declines responsibility for measuring wait-time reductions. Which ongoing control is best? Select ONE answer.
- Update product-based plans when scope or dependencies change
- Refresh forecasts and assumptions at defined progress checkpoints
- Revisit alternatives when conditions alter the preferred option
- Confirm operational ownership as part of closeout and business case updates
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to agree operational benefit owners and post-closure measurement arrangements before handover and diagnostic evidence to inspect acceptance records, benefits plan baselines and responsible business roles. Periodic testing should confirm this result: Handover records identify accountable owners and scheduled benefit reviews after closure. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to confirm operational ownership as part of closeout and business case updates. The project manager does not personally realize every future operational benefit.
Incorrect Answers
A:Update product-based plans when scope or dependencies change. The plan covers required products in a logical sequence with explicit quality expectations. Handover records identify accountable owners and scheduled benefit reviews after closure. To avoid recurrence, confirm operational ownership as part of closeout and business case updates.
B:Refresh forecasts and assumptions at defined progress checkpoints. The relevant authority receives an exception forecast before delegation limits are exceeded. Handover records identify accountable owners and scheduled benefit reviews after closure. To avoid recurrence, confirm operational ownership as part of closeout and business case updates.
C:Revisit alternatives when conditions alter the preferred option. A documented board choice reflects credible comparative value and explicit tradeoffs. Handover records identify accountable owners and scheduled benefit reviews after closure. To avoid recurrence, confirm operational ownership as part of closeout and business case updates.
Question 265
A project manager is under pressure to address the following issue quickly: a local clinic opens a new appointment service but the operational sponsor declines responsibility for measuring wait-time reductions. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Close the benefits plan when the final software feature is deployed
- Set reporting frequency and content proportionate to information needs and risk
- Assess issue impacts on scope, business case, benefits, risks, quality, schedule and resources before approval
- Include measurable sustainability outcomes and material impacts in investment options and evaluation
Explanation
Correct Answer
A:The unsafe shortcut is to close the benefits plan when the final software feature is deployed. The project manager does not personally realize every future operational benefit. The defensible response is instead to agree operational benefit owners and post-closure measurement arrangements before handover, using the diagnostic step to inspect acceptance records, benefits plan baselines and responsible business roles before changing settings. Afterward, the team should confirm this result: Handover records identify accountable owners and scheduled benefit reviews after closure. It must maintain the safeguard to confirm operational ownership as part of closeout and business case updates.
Incorrect Answers
B:Set reporting frequency and content proportionate to information needs and risk. The board receives timely progress forecasts and exceptions while teams receive usable controls. Handover records identify accountable owners and scheduled benefit reviews after closure. The shortcut most directly implicated here is: Close the benefits plan when the final software feature is deployed.
C:Assess issue impacts on scope, business case, benefits, risks, quality, schedule and resources before approval. Change control protects overall project viability rather than only the altered feature. Handover records identify accountable owners and scheduled benefit reviews after closure. The shortcut most directly implicated here is: Close the benefits plan when the final software feature is deployed.
D:Include measurable sustainability outcomes and material impacts in investment options and evaluation. The approved justification includes monitored sustainability indicators and credible tradeoffs. Handover records identify accountable owners and scheduled benefit reviews after closure. The shortcut most directly implicated here is: Close the benefits plan when the final software feature is deployed.
Question 266
A project delivery team reports that a municipal payments product is accepted while the benefits review schedule has no owner or baseline. Which action directly addresses the issue? Select ONE answer.
- Compare realistic options including do nothing using costs, benefits, risk and sustainability impacts
- Agree operational benefit owners and post-closure measurement arrangements before handover
- Identify and manage internal and external product dependencies in the appropriate plans
- Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register
Explanation
Correct Answer
B:First, inspect acceptance records, benefits plan baselines and responsible business roles. Agree operational benefit owners and post-closure measurement arrangements before handover. The reported operational condition is that a municipal payments product is accepted while the benefits review schedule has no owner or baseline. The project manager does not personally realize every future operational benefit. Success requires: Handover records identify accountable owners and scheduled benefit reviews after closure. Repeating confirm operational ownership as part of closeout and business case updates helps prevent recurrence.
Incorrect Answers
A:Compare realistic options including do nothing using costs, benefits, risk and sustainability impacts. A documented board choice reflects credible comparative value and explicit tradeoffs. The project manager does not personally realize every future operational benefit.
C:Identify and manage internal and external product dependencies in the appropriate plans. Upstream products are accepted before dependent work is committed beyond tolerance. The project manager does not personally realize every future operational benefit.
D:Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register. Decision-makers can understand exposure, response ownership and residual status from the register. The project manager does not personally realize every future operational benefit.
Question 267
An administrator wants to identify the failure before making a change: a municipal payments product is accepted while the benefits review schedule has no owner or baseline. Which inspection is the most informative? Select ONE answer.
- Compare role assignments, work package authority and actual approval records
- Check impact forecasts against change budget, tolerances and authorized decision rights
- Inspect acceptance records, benefits plan baselines and responsible business roles
- Compare delivered products and support materials with approved acceptance and transition criteria
Explanation
Correct Answer
C:The strongest first investigation is to inspect acceptance records, benefits plan baselines and responsible business roles. The project manager does not personally realize every future operational benefit. If that evidence confirms the issue, the team should agree operational benefit owners and post-closure measurement arrangements before handover. A subsequent acceptance check should confirm this result: Handover records identify accountable owners and scheduled benefit reviews after closure. This check produces evidence before any broad configuration change, avoiding the risky proposal to close the benefits plan when the final software feature is deployed. By contrast, the response tied to this evidence is: Inspect acceptance records, benefits plan baselines and responsible business roles.
Incorrect Answers
A:Compare role assignments, work package authority and actual approval records. Each major decision and delivery obligation maps to a competent accountable role. The project manager does not personally realize every future operational benefit. The relevant investigation is: Inspect acceptance records, benefits plan baselines and responsible business roles.
B:Check impact forecasts against change budget, tolerances and authorized decision rights. Issue decisions are formally recorded at the right governance level. The project manager does not personally realize every future operational benefit. The relevant investigation is: Inspect acceptance records, benefits plan baselines and responsible business roles.
D:Compare delivered products and support materials with approved acceptance and transition criteria. Receiving owners confirm the product is acceptable and usable in live operations. The project manager does not personally realize every future operational benefit. The relevant investigation is: Inspect acceptance records, benefits plan baselines and responsible business roles.
Question 268
After a controlled change, the team needs to resolve this report: a municipal payments product is accepted while the benefits review schedule has no owner or baseline. Which observable result would best establish success? Select ONE answer.
- The selected opportunity produces measurable value without violating risk tolerance
- The risk register covers material exposures with described causes and impacts
- Material responses are implemented and monitored by identifiable responsible people
- Handover records identify accountable owners and scheduled benefit reviews after closure
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to confirm operational ownership as part of closeout and business case updates. The decisive acceptance evidence is this result: Handover records identify accountable owners and scheduled benefit reviews after closure. The project manager does not personally realize every future operational benefit. The operating team should diagnose it by checking whether it can inspect acceptance records, benefits plan baselines and responsible business roles, then agree operational benefit owners and post-closure measurement arrangements before handover where justified. By contrast, the response tied to this evidence is: Handover records identify accountable owners and scheduled benefit reviews after closure.
Incorrect Answers
A:The selected opportunity produces measurable value without violating risk tolerance. The project manager does not personally realize every future operational benefit. Success in this case requires: Handover records identify accountable owners and scheduled benefit reviews after closure.
B:The risk register covers material exposures with described causes and impacts. The project manager does not personally realize every future operational benefit. Success in this case requires: Handover records identify accountable owners and scheduled benefit reviews after closure.
C:Material responses are implemented and monitored by identifiable responsible people. The project manager does not personally realize every future operational benefit. Success in this case requires: Handover records identify accountable owners and scheduled benefit reviews after closure.
Question 269
A project assurance reviewer sees a pattern in this report: a municipal payments product is accepted while the benefits review schedule has no owner or baseline. Which recurring safeguard should remain in force? Select ONE answer.
- Confirm operational ownership as part of closeout and business case updates
- Exercise contingency plans and review residual risk at boundaries
- Review sustainability impacts when designs, suppliers or operating plans change
- Audit configuration links and change traceability at every release
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to agree operational benefit owners and post-closure measurement arrangements before handover and diagnostic evidence to inspect acceptance records, benefits plan baselines and responsible business roles. Periodic testing should confirm this result: Handover records identify accountable owners and scheduled benefit reviews after closure. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to confirm operational ownership as part of closeout and business case updates. The project manager does not personally realize every future operational benefit. By contrast, the response tied to this evidence is: Confirm operational ownership as part of closeout and business case updates.
Incorrect Answers
B:Exercise contingency plans and review residual risk at boundaries. Tested response arrangements address the defined risk event in realistic conditions. The project manager does not personally realize every future operational benefit. To avoid recurrence, confirm operational ownership as part of closeout and business case updates.
C:Review sustainability impacts when designs, suppliers or operating plans change. The approved justification includes monitored sustainability indicators and credible tradeoffs. The project manager does not personally realize every future operational benefit. To avoid recurrence, confirm operational ownership as part of closeout and business case updates.
D:Audit configuration links and change traceability at every release. Delivered and tested products correspond to the latest authorized baselines. The project manager does not personally realize every future operational benefit. To avoid recurrence, confirm operational ownership as part of closeout and business case updates.
Question 270
A team wants to simplify its response to this situation: a municipal payments product is accepted while the benefits review schedule has no owner or baseline. Which shortcut is the LEAST defensible? Select ONE answer.
- Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register
- Close the benefits plan when the final software feature is deployed
- Control configuration and product baselines so each approved issue maps to the correct version
- Appoint senior user accountability for requirements, expected benefits and user acceptance
Explanation
Correct Answer
B:The unsafe shortcut is to close the benefits plan when the final software feature is deployed. The project manager does not personally realize every future operational benefit. The defensible response is instead to agree operational benefit owners and post-closure measurement arrangements before handover, using the diagnostic step to inspect acceptance records, benefits plan baselines and responsible business roles before changing settings. Afterward, the team should confirm this result: Handover records identify accountable owners and scheduled benefit reviews after closure. It must maintain the safeguard to confirm operational ownership as part of closeout and business case updates. By contrast, the response tied to this evidence is: Close the benefits plan when the final software feature is deployed.
Incorrect Answers
A:Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register. Decision-makers can understand exposure, response ownership and residual status from the register. The project manager does not personally realize every future operational benefit. The shortcut most directly implicated here is: Close the benefits plan when the final software feature is deployed.
C:Control configuration and product baselines so each approved issue maps to the correct version. Delivered and tested products correspond to the latest authorized baselines. The project manager does not personally realize every future operational benefit. The shortcut most directly implicated here is: Close the benefits plan when the final software feature is deployed.
D:Appoint senior user accountability for requirements, expected benefits and user acceptance. User needs and benefits are represented in acceptance decisions and board direction. The project manager does not personally realize every future operational benefit. The shortcut most directly implicated here is: Close the benefits plan when the final software feature is deployed.