PRINCE2 PRINCE2 7 Practitioner Practice Test 26
Question 250
For this project-management problem, the team is comparing possible shortcuts: a retail logistics project receives a major scope request that may erase its strategic advantage. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Define quality responsibilities, standards, methods and records in the tailored quality management approach
- Treat the initial authorization as permission to ignore later business conditions
- Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up
- Update role descriptions, decision limits and interface responsibilities to match the current organization
Explanation
Correct Answer
B:The unsafe shortcut is to treat the initial authorization as permission to ignore later business conditions. An approved business case must remain live throughout delivery. The defensible response is instead to reassess continuing desirability, viability and achievability before approval of the changed commitment, using the diagnostic step to compare revised scope, risks and benefits against original justification and tolerance before changing settings. Afterward, the team should confirm this result: A formal continue, adjust or stop decision is backed by the current business case. It must maintain the safeguard to trigger justification reviews at boundaries and significant external events. By contrast, the response tied to this evidence is: Treat the initial authorization as permission to ignore later business conditions.
Incorrect Answers
A:Define quality responsibilities, standards, methods and records in the tailored quality management approach. The project applies consistent quality controls with retained objective review evidence. A formal continue, adjust or stop decision is backed by the current business case. The shortcut most directly implicated here is: Treat the initial authorization as permission to ignore later business conditions.
C:Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up. The product is accepted only after recorded issues are handled and criteria demonstrated. A formal continue, adjust or stop decision is backed by the current business case. The shortcut most directly implicated here is: Treat the initial authorization as permission to ignore later business conditions.
D:Update role descriptions, decision limits and interface responsibilities to match the current organization. Each major decision and delivery obligation maps to a competent accountable role. A formal continue, adjust or stop decision is backed by the current business case. The shortcut most directly implicated here is: Treat the initial authorization as permission to ignore later business conditions.
Question 251
A project board needs to manage this condition: a community library team tries to create a detailed full business case before approving a short discovery stage. Which administrative action best resolves the specific control gap? Select ONE answer.
- Identify and manage internal and external product dependencies in the appropriate plans
- Verify that risk responses are actionable, proportionate and integrated with plans
- Use a proportionate outline business case and project brief to support initiation, then develop the full justification
- Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register
Explanation
Correct Answer
C:First, check the mandate, initial scope, constraints and preliminary benefit assumptions. Use a proportionate outline business case and project brief to support initiation, then develop the full justification. Early governance should be proportionate to uncertainty and decision maturity. Success requires: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. Repeating refine justification and mandate traceability when initiating a project helps prevent recurrence.
Incorrect Answers
A:Identify and manage internal and external product dependencies in the appropriate plans. Upstream products are accepted before dependent work is committed beyond tolerance. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
B:Verify that risk responses are actionable, proportionate and integrated with plans. Tested response arrangements address the defined risk event in realistic conditions. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
D:Keep clear cause-event-effect descriptions, accountable owners and dated response status in the risk register. Decision-makers can understand exposure, response ownership and residual status from the register. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
Question 252
An operations team is unsure why this occurred: a community library team tries to create a detailed full business case before approving a short discovery stage. Which targeted diagnostic step would produce the most relevant evidence? Select ONE answer.
- Trace each projected benefit to enabling products and operational changes
- Compare project forecasts with energy, disposal and social-impact assumptions
- Compare documented evidence and uncertainty with ratings and project tolerance
- Check the mandate, initial scope, constraints and preliminary benefit assumptions
Explanation
Correct Answer
D:The strongest first investigation is to check the mandate, initial scope, constraints and preliminary benefit assumptions. Early governance should be proportionate to uncertainty and decision maturity. If that evidence confirms the issue, the team should use a proportionate outline business case and project brief to support initiation, then develop the full justification. A subsequent acceptance check should confirm this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. This check produces evidence before any broad configuration change, avoiding the risky proposal to commit the full delivery budget based only on an untested preliminary project brief.
Incorrect Answers
A:Trace each projected benefit to enabling products and operational changes. Unmanaged external dependencies can make technically successful projects miss strategic goals. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The relevant investigation is: Check the mandate, initial scope, constraints and preliminary benefit assumptions.
B:Compare project forecasts with energy, disposal and social-impact assumptions. The approved justification includes monitored sustainability indicators and credible tradeoffs. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The relevant investigation is: Check the mandate, initial scope, constraints and preliminary benefit assumptions.
C:Compare documented evidence and uncertainty with ratings and project tolerance. Risk ratings distinguish priority exposures and support defensible response decisions. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The relevant investigation is: Check the mandate, initial scope, constraints and preliminary benefit assumptions.
Question 253
The senior user wants proof that this problem is resolved: a community library team tries to create a detailed full business case before approving a short discovery stage. Which end-to-end verification is most useful? Select ONE answer.
- Initiation is authorized on a credible brief while the full business case is developed before delivery commitment
- Handover records identify accountable owners and scheduled benefit reviews after closure
- Change expenditure stays within authority and project forecasts reflect cumulative commitments
- Technical resource gaps are escalated through appropriate supplier governance
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to refine justification and mandate traceability when initiating a project. The decisive acceptance evidence is this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. Early governance should be proportionate to uncertainty and decision maturity. The operating team should diagnose it by checking whether it can check the mandate, initial scope, constraints and preliminary benefit assumptions, then use a proportionate outline business case and project brief to support initiation, then develop the full justification where justified.
Incorrect Answers
B:Handover records identify accountable owners and scheduled benefit reviews after closure. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
C:Change expenditure stays within authority and project forecasts reflect cumulative commitments. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
D:Technical resource gaps are escalated through appropriate supplier governance. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
Question 254
An incident has been closed after the team addressed this condition: a community library team tries to create a detailed full business case before approving a short discovery stage. Which follow-up control is most effective? Select ONE answer.
- Revalidate benefit forecasts and their owners when scope and usage assumptions change
- Refine justification and mandate traceability when initiating a project
- Trigger justification reviews at boundaries and significant external events
- Include support-readiness reviews in future product handovers
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to use a proportionate outline business case and project brief to support initiation, then develop the full justification and diagnostic evidence to check the mandate, initial scope, constraints and preliminary benefit assumptions. Periodic testing should confirm this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to refine justification and mandate traceability when initiating a project. Early governance should be proportionate to uncertainty and decision maturity.
Incorrect Answers
A:Revalidate benefit forecasts and their owners when scope and usage assumptions change. Approved benefit measures can be traced to users, data sources and review dates. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. To avoid recurrence, refine justification and mandate traceability when initiating a project.
C:Trigger justification reviews at boundaries and significant external events. A formal continue, adjust or stop decision is backed by the current business case. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. To avoid recurrence, refine justification and mandate traceability when initiating a project.
D:Include support-readiness reviews in future product handovers. Receiving owners confirm the product is acceptable and usable in live operations. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. To avoid recurrence, refine justification and mandate traceability when initiating a project.
Question 255
For this project-management problem, the team is comparing possible shortcuts: a community library team tries to create a detailed full business case before approving a short discovery stage. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Translate relevant lessons into owned improvements and monitor completion as part of stage controls
- Develop a product breakdown and product flow before deriving activities and resources
- Commit the full delivery budget based only on an untested preliminary project brief
- Identify threats and opportunities across objectives, stakeholders, sustainability and delivery dependencies
Explanation
Correct Answer
C:The unsafe shortcut is to commit the full delivery budget based only on an untested preliminary project brief. Early governance should be proportionate to uncertainty and decision maturity. The defensible response is instead to use a proportionate outline business case and project brief to support initiation, then develop the full justification, using the diagnostic step to check the mandate, initial scope, constraints and preliminary benefit assumptions before changing settings. Afterward, the team should confirm this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. It must maintain the safeguard to refine justification and mandate traceability when initiating a project.
Incorrect Answers
A:Translate relevant lessons into owned improvements and monitor completion as part of stage controls. Later stage reports show implemented learning and reduced recurrence. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.
B:Develop a product breakdown and product flow before deriving activities and resources. The plan covers required products in a logical sequence with explicit quality expectations. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.
D:Identify threats and opportunities across objectives, stakeholders, sustainability and delivery dependencies. The risk register covers material exposures with described causes and impacts. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.
Question 256
During a PRINCE2 management-stage review, the team encounters this situation: a renewable energy project has a vague project brief whose mandate cannot support an initiation decision. What is the most appropriate controlled response? Select ONE answer.
- Adopt controlled project data ownership, versioning and secure information-sharing arrangements
- Assign one executive accountable for overall project business justification and board decisions
- Assess likelihood, impact and proximity consistently against agreed risk criteria
- Use a proportionate outline business case and project brief to support initiation, then develop the full justification
Explanation
Correct Answer
D:First, check the mandate, initial scope, constraints and preliminary benefit assumptions. Use a proportionate outline business case and project brief to support initiation, then develop the full justification. Early governance should be proportionate to uncertainty and decision maturity. Success requires: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. Repeating refine justification and mandate traceability when initiating a project helps prevent recurrence. By contrast, the response tied to this evidence is: Use a proportionate outline business case and project brief to support initiation, then develop the full justification.
Incorrect Answers
A:Adopt controlled project data ownership, versioning and secure information-sharing arrangements. Digital information management supports accurate governance and safe collaboration. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
B:Assign one executive accountable for overall project business justification and board decisions. The executive provides a single point of business accountability. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
C:Assess likelihood, impact and proximity consistently against agreed risk criteria. Risk ratings distinguish priority exposures and support defensible response decisions. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
Question 257
The project management team is troubleshooting this situation: a renewable energy project has a vague project brief whose mandate cannot support an initiation decision. Which check isolates the likely operating dependency? Select ONE answer.
- Check the mandate, initial scope, constraints and preliminary benefit assumptions
- Trace each planned activity to a described product, dependencies and acceptance criteria
- Inspect assurance mandates and conflicts of interest against project delivery responsibilities
- Compare team activities, deliverables and quality records against the authorized work package
Explanation
Correct Answer
A:The strongest first investigation is to check the mandate, initial scope, constraints and preliminary benefit assumptions. Early governance should be proportionate to uncertainty and decision maturity. If that evidence confirms the issue, the team should use a proportionate outline business case and project brief to support initiation, then develop the full justification. A subsequent acceptance check should confirm this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. This check produces evidence before any broad configuration change, avoiding the risky proposal to commit the full delivery budget based only on an untested preliminary project brief. By contrast, the response tied to this evidence is: Check the mandate, initial scope, constraints and preliminary benefit assumptions.
Incorrect Answers
B:Trace each planned activity to a described product, dependencies and acceptance criteria. The plan covers required products in a logical sequence with explicit quality expectations. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The relevant investigation is: Check the mandate, initial scope, constraints and preliminary benefit assumptions.
C:Inspect assurance mandates and conflicts of interest against project delivery responsibilities. The board receives objective challenge and evidence without confusing assurance and management. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The relevant investigation is: Check the mandate, initial scope, constraints and preliminary benefit assumptions.
D:Compare team activities, deliverables and quality records against the authorized work package. Teams may plan work flexibly but cannot unilaterally change authorized product acceptance. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The relevant investigation is: Check the mandate, initial scope, constraints and preliminary benefit assumptions.
Question 258
An administrator claims the following problem is resolved: a renewable energy project has a vague project brief whose mandate cannot support an initiation decision. Which measured outcome confirms that claim? Select ONE answer.
- Delivered and tested products correspond to the latest authorized baselines
- Initiation is authorized on a credible brief while the full business case is developed before delivery commitment
- The structure is proportionate and still supports clear user, business and supplier decisions
- The approved justification includes monitored sustainability indicators and credible tradeoffs
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to refine justification and mandate traceability when initiating a project. The decisive acceptance evidence is this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. Early governance should be proportionate to uncertainty and decision maturity. The operating team should diagnose it by checking whether it can check the mandate, initial scope, constraints and preliminary benefit assumptions, then use a proportionate outline business case and project brief to support initiation, then develop the full justification where justified. By contrast, the response tied to this evidence is: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
Incorrect Answers
A:Delivered and tested products correspond to the latest authorized baselines. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
C:The structure is proportionate and still supports clear user, business and supplier decisions. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
D:The approved justification includes monitored sustainability indicators and credible tradeoffs. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment.
Question 259
After resolving the following issue, the operations team wants to prevent a recurrence: a renewable energy project has a vague project brief whose mandate cannot support an initiation decision. Which ongoing control is best? Select ONE answer.
- Keep the project product description aligned with authorized changes
- Review the quality approach as products, suppliers or regulatory demands change
- Refine justification and mandate traceability when initiating a project
- Check cost assumptions regularly and escalate predicted breaches against tolerance
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to use a proportionate outline business case and project brief to support initiation, then develop the full justification and diagnostic evidence to check the mandate, initial scope, constraints and preliminary benefit assumptions. Periodic testing should confirm this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to refine justification and mandate traceability when initiating a project. Early governance should be proportionate to uncertainty and decision maturity. By contrast, the response tied to this evidence is: Refine justification and mandate traceability when initiating a project.
Incorrect Answers
A:Keep the project product description aligned with authorized changes. The final project output can be tested against clearly approved acceptance criteria. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. To avoid recurrence, refine justification and mandate traceability when initiating a project.
B:Review the quality approach as products, suppliers or regulatory demands change. The project applies consistent quality controls with retained objective review evidence. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. To avoid recurrence, refine justification and mandate traceability when initiating a project.
D:Check cost assumptions regularly and escalate predicted breaches against tolerance. The board considers a transparent forecast with affordable funding and defensible benefits. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. To avoid recurrence, refine justification and mandate traceability when initiating a project.
Question 260
A project manager is under pressure to address the following issue quickly: a renewable energy project has a vague project brief whose mandate cannot support an initiation decision. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Agree operational benefit owners and post-closure measurement arrangements before handover
- Specify measurable product quality criteria, methods and responsibilities before acceptance
- Assign accountable risk ownership and specific response action ownership with suitable authority
- Commit the full delivery budget based only on an untested preliminary project brief
Explanation
Correct Answer
D:The unsafe shortcut is to commit the full delivery budget based only on an untested preliminary project brief. Early governance should be proportionate to uncertainty and decision maturity. The defensible response is instead to use a proportionate outline business case and project brief to support initiation, then develop the full justification, using the diagnostic step to check the mandate, initial scope, constraints and preliminary benefit assumptions before changing settings. Afterward, the team should confirm this result: Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. It must maintain the safeguard to refine justification and mandate traceability when initiating a project. By contrast, the response tied to this evidence is: Commit the full delivery budget based only on an untested preliminary project brief.
Incorrect Answers
A:Agree operational benefit owners and post-closure measurement arrangements before handover. Handover records identify accountable owners and scheduled benefit reviews after closure. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.
B:Specify measurable product quality criteria, methods and responsibilities before acceptance. Quality expectations must become testable acceptance evidence. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.
C:Assign accountable risk ownership and specific response action ownership with suitable authority. Material responses are implemented and monitored by identifiable responsible people. Initiation is authorized on a credible brief while the full business case is developed before delivery commitment. The shortcut most directly implicated here is: Commit the full delivery budget based only on an untested preliminary project brief.