PRINCE2 PRINCE2 7 Practitioner Practice Test 22
Question 210
A project manager is under pressure to address the following issue quickly: a coastal protection initiative faces procurement inflation that invalidates its earlier cost-benefit forecast. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Classify actual problems, requests for change and off-specifications in the issue process
- Hide indirect costs so the project's original benefit-cost ratio remains unchanged
- Update role descriptions, decision limits and interface responsibilities to match the current organization
- Develop a product breakdown and product flow before deriving activities and resources
Explanation
Correct Answer
B:The unsafe shortcut is to hide indirect costs so the project's original benefit-cost ratio remains unchanged. Business justification depends on credible future cost as well as delivery output. The defensible response is instead to refresh life-cycle costs, assumptions and the investment justification before requesting commitment, using the diagnostic step to compare new vendor and operating-cost estimates with the cost assumptions in the business case before changing settings. Afterward, the team should confirm this result: The board considers a transparent forecast with affordable funding and defensible benefits. It must maintain the safeguard to check cost assumptions regularly and escalate predicted breaches against tolerance. By contrast, the response tied to this evidence is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
Incorrect Answers
A:Classify actual problems, requests for change and off-specifications in the issue process. Each issue has the appropriate impact analysis and decision path. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
C:Update role descriptions, decision limits and interface responsibilities to match the current organization. Each major decision and delivery obligation maps to a competent accountable role. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
D:Develop a product breakdown and product flow before deriving activities and resources. The plan covers required products in a logical sequence with explicit quality expectations. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
Question 211
During a PRINCE2 management-stage review, the team encounters this situation: a museum visitor project has two viable solution designs but selects the familiar vendor without comparing expected value. What is the most appropriate controlled response? Select ONE answer.
- Escalate threats that threaten delegated tolerance while managing routine risks at the proper level
- Assign project commercial management responsibilities and define how supplier commitments and changes are coordinated
- Compare realistic options including do nothing using costs, benefits, risk and sustainability impacts
- Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up
Explanation
Correct Answer
C:First, inspect whether options share consistent assumptions and measurable decision criteria. Compare realistic options including do nothing using costs, benefits, risk and sustainability impacts. The business case is a decision aid that tests alternatives rather than a justification written after selection. Success requires: A documented board choice reflects credible comparative value and explicit tradeoffs. Repeating revisit alternatives when conditions alter the preferred option helps prevent recurrence.
Incorrect Answers
A:Escalate threats that threaten delegated tolerance while managing routine risks at the proper level. Risk governance requires clear boundaries between routine response and exception. A documented board choice reflects credible comparative value and explicit tradeoffs.
B:Assign project commercial management responsibilities and define how supplier commitments and changes are coordinated. Contracts and project governance must align so the board can control risk and value. A documented board choice reflects credible comparative value and explicit tradeoffs.
D:Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up. The product is accepted only after recorded issues are handled and criteria demonstrated. A documented board choice reflects credible comparative value and explicit tradeoffs.
Question 212
The project management team is troubleshooting this situation: a museum visitor project has two viable solution designs but selects the familiar vendor without comparing expected value. Which check isolates the likely operating dependency? Select ONE answer.
- Compare opportunity assumptions, probability and benefit with the current business case
- Compare stakeholder complexity, risk and decision rights with the proposed team structure
- Compare team activities, deliverables and quality records against the authorized work package
- Inspect whether options share consistent assumptions and measurable decision criteria
Explanation
Correct Answer
D:The strongest first investigation is to inspect whether options share consistent assumptions and measurable decision criteria. The business case is a decision aid that tests alternatives rather than a justification written after selection. If that evidence confirms the issue, the team should compare realistic options including do nothing using costs, benefits, risk and sustainability impacts. A subsequent acceptance check should confirm this result: A documented board choice reflects credible comparative value and explicit tradeoffs. This check produces evidence before any broad configuration change, avoiding the risky proposal to approve the first proposed option without comparing it with alternatives or doing nothing.
Incorrect Answers
A:Compare opportunity assumptions, probability and benefit with the current business case. The selected opportunity produces measurable value without violating risk tolerance. A documented board choice reflects credible comparative value and explicit tradeoffs. The relevant investigation is: Inspect whether options share consistent assumptions and measurable decision criteria.
B:Compare stakeholder complexity, risk and decision rights with the proposed team structure. The structure is proportionate and still supports clear user, business and supplier decisions. A documented board choice reflects credible comparative value and explicit tradeoffs. The relevant investigation is: Inspect whether options share consistent assumptions and measurable decision criteria.
C:Compare team activities, deliverables and quality records against the authorized work package. Teams may plan work flexibly but cannot unilaterally change authorized product acceptance. A documented board choice reflects credible comparative value and explicit tradeoffs. The relevant investigation is: Inspect whether options share consistent assumptions and measurable decision criteria.
Question 213
An administrator claims the following problem is resolved: a museum visitor project has two viable solution designs but selects the familiar vendor without comparing expected value. Which measured outcome confirms that claim? Select ONE answer.
- A documented board choice reflects credible comparative value and explicit tradeoffs
- Technical resource gaps are escalated through appropriate supplier governance
- Decision-makers can understand exposure, response ownership and residual status from the register
- Later stage reports show implemented learning and reduced recurrence
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to revisit alternatives when conditions alter the preferred option. The decisive acceptance evidence is this result: A documented board choice reflects credible comparative value and explicit tradeoffs. The business case is a decision aid that tests alternatives rather than a justification written after selection. The operating team should diagnose it by checking whether it can inspect whether options share consistent assumptions and measurable decision criteria, then compare realistic options including do nothing using costs, benefits, risk and sustainability impacts where justified.
Incorrect Answers
B:Technical resource gaps are escalated through appropriate supplier governance. A documented board choice reflects credible comparative value and explicit tradeoffs.
C:Decision-makers can understand exposure, response ownership and residual status from the register. A documented board choice reflects credible comparative value and explicit tradeoffs.
D:Later stage reports show implemented learning and reduced recurrence. A documented board choice reflects credible comparative value and explicit tradeoffs.
Question 214
After resolving the following issue, the operations team wants to prevent a recurrence: a museum visitor project has two viable solution designs but selects the familiar vendor without comparing expected value. Which ongoing control is best? Select ONE answer.
- Review both new and existing lessons in progress checkpoints
- Revisit alternatives when conditions alter the preferred option
- Review board membership and delegated authority when sponsorship changes
- Keep the project product description aligned with authorized changes
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to compare realistic options including do nothing using costs, benefits, risk and sustainability impacts and diagnostic evidence to inspect whether options share consistent assumptions and measurable decision criteria. Periodic testing should confirm this result: A documented board choice reflects credible comparative value and explicit tradeoffs. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to revisit alternatives when conditions alter the preferred option. The business case is a decision aid that tests alternatives rather than a justification written after selection.
Incorrect Answers
A:Review both new and existing lessons in progress checkpoints. Later stage reports show implemented learning and reduced recurrence. A documented board choice reflects credible comparative value and explicit tradeoffs. To avoid recurrence, revisit alternatives when conditions alter the preferred option.
C:Review board membership and delegated authority when sponsorship changes. The executive provides a single point of business accountability. A documented board choice reflects credible comparative value and explicit tradeoffs. To avoid recurrence, revisit alternatives when conditions alter the preferred option.
D:Keep the project product description aligned with authorized changes. The final project output can be tested against clearly approved acceptance criteria. A documented board choice reflects credible comparative value and explicit tradeoffs. To avoid recurrence, revisit alternatives when conditions alter the preferred option.
Question 215
A project manager is under pressure to address the following issue quickly: a museum visitor project has two viable solution designs but selects the familiar vendor without comparing expected value. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Agree operational benefit owners and post-closure measurement arrangements before handover
- Escalate threats that threaten delegated tolerance while managing routine risks at the proper level
- Approve the first proposed option without comparing it with alternatives or doing nothing
- Route issue decisions to the person or board holding the relevant delegated authority
Explanation
Correct Answer
C:The unsafe shortcut is to approve the first proposed option without comparing it with alternatives or doing nothing. The business case is a decision aid that tests alternatives rather than a justification written after selection. The defensible response is instead to compare realistic options including do nothing using costs, benefits, risk and sustainability impacts, using the diagnostic step to inspect whether options share consistent assumptions and measurable decision criteria before changing settings. Afterward, the team should confirm this result: A documented board choice reflects credible comparative value and explicit tradeoffs. It must maintain the safeguard to revisit alternatives when conditions alter the preferred option.
Incorrect Answers
A:Agree operational benefit owners and post-closure measurement arrangements before handover. Handover records identify accountable owners and scheduled benefit reviews after closure. A documented board choice reflects credible comparative value and explicit tradeoffs. The shortcut most directly implicated here is: Approve the first proposed option without comparing it with alternatives or doing nothing.
B:Escalate threats that threaten delegated tolerance while managing routine risks at the proper level. Risk governance requires clear boundaries between routine response and exception. A documented board choice reflects credible comparative value and explicit tradeoffs. The shortcut most directly implicated here is: Approve the first proposed option without comparing it with alternatives or doing nothing.
D:Route issue decisions to the person or board holding the relevant delegated authority. Issue decisions are formally recorded at the right governance level. A documented board choice reflects credible comparative value and explicit tradeoffs. The shortcut most directly implicated here is: Approve the first proposed option without comparing it with alternatives or doing nothing.
Question 216
A project delivery team reports that a city waste-monitoring pilot might be stopped, delayed or scaled but only expansion appears in the approval paper. Which action directly addresses the issue? Select ONE answer.
- Identify and manage internal and external product dependencies in the appropriate plans
- Appoint senior user accountability for requirements, expected benefits and user acceptance
- Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up
- Compare realistic options including do nothing using costs, benefits, risk and sustainability impacts
Explanation
Correct Answer
D:First, inspect whether options share consistent assumptions and measurable decision criteria. Compare realistic options including do nothing using costs, benefits, risk and sustainability impacts. The reported operational condition is that a city waste-monitoring pilot might be stopped, delayed or scaled but only expansion appears in the approval paper. The business case is a decision aid that tests alternatives rather than a justification written after selection. Success requires: A documented board choice reflects credible comparative value and explicit tradeoffs. Repeating revisit alternatives when conditions alter the preferred option helps prevent recurrence.
Incorrect Answers
A:Identify and manage internal and external product dependencies in the appropriate plans. Upstream products are accepted before dependent work is committed beyond tolerance. The business case is a decision aid that tests alternatives rather than a justification written after selection.
B:Appoint senior user accountability for requirements, expected benefits and user acceptance. User needs and benefits are represented in acceptance decisions and board direction. The business case is a decision aid that tests alternatives rather than a justification written after selection.
C:Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up. The product is accepted only after recorded issues are handled and criteria demonstrated. The business case is a decision aid that tests alternatives rather than a justification written after selection.
Question 217
An administrator wants to identify the failure before making a change: a city waste-monitoring pilot might be stopped, delayed or scaled but only expansion appears in the approval paper. Which inspection is the most informative? Select ONE answer.
- Inspect whether options share consistent assumptions and measurable decision criteria
- Compare planned quality activities with product types, compliance needs and roles
- Compare forecast deviation with delegated tolerance and the options available to recover
- Check reviewer readiness, product description and unresolved review findings
Explanation
Correct Answer
A:The strongest first investigation is to inspect whether options share consistent assumptions and measurable decision criteria. The business case is a decision aid that tests alternatives rather than a justification written after selection. If that evidence confirms the issue, the team should compare realistic options including do nothing using costs, benefits, risk and sustainability impacts. A subsequent acceptance check should confirm this result: A documented board choice reflects credible comparative value and explicit tradeoffs. This check produces evidence before any broad configuration change, avoiding the risky proposal to approve the first proposed option without comparing it with alternatives or doing nothing. By contrast, the response tied to this evidence is: Inspect whether options share consistent assumptions and measurable decision criteria.
Incorrect Answers
B:Compare planned quality activities with product types, compliance needs and roles. The project applies consistent quality controls with retained objective review evidence. The business case is a decision aid that tests alternatives rather than a justification written after selection. The relevant investigation is: Inspect whether options share consistent assumptions and measurable decision criteria.
C:Compare forecast deviation with delegated tolerance and the options available to recover. The relevant authority approves a replacement baseline before exception delivery proceeds. The business case is a decision aid that tests alternatives rather than a justification written after selection. The relevant investigation is: Inspect whether options share consistent assumptions and measurable decision criteria.
D:Check reviewer readiness, product description and unresolved review findings. The product is accepted only after recorded issues are handled and criteria demonstrated. The business case is a decision aid that tests alternatives rather than a justification written after selection. The relevant investigation is: Inspect whether options share consistent assumptions and measurable decision criteria.
Question 218
After a controlled change, the team needs to resolve this report: a city waste-monitoring pilot might be stopped, delayed or scaled but only expansion appears in the approval paper. Which observable result would best establish success? Select ONE answer.
- Later stage reports show implemented learning and reduced recurrence
- A documented board choice reflects credible comparative value and explicit tradeoffs
- Reporting is proportionate yet produces reliable forecasts and clear authority decisions
- The project board can decide continuation or recovery using a credible report
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to revisit alternatives when conditions alter the preferred option. The decisive acceptance evidence is this result: A documented board choice reflects credible comparative value and explicit tradeoffs. The business case is a decision aid that tests alternatives rather than a justification written after selection. The operating team should diagnose it by checking whether it can inspect whether options share consistent assumptions and measurable decision criteria, then compare realistic options including do nothing using costs, benefits, risk and sustainability impacts where justified. By contrast, the response tied to this evidence is: A documented board choice reflects credible comparative value and explicit tradeoffs.
Incorrect Answers
A:Later stage reports show implemented learning and reduced recurrence. The business case is a decision aid that tests alternatives rather than a justification written after selection. Success in this case requires: A documented board choice reflects credible comparative value and explicit tradeoffs.
C:Reporting is proportionate yet produces reliable forecasts and clear authority decisions. The business case is a decision aid that tests alternatives rather than a justification written after selection. Success in this case requires: A documented board choice reflects credible comparative value and explicit tradeoffs.
D:The project board can decide continuation or recovery using a credible report. The business case is a decision aid that tests alternatives rather than a justification written after selection. Success in this case requires: A documented board choice reflects credible comparative value and explicit tradeoffs.
Question 219
A project assurance reviewer sees a pattern in this report: a city waste-monitoring pilot might be stopped, delayed or scaled but only expansion appears in the approval paper. Which recurring safeguard should remain in force? Select ONE answer.
- Repeat risk discovery after significant scope or external changes
- Monitor recurring quality variances and their causes across products
- Revisit alternatives when conditions alter the preferred option
- Require impact evidence and user/supplier input for significant issues
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to compare realistic options including do nothing using costs, benefits, risk and sustainability impacts and diagnostic evidence to inspect whether options share consistent assumptions and measurable decision criteria. Periodic testing should confirm this result: A documented board choice reflects credible comparative value and explicit tradeoffs. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to revisit alternatives when conditions alter the preferred option. The business case is a decision aid that tests alternatives rather than a justification written after selection. By contrast, the response tied to this evidence is: Revisit alternatives when conditions alter the preferred option.
Incorrect Answers
A:Repeat risk discovery after significant scope or external changes. The risk register covers material exposures with described causes and impacts. The business case is a decision aid that tests alternatives rather than a justification written after selection. To avoid recurrence, revisit alternatives when conditions alter the preferred option.
B:Monitor recurring quality variances and their causes across products. Any revised acceptance is explicitly authorized and evidence demonstrates the approved criteria. The business case is a decision aid that tests alternatives rather than a justification written after selection. To avoid recurrence, revisit alternatives when conditions alter the preferred option.
D:Require impact evidence and user/supplier input for significant issues. Change control protects overall project viability rather than only the altered feature. The business case is a decision aid that tests alternatives rather than a justification written after selection. To avoid recurrence, revisit alternatives when conditions alter the preferred option.
Question 220
A team wants to simplify its response to this situation: a city waste-monitoring pilot might be stopped, delayed or scaled but only expansion appears in the approval paper. Which shortcut is the LEAST defensible? Select ONE answer.
- Classify actual problems, requests for change and off-specifications in the issue process
- Verify that risk responses are actionable, proportionate and integrated with plans
- Scale the project management structure proportionately while preserving necessary governance interests and roles
- Approve the first proposed option without comparing it with alternatives or doing nothing
Explanation
Correct Answer
D:The unsafe shortcut is to approve the first proposed option without comparing it with alternatives or doing nothing. The business case is a decision aid that tests alternatives rather than a justification written after selection. The defensible response is instead to compare realistic options including do nothing using costs, benefits, risk and sustainability impacts, using the diagnostic step to inspect whether options share consistent assumptions and measurable decision criteria before changing settings. Afterward, the team should confirm this result: A documented board choice reflects credible comparative value and explicit tradeoffs. It must maintain the safeguard to revisit alternatives when conditions alter the preferred option. By contrast, the response tied to this evidence is: Approve the first proposed option without comparing it with alternatives or doing nothing.
Incorrect Answers
A:Classify actual problems, requests for change and off-specifications in the issue process. Each issue has the appropriate impact analysis and decision path. The business case is a decision aid that tests alternatives rather than a justification written after selection. The shortcut most directly implicated here is: Approve the first proposed option without comparing it with alternatives or doing nothing.
B:Verify that risk responses are actionable, proportionate and integrated with plans. Tested response arrangements address the defined risk event in realistic conditions. The business case is a decision aid that tests alternatives rather than a justification written after selection. The shortcut most directly implicated here is: Approve the first proposed option without comparing it with alternatives or doing nothing.
C:Scale the project management structure proportionately while preserving necessary governance interests and roles. The structure is proportionate and still supports clear user, business and supplier decisions. The business case is a decision aid that tests alternatives rather than a justification written after selection. The shortcut most directly implicated here is: Approve the first proposed option without comparing it with alternatives or doing nothing.