PRINCE2 PRINCE2 7 Practitioner Practice Test 21
Question 200
For this project-management problem, the team is comparing possible shortcuts: a public health dashboard promises fewer emergency visits without assigning anyone to measure post-project outcomes. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Arrange board-delegated business, user and supplier assurance independent of day-to-day management
- Use checkpoint evidence to produce stage-level highlight reporting appropriate to each authority
- Record and evaluate the quality deviation through authorized issue and acceptance decisions
- Count completed installations as proof that every long-term benefit has already occurred
Explanation
Correct Answer
D:The unsafe shortcut is to count completed installations as proof that every long-term benefit has already occurred. A product can be delivered successfully while expected business benefits remain unrealized. The defensible response is instead to define benefits, owners, measurement timing and dependencies in the updated business case and benefits management approach, using the diagnostic step to compare proposed benefits with baselines, assumptions and named post-project owners before changing settings. Afterward, the team should confirm this result: Approved benefit measures can be traced to users, data sources and review dates. It must maintain the safeguard to revalidate benefit forecasts and their owners when scope and usage assumptions change. By contrast, the response tied to this evidence is: Count completed installations as proof that every long-term benefit has already occurred.
Incorrect Answers
A:Arrange board-delegated business, user and supplier assurance independent of day-to-day management. The board receives objective challenge and evidence without confusing assurance and management. Approved benefit measures can be traced to users, data sources and review dates. The shortcut most directly implicated here is: Count completed installations as proof that every long-term benefit has already occurred.
B:Use checkpoint evidence to produce stage-level highlight reporting appropriate to each authority. Team-level progress supports accurate board-facing stage summaries. Approved benefit measures can be traced to users, data sources and review dates. The shortcut most directly implicated here is: Count completed installations as proof that every long-term benefit has already occurred.
C:Record and evaluate the quality deviation through authorized issue and acceptance decisions. Any revised acceptance is explicitly authorized and evidence demonstrates the approved criteria. Approved benefit measures can be traced to users, data sources and review dates. The shortcut most directly implicated here is: Count completed installations as proof that every long-term benefit has already occurred.
Question 201
A project board needs to manage this condition: a district school modernization discovers a second licensing fee excluded from the approved project forecast. Which administrative action best resolves the specific control gap? Select ONE answer.
- Refresh life-cycle costs, assumptions and the investment justification before requesting commitment
- Assign accountable risk ownership and specific response action ownership with suitable authority
- Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up
- Translate relevant lessons into owned improvements and monitor completion as part of stage controls
Explanation
Correct Answer
A:First, compare new vendor and operating-cost estimates with the cost assumptions in the business case. Refresh life-cycle costs, assumptions and the investment justification before requesting commitment. Business justification depends on credible future cost as well as delivery output. Success means the board considers a transparent forecast with affordable funding and defensible benefits. Repeating check cost assumptions regularly and escalate predicted breaches against tolerance helps prevent recurrence.
Incorrect Answers
B:Assign accountable risk ownership and specific response action ownership with suitable authority. Material responses are implemented and monitored by identifiable responsible people. The board considers a transparent forecast with affordable funding and defensible benefits.
C:Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up. The product is accepted only after recorded issues are handled and criteria demonstrated. The board considers a transparent forecast with affordable funding and defensible benefits.
D:Translate relevant lessons into owned improvements and monitor completion as part of stage controls. Later stage reports show implemented learning and reduced recurrence. The board considers a transparent forecast with affordable funding and defensible benefits.
Question 202
An operations team is unsure why this occurred: a district school modernization discovers a second licensing fee excluded from the approved project forecast. Which targeted diagnostic step would produce the most relevant evidence? Select ONE answer.
- Compare consolidated exposure and latest forecasts with stage and project risk tolerances
- Compare new vendor and operating-cost estimates with the cost assumptions in the business case
- Compare reported facts with approved product baselines and occurrence timing
- Trace each planned activity to a described product, dependencies and acceptance criteria
Explanation
Correct Answer
B:The strongest first investigation is to compare new vendor and operating-cost estimates with the cost assumptions in the business case. Business justification depends on credible future cost as well as delivery output. If that evidence confirms the issue, the team should refresh life-cycle costs, assumptions and the investment justification before requesting commitment. A subsequent acceptance check should confirm this result: The board considers a transparent forecast with affordable funding and defensible benefits. This check produces evidence before any broad configuration change, avoiding the risky proposal to hide indirect costs so the project's original benefit-cost ratio remains unchanged.
Incorrect Answers
A:Compare consolidated exposure and latest forecasts with stage and project risk tolerances. Risk governance requires clear boundaries between routine response and exception. The board considers a transparent forecast with affordable funding and defensible benefits. The relevant investigation is: Compare new vendor and operating-cost estimates with the cost assumptions in the business case.
C:Compare reported facts with approved product baselines and occurrence timing. Each issue has the appropriate impact analysis and decision path. The board considers a transparent forecast with affordable funding and defensible benefits. The relevant investigation is: Compare new vendor and operating-cost estimates with the cost assumptions in the business case.
D:Trace each planned activity to a described product, dependencies and acceptance criteria. The plan covers required products in a logical sequence with explicit quality expectations. The board considers a transparent forecast with affordable funding and defensible benefits. The relevant investigation is: Compare new vendor and operating-cost estimates with the cost assumptions in the business case.
Question 203
The senior user wants proof that this problem is resolved: a district school modernization discovers a second licensing fee excluded from the approved project forecast. Which end-to-end verification is most useful? Select ONE answer.
- Team outputs and reports meet the approved product descriptions and handoff conditions
- Approved benefit measures can be traced to users, data sources and review dates
- The board considers a transparent forecast with affordable funding and defensible benefits
- The project applies consistent quality controls with retained objective review evidence
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to check cost assumptions regularly and escalate predicted breaches against tolerance. The decisive acceptance evidence is this result: The board considers a transparent forecast with affordable funding and defensible benefits. Business justification depends on credible future cost as well as delivery output. The operating team should diagnose it by checking whether it can compare new vendor and operating-cost estimates with the cost assumptions in the business case, then refresh life-cycle costs, assumptions and the investment justification before requesting commitment where justified.
Incorrect Answers
A:Team outputs and reports meet the approved product descriptions and handoff conditions. Teams may plan work flexibly but cannot unilaterally change authorized product acceptance. The board considers a transparent forecast with affordable funding and defensible benefits.
B:Approved benefit measures can be traced to users, data sources and review dates. The board considers a transparent forecast with affordable funding and defensible benefits.
D:The project applies consistent quality controls with retained objective review evidence. The board considers a transparent forecast with affordable funding and defensible benefits.
Question 204
An incident has been closed after the team addressed this condition: a district school modernization discovers a second licensing fee excluded from the approved project forecast. Which follow-up control is most effective? Select ONE answer.
- Maintain a current delegation matrix for changes and exceptions
- Review the reporting approach when scope, governance or delivery methods change
- Review the quality approach as products, suppliers or regulatory demands change
- Check cost assumptions regularly and escalate predicted breaches against tolerance
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to refresh life-cycle costs, assumptions and the investment justification before requesting commitment and diagnostic evidence to compare new vendor and operating-cost estimates with the cost assumptions in the business case. Periodic testing should confirm this result: The board considers a transparent forecast with affordable funding and defensible benefits. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to check cost assumptions regularly and escalate predicted breaches against tolerance. Business justification depends on credible future cost as well as delivery output.
Incorrect Answers
A:Maintain a current delegation matrix for changes and exceptions. Issue decisions are formally recorded at the right governance level. The board considers a transparent forecast with affordable funding and defensible benefits. To avoid recurrence, check cost assumptions regularly and escalate predicted breaches against tolerance.
B:Review the reporting approach when scope, governance or delivery methods change. Reporting is proportionate yet produces reliable forecasts and clear authority decisions. The board considers a transparent forecast with affordable funding and defensible benefits. To avoid recurrence, check cost assumptions regularly and escalate predicted breaches against tolerance.
C:Review the quality approach as products, suppliers or regulatory demands change. The project applies consistent quality controls with retained objective review evidence. The board considers a transparent forecast with affordable funding and defensible benefits. To avoid recurrence, check cost assumptions regularly and escalate predicted breaches against tolerance.
Question 205
For this project-management problem, the team is comparing possible shortcuts: a district school modernization discovers a second licensing fee excluded from the approved project forecast. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Hide indirect costs so the project's original benefit-cost ratio remains unchanged
- Tailor progress controls to risk and scale while preserving evidence, delegated authority and exception escalation
- Arrange board-delegated business, user and supplier assurance independent of day-to-day management
- Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up
Explanation
Correct Answer
A:The unsafe shortcut is to hide indirect costs so the project's original benefit-cost ratio remains unchanged. Business justification depends on credible future cost as well as delivery output. The defensible response is instead to refresh life-cycle costs, assumptions and the investment justification before requesting commitment, using the diagnostic step to compare new vendor and operating-cost estimates with the cost assumptions in the business case before changing settings. Afterward, the team should confirm this result: The board considers a transparent forecast with affordable funding and defensible benefits. It must maintain the safeguard to check cost assumptions regularly and escalate predicted breaches against tolerance.
Incorrect Answers
B:Tailor progress controls to risk and scale while preserving evidence, delegated authority and exception escalation. Reporting is proportionate yet produces reliable forecasts and clear authority decisions. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
C:Arrange board-delegated business, user and supplier assurance independent of day-to-day management. The board receives objective challenge and evidence without confusing assurance and management. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
D:Organize a prepared quality review with agreed criteria, roles, issue logging and follow-up. The product is accepted only after recorded issues are handled and criteria demonstrated. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
Question 206
During a PRINCE2 management-stage review, the team encounters this situation: a coastal protection initiative faces procurement inflation that invalidates its earlier cost-benefit forecast. What is the most appropriate controlled response? Select ONE answer.
- Apply controlled change authorization within an agreed change budget and maintain a decision log
- Refresh life-cycle costs, assumptions and the investment justification before requesting commitment
- Translate relevant lessons into owned improvements and monitor completion as part of stage controls
- Escalate threats that threaten delegated tolerance while managing routine risks at the proper level
Explanation
Correct Answer
B:First, compare new vendor and operating-cost estimates with the cost assumptions in the business case. Refresh life-cycle costs, assumptions and the investment justification before requesting commitment. Business justification depends on credible future cost as well as delivery output. Success means the board considers a transparent forecast with affordable funding and defensible benefits. Repeating check cost assumptions regularly and escalate predicted breaches against tolerance helps prevent recurrence. By contrast, the response tied to this evidence is: Refresh life-cycle costs, assumptions and the investment justification before requesting commitment.
Incorrect Answers
A:Apply controlled change authorization within an agreed change budget and maintain a decision log. Change expenditure stays within authority and project forecasts reflect cumulative commitments. The board considers a transparent forecast with affordable funding and defensible benefits.
C:Translate relevant lessons into owned improvements and monitor completion as part of stage controls. Later stage reports show implemented learning and reduced recurrence. The board considers a transparent forecast with affordable funding and defensible benefits. By contrast, the response tied to this evidence is: Refresh life-cycle costs, assumptions and the investment justification before requesting commitment.
D:Escalate threats that threaten delegated tolerance while managing routine risks at the proper level. Risk governance requires clear boundaries between routine response and exception. The board considers a transparent forecast with affordable funding and defensible benefits.
Question 207
The project management team is troubleshooting this situation: a coastal protection initiative faces procurement inflation that invalidates its earlier cost-benefit forecast. Which check isolates the likely operating dependency? Select ONE answer.
- Check reviewer readiness, product description and unresolved review findings
- Compare opportunity assumptions, probability and benefit with the current business case
- Compare new vendor and operating-cost estimates with the cost assumptions in the business case
- Inspect assurance mandates and conflicts of interest against project delivery responsibilities
Explanation
Correct Answer
C:The strongest first investigation is to compare new vendor and operating-cost estimates with the cost assumptions in the business case. Business justification depends on credible future cost as well as delivery output. If that evidence confirms the issue, the team should refresh life-cycle costs, assumptions and the investment justification before requesting commitment. A subsequent acceptance check should confirm this result: The board considers a transparent forecast with affordable funding and defensible benefits. This check produces evidence before any broad configuration change, avoiding the risky proposal to hide indirect costs so the project's original benefit-cost ratio remains unchanged. By contrast, the response tied to this evidence is: Compare new vendor and operating-cost estimates with the cost assumptions in the business case.
Incorrect Answers
A:Check reviewer readiness, product description and unresolved review findings. The product is accepted only after recorded issues are handled and criteria demonstrated. The board considers a transparent forecast with affordable funding and defensible benefits. The relevant investigation is: Compare new vendor and operating-cost estimates with the cost assumptions in the business case.
B:Compare opportunity assumptions, probability and benefit with the current business case. The selected opportunity produces measurable value without violating risk tolerance. The board considers a transparent forecast with affordable funding and defensible benefits. The relevant investigation is: Compare new vendor and operating-cost estimates with the cost assumptions in the business case.
D:Inspect assurance mandates and conflicts of interest against project delivery responsibilities. The board receives objective challenge and evidence without confusing assurance and management. The board considers a transparent forecast with affordable funding and defensible benefits. The relevant investigation is: Compare new vendor and operating-cost estimates with the cost assumptions in the business case.
Question 208
An administrator claims the following problem is resolved: a coastal protection initiative faces procurement inflation that invalidates its earlier cost-benefit forecast. Which measured outcome confirms that claim? Select ONE answer.
- The risk register covers material exposures with described causes and impacts
- Risk ratings distinguish priority exposures and support defensible response decisions
- The product is accepted only after recorded issues are handled and criteria demonstrated
- The board considers a transparent forecast with affordable funding and defensible benefits
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to check cost assumptions regularly and escalate predicted breaches against tolerance. The decisive acceptance evidence is this result: The board considers a transparent forecast with affordable funding and defensible benefits. Business justification depends on credible future cost as well as delivery output. The operating team should diagnose it by checking whether it can compare new vendor and operating-cost estimates with the cost assumptions in the business case, then refresh life-cycle costs, assumptions and the investment justification before requesting commitment where justified. By contrast, the response tied to this evidence is: The board considers a transparent forecast with affordable funding and defensible benefits.
Incorrect Answers
A:The risk register covers material exposures with described causes and impacts. The board considers a transparent forecast with affordable funding and defensible benefits.
B:Risk ratings distinguish priority exposures and support defensible response decisions. The board considers a transparent forecast with affordable funding and defensible benefits.
C:The product is accepted only after recorded issues are handled and criteria demonstrated. The board considers a transparent forecast with affordable funding and defensible benefits.
Question 209
After resolving the following issue, the operations team wants to prevent a recurrence: a coastal protection initiative faces procurement inflation that invalidates its earlier cost-benefit forecast. Which ongoing control is best? Select ONE answer.
- Check cost assumptions regularly and escalate predicted breaches against tolerance
- Review information integrity and sharing controls whenever tools or teams change
- Include support-readiness reviews in future product handovers
- Reconcile team plans and work packages whenever delivery methods or dependencies change
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to refresh life-cycle costs, assumptions and the investment justification before requesting commitment and diagnostic evidence to compare new vendor and operating-cost estimates with the cost assumptions in the business case. Periodic testing should confirm this result: The board considers a transparent forecast with affordable funding and defensible benefits. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to check cost assumptions regularly and escalate predicted breaches against tolerance. Business justification depends on credible future cost as well as delivery output. By contrast, the response tied to this evidence is: Check cost assumptions regularly and escalate predicted breaches against tolerance.
Incorrect Answers
B:Review information integrity and sharing controls whenever tools or teams change. Digital information management supports accurate governance and safe collaboration. The board considers a transparent forecast with affordable funding and defensible benefits. To avoid recurrence, check cost assumptions regularly and escalate predicted breaches against tolerance.
C:Include support-readiness reviews in future product handovers. Receiving owners confirm the product is acceptable and usable in live operations. The board considers a transparent forecast with affordable funding and defensible benefits. To avoid recurrence, check cost assumptions regularly and escalate predicted breaches against tolerance.
D:Reconcile team plans and work packages whenever delivery methods or dependencies change. Teams may plan work flexibly but cannot unilaterally change authorized product acceptance. The board considers a transparent forecast with affordable funding and defensible benefits. To avoid recurrence, check cost assumptions regularly and escalate predicted breaches against tolerance.
Question 210
A project manager is under pressure to address the following issue quickly: a coastal protection initiative faces procurement inflation that invalidates its earlier cost-benefit forecast. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Classify actual problems, requests for change and off-specifications in the issue process
- Hide indirect costs so the project's original benefit-cost ratio remains unchanged
- Update role descriptions, decision limits and interface responsibilities to match the current organization
- Develop a product breakdown and product flow before deriving activities and resources
Explanation
Correct Answer
B:The unsafe shortcut is to hide indirect costs so the project's original benefit-cost ratio remains unchanged. Business justification depends on credible future cost as well as delivery output. The defensible response is instead to refresh life-cycle costs, assumptions and the investment justification before requesting commitment, using the diagnostic step to compare new vendor and operating-cost estimates with the cost assumptions in the business case before changing settings. Afterward, the team should confirm this result: The board considers a transparent forecast with affordable funding and defensible benefits. It must maintain the safeguard to check cost assumptions regularly and escalate predicted breaches against tolerance. By contrast, the response tied to this evidence is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
Incorrect Answers
A:Classify actual problems, requests for change and off-specifications in the issue process. Each issue has the appropriate impact analysis and decision path. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
C:Update role descriptions, decision limits and interface responsibilities to match the current organization. Each major decision and delivery obligation maps to a competent accountable role. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.
D:Develop a product breakdown and product flow before deriving activities and resources. The plan covers required products in a logical sequence with explicit quality expectations. The board considers a transparent forecast with affordable funding and defensible benefits. The shortcut most directly implicated here is: Hide indirect costs so the project's original benefit-cost ratio remains unchanged.