Question 150
Which TWO claims link a supported response and validation for this wired switching scenario? An uplink records thousands of FCS errors during cable movement but the technician believes Ethernet frames provide automatic retransmission.
- Unsafe shortcut: Suppress FCS counters and claim TCP retransmissions will prevent all performance impact.
- Action: Repair the physical error source and let appropriate upper-layer protocols recover dropped data.
- Verification: Latency-sensitive services stay responsive while bulk traffic uses its allowed residual capacity.
- Action: Validate the access or trunk VLAN and spanning-tree state separately from LLDP discovery.
- Verification: FCS errors stop and higher-layer retransmission and application latency improve.
Explanation
Correct Answers
B:Action: Repair the physical error source and let appropriate upper-layer protocols recover dropped data. Ethernet FCS detects damaged frames; link-layer Ethernet does not normally retransmit corrupted frames by itself.
E:Verification: FCS errors stop and higher-layer retransmission and application latency improve. Ethernet FCS detects damaged frames; link-layer Ethernet does not normally retransmit corrupted frames by itself.
Incorrect Answers
A:Ethernet FCS detects damaged frames; link-layer Ethernet does not normally retransmit corrupted frames by itself.
C:Verification: Latency-sensitive services stay responsive while bulk traffic uses its allowed residual capacity. This is validation for another condition (A backup job saturates a campus uplink and a technician proposes policing voice media to solve file-transfer congestion.). Here verify: FCS errors stop and higher-layer retransmission and application latency improve.
D:This remedy fits a different fault (An installer sees a neighbor device in LLDP but no user data passes on its port and assumes LLDP guarantees VLAN forwarding.). For this case use: Repair the physical error source and let appropriate upper-layer protocols recover dropped data.
Question 151
What mistaken approach is MOST likely to worsen this networking fault? A proposed campus core has ample 10G ports but a forwarding capacity below aggregate expected east-west traffic.
- Document a tested service restoration result before closing an outage.
- Verify spanning-tree topology after changing redundant links.
- Multiply port labels without checking forwarding capacity and declare zero oversubscription.
- Test both allowed and denied network paths after access-control changes.
Explanation
Correct Answer
C:Multiply port labels without checking forwarding capacity and declare zero oversubscription. Switching system throughput and fabric limits are distinct from the sum of advertised front-panel line rates. Safer action: Review forwarding performance and interface mix when selecting the core switching model.
Incorrect Answers
A:Document a tested service restoration result before closing an outage. A successful command alone does not prove business recovery. For the stated issue, the appropriate action is: Review forwarding performance and interface mix when selecting the core switching model.
B:Verify spanning-tree topology after changing redundant links. Layer 2 redundancy must remain loop-free. For the stated issue, the appropriate action is: Review forwarding performance and interface mix when selecting the core switching model.
D:Test both allowed and denied network paths after access-control changes. Negative tests confirm unauthorized paths remain restricted. For the stated issue, the appropriate action is: Review forwarding performance and interface mix when selecting the core switching model.
Question 152
An engineer wants to troubleshoot before making a change. Which sequence is MOST appropriate? Several users see intermittent connection failures to a local NAS after it moved ports but an old static MAC mapping remains on the switch.
- First, Check static/dynamic MAC table entries, NAS link location and ARP resolution. Then, Remove or update the obsolete static MAC entry and validate dynamic forwarding learning.
- First, Review MAC move events, trunk topology, STP roles and broadcast counters. Then, Find and correct the unintended Layer 2 loop or unapproved bridge and restore STP protection.
- First, Inspect route tables at both endpoints, traceroute each direction and firewall drop logs. Then, Establish an approved return route and validate both forward and reverse paths.
- First, Inspect interface disabled reason, BPDU guard event, neighbor identity and local topology. Then, Determine whether the attached device is appropriate and correct its cabling or edge-policy treatment before recovery.
Explanation
Correct Answer
A:Static MAC forwarding entries override dynamic learning and can point traffic to an obsolete location.
Incorrect Answers
B:This plan investigates a different issue (A switch repeatedly learns one server MAC on two trunk ports while broadcast utilization rises sharply.). For the case described, inspect: Check static/dynamic MAC table entries, NAS link location and ARP resolution.
C:This plan investigates a different issue (Traffic reaches a remote printer server from a new department VLAN, but the printer server's reply follows a firewall with no path back.). For the case described, inspect: Check static/dynamic MAC table entries, NAS link location and ARP resolution.
D:This plan investigates a different issue (A newly deployed access point cannot connect after switch security protection placed its port into a disabled state on detecting a BPDU.).
Question 153
Following the planned correction, which outcome MOST strongly confirms success? An engineer adds a route for a remote monitoring network using a next hop that is not reachable on any connected interface.
- Untagged frames enter the intended network at both ends and unexpected VLAN leakage disappears.
- The intended route is active and packets reach the monitoring segment without forwarding loop.
- The link negotiates the expected rate with low physical errors after certifying the cable plant.
- The host uses its correct /26 gateway and reaches the remote /26 via a routed hop.
Explanation
Correct Answer
B:The intended route is active and packets reach the monitoring segment without forwarding loop. Corresponding action: Correct the next hop or provide a supported recursive route resolution path with reachable adjacency.
Incorrect Answers
A:That observation verifies a different fault (An inter-switch trunk receives untagged management traffic into different native VLANs at opposite ends.). For the question at hand, verify: The intended route is active and packets reach the monitoring segment without forwarding loop.
C:That observation verifies a different fault (An office switch negotiates 100 Mb/s unexpectedly after a patch-panel repair although both endpoints support gigabit copper.). For the question at hand, verify: The intended route is active and packets reach the monitoring segment without forwarding loop.
D:That observation verifies a different fault (A switch SVI is configured as 192.0.2.126/26 while a new host uses 192.0.2.130/26 and expects same-subnet ARP.).
Question 154
Select TWO statements: the correct intervention and its observed verification in this AOS-CX case. A wall outlet repeatedly flaps between operational states, but the network team replaces the switch firmware before testing the copper run.
- Action: Perform physical cable/termination testing and correlate port error counters before software changes.
- Verification: The certified cable plant sustains negotiated speed and port flap events disappear.
- Verification: Both links report matching partner and aggregator state with expected multiflow forwarding capacity.
- Unsafe shortcut: Factory reset the entire switch whenever one office jack has intermittent continuity.
- Action: Review boot history, active firmware checksum and crash diagnostics against the supported vendor image.
Explanation
Correct Answers
A:Action: Perform physical cable/termination testing and correlate port error counters before software changes. A repeatable physical diagnostic sequence avoids attributing cabling faults to switch software.
B:Verification: The certified cable plant sustains negotiated speed and port flap events disappear. A repeatable physical diagnostic sequence avoids attributing cabling faults to switch software.
Incorrect Answers
C:This is validation for another condition (A campus uplink LAG stays up but only one of two links forwards, and the nonforwarding member shows a different partner system ID.). Here verify: The certified cable plant sustains negotiated speed and port flap events disappear.
D:Unsafe shortcut: Factory reset the entire switch whenever one office jack has intermittent continuity. A repeatable physical diagnostic sequence avoids attributing cabling faults to switch software. Better response: Perform physical cable/termination testing and correlate port error counters before software changes.
E:This remedy fits a different fault (A switch reboots unexpectedly after a maintenance window and staff blame a network loop without confirming image integrity or boot logs.).
Question 155
For the following AOS-CX switching task, which intervention should the engineer take FIRST? A quarterly upgrade plan has a start time but no explicit abort criteria if a routing adjacency fails after the first switch is updated.
- Define measurable health gates, stop conditions and tested rollback steps before beginning the staged change.
- Set event classifications and thresholds that distinguish routine edge changes from material uplink or stack faults.
- Issue a supported least-privileged API identity and rotate or revoke the original overpowered credential.
- Maintain software/version inventory, determine applicability and create risk-based supported patch plans.
Explanation
Correct Answer
A:Define measurable health gates, stop conditions and tested rollback steps before beginning the staged change. Effective maintenance plans depend on monitoring checkpoints and clear decision thresholds, not only a change window. Verified result: If the pilot fails, deployment stops and previously approved routing and access recover within limits.
Incorrect Answers
B:This change serves a different network condition (A NOC pages engineers every time an access port changes state even when users regularly unplug docking stations at closing time.), not the issue described. Appropriate response here: Define measurable health gates, stop conditions and tested rollback steps before beginning the staged change.
C:This change serves a different network condition (An internal monitoring application holds a full-config-change REST API credential even though it collects only interface statistics.), not the issue described. Appropriate response here: Define measurable health gates, stop conditions and tested rollback steps before beginning the staged change.
D:This change serves a different network condition (An AOS-CX security notice names a vulnerable release, but the team lacks an inventory tying installed versions to affected devices.), not the issue described. Appropriate response here: Define measurable health gates, stop conditions and tested rollback steps before beginning the staged change.
Question 156
Which proposed action would be LEAST defensible for this AOS-CX or network problem? A two-building deployment wants separate spanning-tree paths for user and voice VLANs but maps all VLANs into one MST instance.
- Configure a different MST region revision on each switch and assume they share one region.
- Verify the correct device and port before changing production configuration.
- Maintain complete asset records and switch software inventory.
- Confirm the approved gateway for traffic leaving a subnet.
Explanation
Correct Answer
A:Configure a different MST region revision on each switch and assume they share one region. MSTP can map VLANs into multiple logical spanning-tree instances to distribute paths safely. Safer action: Define supported MST instances and consistent VLAN mapping throughout the intended MST region.
Incorrect Answers
B:Verify the correct device and port before changing production configuration. Accurate change scoping prevents unintended service disruption. For the stated issue, the appropriate action is: Define supported MST instances and consistent VLAN mapping throughout the intended MST region.
C:Maintain complete asset records and switch software inventory. Accurate inventory underpins maintenance and vulnerability handling. For the stated issue, the appropriate action is: Define supported MST instances and consistent VLAN mapping throughout the intended MST region.
D:Confirm the approved gateway for traffic leaving a subnet. Off-subnet forwarding depends on usable Layer 3 next hops. For the stated issue, the appropriate action is: Define supported MST instances and consistent VLAN mapping throughout the intended MST region.
Question 157
Identify the unsafe shortcut to REJECT for the following campus switching situation: A stack of badge readers reboots during shift change after the access switch exhausts its available PoE budget.
- Separate an Ethernet tagging fault from an IP route fault.
- Verify HPE Aruba Central enrollment and group assignment after provisioning.
- Keep recovery configuration files protected and versioned.
- Assume switchport link-up guarantees unlimited power for every connected endpoint.
Explanation
Correct Answer
D:Assume switchport link-up guarantees unlimited power for every connected endpoint. PoE power delivered by ports is constrained by device requirements and the switch power budget. Safer action: Calculate total power demand and allocate or upgrade supported power capacity for priority ports.
Incorrect Answers
A:Separate an Ethernet tagging fault from an IP route fault. Correct problem-layer isolation avoids ineffective reconfiguration. For the stated issue, the appropriate action is: Calculate total power demand and allocate or upgrade supported power capacity for priority ports.
B:Verify HPE Aruba Central enrollment and group assignment after provisioning. Managed inventory and applied templates determine operational state. For the stated issue, the appropriate action is: Calculate total power demand and allocate or upgrade supported power capacity for priority ports.
C:Keep recovery configuration files protected and versioned. Backup confidentiality and integrity support safe restoration. For the stated issue, the appropriate action is: Calculate total power demand and allocate or upgrade supported power capacity for priority ports.
Question 158
What fundamental switching or routing concept is MOST relevant here? A school runs critical badge readers from a PoE switch with dual power supplies but disables power redundancy allocation.
- Access platform selection must consider port density, endpoint power and operational features rather than only device cost.
- Out-of-band management separates control access from production forwarding dependencies.
- PoE redundancy under power supply failure depends on actual reserved capacity and switch policy.
- Access bandwidth and aggregated upstream capacity are separate sizing dimensions.
Explanation
Correct Answer
C:PoE redundancy under power supply failure depends on actual reserved capacity and switch policy. Appropriate intervention: Configure and validate the supported redundant PoE budget appropriate to both PSU capacities and critical endpoints.
Incorrect Answers
A:This concept applies to another switch problem (An office expansion needs 96 wired desks with PoE handsets, and purchasing selects one unmanaged eight-port switch based on low price.). PoE redundancy under power supply failure depends on actual reserved capacity and switch policy.
B:This concept applies to another switch problem (A network architect wants troubleshooting access during a data-VLAN outage but locates all switch management behind the same failed user trunk.). PoE redundancy under power supply failure depends on actual reserved capacity and switch policy.
D:This concept applies to another switch problem (A remote closet has forty gigabit users and a 1-Gb/s uplink saturated by backups, yet planners buy more client ports without changing aggregation.). PoE redundancy under power supply failure depends on actual reserved capacity and switch policy.
Question 159
Which proposed action would be LEAST defensible for this AOS-CX or network problem? During afternoon use, a small office suffers bursts of MAC-table instability every time a contractor unplugs a mini-switch in a meeting room.
- Preserve separate management and guest network security boundaries.
- Review current NTP and syslog health during an incident.
- Disable RSTP on every uplink to avoid topology-change notifications.
- Verify the correct device and port before changing production configuration.
Explanation
Correct Answer
C:Disable RSTP on every uplink to avoid topology-change notifications. Frequent spanning-tree topology changes can trigger MAC-table flushes and temporary forwarding disruption. Safer action: Correlate STP topology-change events with affected edge ports and apply appropriate edge protection policies.
Incorrect Answers
A:Preserve separate management and guest network security boundaries. Least-privilege reachability limits management-plane exposure. For the stated issue, the appropriate action is: Correlate STP topology-change events with affected edge ports and apply appropriate edge protection policies.
B:Review current NTP and syslog health during an incident. Time-aligned logs support sound fault analysis. For the stated issue, the appropriate action is: Correlate STP topology-change events with affected edge ports and apply appropriate edge protection policies.
D:Verify the correct device and port before changing production configuration. Accurate change scoping prevents unintended service disruption. For the stated issue, the appropriate action is: Correlate STP topology-change events with affected edge ports and apply appropriate edge protection policies.
Question 160
Identify the unsafe shortcut to REJECT for the following campus switching situation: An internal monitoring application holds a full-config-change REST API credential even though it collects only interface statistics.
- Check optic and fiber compatibility when physical errors appear.
- Retain change approval and operator accountability.
- Preserve separate management and guest network security boundaries.
- Assign the network monitoring dashboard the most powerful local administrative role by default.
Explanation
Correct Answer
D:Assign the network monitoring dashboard the most powerful local administrative role by default. Automation identities should receive only the permissions required for their intended management actions. Safer action: Issue a supported least-privileged API identity and rotate or revoke the original overpowered credential.
Incorrect Answers
A:Check optic and fiber compatibility when physical errors appear. Optical power and media standards constrain link operation. For the stated issue, the appropriate action is: Issue a supported least-privileged API identity and rotate or revoke the original overpowered credential.
B:Retain change approval and operator accountability. Production changes require traceable ownership and risk controls. For the stated issue, the appropriate action is: Issue a supported least-privileged API identity and rotate or revoke the original overpowered credential.
C:Preserve separate management and guest network security boundaries. Least-privilege reachability limits management-plane exposure. For the stated issue, the appropriate action is: Issue a supported least-privileged API identity and rotate or revoke the original overpowered credential.