cert
cert-1
cert-2

Pass CompTIA SK0-005 Exam in First Attempt Guaranteed!

Get 100% Latest Exam Questions, Accurate & Verified Answers to Pass the Actual Exam!
30 Days Free Updates, Instant Download!

cert-5
cert-6
SK0-005 Exam - Verified By Experts
SK0-005 Premium Bundle
$29.98

SK0-005 Premium Bundle

$79.99
$109.97
  • Premium File 617 Questions & Answers. Last update: Nov 13, 2026
  • Training Course 139 Video Lectures
  • Study Guide 533 Pages
 
$109.97
$79.99
accept 21 downloads in last 7 days
block-screenshots
Purchase CompTIA SK0-005 Exam Training Products Individually
CompTIA SK0-005 Premium File
Premium File 617 Q&A
$76.99$69.99
CompTIA SK0-005 Video Training Course
Training Course 139 Lectures
$21.99 $19.99
CompTIA SK0-005 PDF Study Guide
Study Guide 533 Pages
$21.99 $19.99
CompTIA SK0-005 Practice Test 37

Question 360

A change board is planning a verified response to this server event: A virtual server is promoted to production without recording application owner, support contract, dependency diagram or approved change. For the Asset inventory and change records issue, which response elements belong in the approved plan? Select TWO answers.

  1. Maintain supported, patched golden images with version pinning, vulnerability scanning and reproducible configuration validation.
  2. A rehearsed failover restores service within RTO with observed data loss no greater than RPO.
  3. Reconcile discovered hardware IDs, IP/MAC mappings, rack positions, CMDB ownership and change tickets.
  4. Update authoritative asset, dependency and change records at deployment and verify ownership and configuration links.
  5. Treat documentation updates as optional because the server responds to pings.

Explanation

Correct Answer

C:

These observations investigate the exact Asset inventory and change records failure rather than unrelated components. The expected technical relationship is: Accurate inventories and documented changes shorten incident response and support accountable operations.

D:

A successful outcome is: Inventory and dependency records match deployed assets and can be used to locate each service during incidents. This is the appropriate targeted correction for Asset inventory and change records.

Incorrect Answers

A:

For this incident, the relevant principle is: Accurate inventories and documented changes shorten incident response and support accountable operations. This statement concerns Golden image lifecycle and OS support, a different Server+ technical control.

B:

For this incident, the relevant principle is: Accurate inventories and documented changes shorten incident response and support accountable operations. This statement concerns Database replication and failover objective, a different Server+ technical control.

E:

Incident: A virtual server is promoted to production without recording application owner, support contract, dependency diagram or approved change.

Question 361

A server administrator is investigating a server issue involving per-core and virtual machine licensing: A company doubles CPU cores in a licensed database host but keeps the old per-core entitlement count. The change must address the documented fault without creating unrelated risk. Which corrective action is most appropriate? Select ONE best answer.

  1. Maintain a software bill of materials and honor relevant distribution, attribution and support-license obligations.
  2. Update authoritative asset, dependency and change records at deployment and verify ownership and configuration links.
  3. Assume installing licensed software on one physical server authorizes unlimited replicas everywhere.
  4. Recalculate entitlement by the vendor's applicable core, socket, VM and mobility terms before changing deployment.

Explanation

Correct Answer

D:

Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Incorrect Answers

A:

That option would maintain a software bill of materials and honor relevant distribution, attribution and support-license obligations, but it addresses a different concern. Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

B:

That option would update authoritative asset, dependency and change records at deployment and verify ownership and configuration links, but it addresses a different concern. Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

C:

This is the unsafe shortcut in the Per-core and virtual machine licensing scenario, not a justified remediation or diagnostic. Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Question 362

While reviewing the CompTIA Server+ administration incident, a technician learns: A company doubles CPU cores in a licensed database host but keeps the old per-core entitlement count. Which principle most directly explains how to address the described issue safely? Select ONE best answer.

  1. DHCP broadcasts normally need a relay across routed subnets, and leases must match the client network and scope policy.
  2. Time synchronization is required for trustworthy logs, certificate validation windows and time-sensitive authentication.
  3. Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.
  4. A successful OS install does not establish ongoing supportability or image provenance; images require lifecycle controls.

Explanation

Correct Answer

C:

Applying it leads to this operational action: Recalculate entitlement by the vendor's applicable core, socket, VM and mobility terms before changing deployment.

Incorrect Answers

A:

This statement concerns DHCP scope and relay design, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

B:

This statement concerns NTP time sources and clock skew, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

D:

This statement concerns Golden image lifecycle and OS support, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

Question 363

Before a server change is approved, the on-call engineer receives this incident report: A company doubles CPU cores in a licensed database host but keeps the old per-core entitlement count. Which evidence would most directly establish the stated root-cause hypothesis? Select ONE best answer.

  1. Assume installing licensed software on one physical server authorizes unlimited replicas everywhere.
  2. Inspect package SBOM, license texts, modification/distribution history and subscription records.
  3. Inventory physical cores, virtual instances, license assignments, agreement version and current usage.
  4. Inspect DHCP discover/offer captures, relay configuration, scope utilization and leased default gateways.

Explanation

Correct Answer

C:

These observations investigate the exact Per-core and virtual machine licensing failure rather than unrelated components. Incident: A company doubles CPU cores in a licensed database host but keeps the old per-core entitlement count.

Incorrect Answers

A:

This is the unsafe shortcut in the Per-core and virtual machine licensing scenario, not a justified remediation or diagnostic. Incident: A company doubles CPU cores in a licensed database host but keeps the old per-core entitlement count.

B:

For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage.

D:

For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Question 364

After the team implements a targeted remediation for Per-core and virtual machine licensing, the original incident was: A company doubles CPU cores in a licensed database host but keeps the old per-core entitlement count. Which acceptance criterion would best demonstrate a durable and safe resolution? Select ONE best answer.

  1. Offset falls within the authentication policy threshold and timestamps align across systems.
  2. Inventory and dependency records match deployed assets and can be used to locate each service during incidents.
  3. Installed instances and host resources are covered by documented valid entitlements after migration.
  4. The OS boots consistently using the intended UEFI entry and approved partition scheme after reboot tests.

Explanation

Correct Answer

C:

Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Incorrect Answers

A:

This statement concerns NTP time sources and clock skew, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair.

B:

This statement concerns Asset inventory and change records, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

D:

This statement concerns UEFI boot and GPT provisioning, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

Question 365

A change board is planning a verified response to this server event: A company doubles CPU cores in a licensed database host but keeps the old per-core entitlement count. For the Per-core and virtual machine licensing issue, which response elements belong in the approved plan? Select ONE best answer.

  1. Assume installing licensed software on one physical server authorizes unlimited replicas everywhere.
  2. Query each resolver directly, inspect answer sections and TTLs, compare private/public zones and client resolver lists.
  3. Recalculate entitlement by the vendor's applicable core, socket, VM and mobility terms before changing deployment. Then validate the change by confirming: Installed instances and host resources are covered by documented valid entitlements after migration.
  4. Configure nonoverlapping DHCP scopes, appropriate relay or helper settings and correct lease, gateway and DNS options.

Explanation

Correct Answer

C:

Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. The proposed change and outcome assessment work together for Per-core and virtual machine licensing.

Incorrect Answers

A:

This is the unsafe shortcut in the Per-core and virtual machine licensing scenario, not a justified remediation or diagnostic. Discriminate using: Inventory physical cores, virtual instances, license assignments, agreement version and current usage.

B:

This statement concerns DNS split-horizon and resolver troubleshooting, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

D:

That option would configure nonoverlapping DHCP scopes, appropriate relay or helper settings and correct lease, gateway and DNS options, but it addresses a different concern. Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Question 366

A server administrator is investigating a server issue involving per-core and virtual machine licensing: A datacenter consolidates Windows Server VMs onto a new cluster without checking host/VM licensing or mobility rights. The change must address the documented fault without creating unrelated risk. Which corrective action is most appropriate? Select ONE best answer.

  1. Assume installing licensed software on one physical server authorizes unlimited replicas everywhere.
  2. Recalculate entitlement by the vendor's applicable core, socket, VM and mobility terms before changing deployment.
  3. Configure redundant trusted time sources and verify host, hypervisor and directory time hierarchy with monitored offset.
  4. Restrict PXE and imaging infrastructure to trusted networks and protect signed, versioned images and unattended-install credentials.

Explanation

Correct Answer

B:

Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Incorrect Answers

A:

This is the unsafe shortcut in the Per-core and virtual machine licensing scenario, not a justified remediation or diagnostic. Incident: A datacenter consolidates Windows Server VMs onto a new cluster without checking host/VM licensing or mobility rights.

C:

That option would configure redundant trusted time sources and verify host, hypervisor and directory time hierarchy with monitored offset, but it addresses a different concern. Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

D:

This statement concerns PXE and unattended installation integrity, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

Question 367

While reviewing the CompTIA Server+ administration incident, a technician learns: A datacenter consolidates Windows Server VMs onto a new cluster without checking host/VM licensing or mobility rights. Which principle most directly explains how to address the described issue safely? Select ONE best answer.

  1. Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.
  2. Layer-two VLAN membership and layer-three routing are distinct requirements; correct IP syntax alone does not guarantee reachability.
  3. Network boot is a high-trust supply chain; authenticated image provenance and secret protection matter as much as automation speed.
  4. Time synchronization is required for trustworthy logs, certificate validation windows and time-sensitive authentication.

Explanation

Correct Answer

A:

Applying it leads to this operational action: Recalculate entitlement by the vendor's applicable core, socket, VM and mobility terms before changing deployment.

Incorrect Answers

B:

This statement concerns VLAN segmentation and default gateway, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

C:

This statement concerns PXE and unattended installation integrity, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair.

D:

This statement concerns NTP time sources and clock skew, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

Question 368

Before a server change is approved, the on-call engineer receives this incident report: A datacenter consolidates Windows Server VMs onto a new cluster without checking host/VM licensing or mobility rights. Which evidence would most directly establish the stated root-cause hypothesis? Select ONE best answer.

  1. Measure apply lag, replication errors, client reconnection behavior and failover event timestamps.
  2. Inventory physical cores, virtual instances, license assignments, agreement version and current usage.
  3. Inspect switch port VLAN/trunk state, ARP tables, interface settings, routing table and path traces.
  4. Assume installing licensed software on one physical server authorizes unlimited replicas everywhere.

Explanation

Correct Answer

B:

These observations investigate the exact Per-core and virtual machine licensing failure rather than unrelated components. Incident: A datacenter consolidates Windows Server VMs onto a new cluster without checking host/VM licensing or mobility rights.

Incorrect Answers

A:

For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

C:

For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. This statement concerns VLAN segmentation and default gateway, a different Server+ technical control.

D:

Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Question 369

After the team implements a targeted remediation for Per-core and virtual machine licensing, the original incident was: A datacenter consolidates Windows Server VMs onto a new cluster without checking host/VM licensing or mobility rights. Which acceptance criterion would best demonstrate a durable and safe resolution? Select ONE best answer.

  1. Deployments have traceable licenses and required notices or source obligations are fulfilled.
  2. Inventory and dependency records match deployed assets and can be used to locate each service during incidents.
  3. Offset falls within the authentication policy threshold and timestamps align across systems.
  4. Installed instances and host resources are covered by documented valid entitlements after migration.

Explanation

Correct Answer

D:

Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Incorrect Answers

A:

This statement concerns Open-source license obligations and audit, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

B:

This statement concerns Asset inventory and change records, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. A targeted investigation checks: Inventory physical cores, virtual instances, license assignments, agreement version and current usage. The desired recovery condition is: Installed instances and host resources are covered by documented valid entitlements after migration.

C:

This statement concerns NTP time sources and clock skew, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair. For this incident, the relevant principle is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Question 370

A change board is planning a verified response to this server event: A datacenter consolidates Windows Server VMs onto a new cluster without checking host/VM licensing or mobility rights. For the Per-core and virtual machine licensing issue, which response elements belong in the approved plan? Select TWO answers.

  1. Recalculate entitlement by the vendor's applicable core, socket, VM and mobility terms before changing deployment.
  2. Inventory physical cores, virtual instances, license assignments, agreement version and current usage.
  3. Assume installing licensed software on one physical server authorizes unlimited replicas everywhere.
  4. Assign supported switch VLAN modes and correct interface subnet, mask, gateway and routes; verify permitted inter-VLAN flows.
  5. Deployments have traceable licenses and required notices or source obligations are fulfilled.

Explanation

Correct Answer

A:

Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable. This is the appropriate targeted correction for Per-core and virtual machine licensing.

B:

These observations investigate the exact Per-core and virtual machine licensing failure rather than unrelated components. The expected technical relationship is: Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

Incorrect Answers

C:

Incident: A datacenter consolidates Windows Server VMs onto a new cluster without checking host/VM licensing or mobility rights.

D:

That option would assign supported switch VLAN modes and correct interface subnet, mask, gateway and routes; verify permitted inter-VLAN flows, but it addresses a different concern. Software rights depend on the actual product agreement and deployment topology; a paid license on one host is not always transferable.

E:

This statement concerns Open-source license obligations and audit, a different Server+ technical control. It does not directly address the reported Per-core and virtual machine licensing fault or prove its repair.