Question 490
A retail application release is scheduled without a rollback path for failed payment processing. Which project-management response BEST addresses the stated need?
Explanation
Correct Answer
Plan operational training, support ownership, go-live validation, monitoring and rollback before scheduling release to production. This targets the specific project decision. Transition planning bridges delivery and routine operations; a technically successful deployment without support readiness can still fail adoption. Before committing, assess: Inspect support readiness, training materials, release checklist, outage communication, acceptance and recovery procedures. Situation: A retail application release is scheduled without a rollback path for failed payment processing.
Incorrect Answers
Define quality standards, independent checks, test responsibilities, defect severity, and entry and exit criteria before execution. That response is associated with Quality assurance plan and test entry criteria and does not directly settle this case. Its relevant principle is: A QA plan defines how quality will be checked and assured; passing one smoke test does not satisfy all acceptance conditions. The stated case instead calls for: Plan operational training, support ownership, go-live validation, monitoring and rollback before scheduling release to production. Situation: A retail application release is scheduled without a rollback path for failed payment processing.
Identify affected stakeholders, classify their influence and interest, and choose engagement actions appropriate to their impact on the project. That response is associated with Stakeholder analysis and engagement and does not directly settle this case. Its relevant principle is: Stakeholder analysis includes people affected by outcomes as well as funders; importance varies by power, interest and change impact. The stated case instead calls for: Plan operational training, support ownership, go-live validation, monitoring and rollback before scheduling release to production. Situation: A retail application release is scheduled without a rollback path for failed payment processing.
Draft a sponsor-approved project charter with purpose, high-level scope, constraints, authority, and measurable success criteria. That response is associated with Project charter and measurable success criteria and does not directly settle this case. Its relevant principle is: A project charter establishes a formal purpose and initial authority; it is not a substitute for the later detailed work breakdown and schedule. The stated case instead calls for: Plan operational training, support ownership, go-live validation, monitoring and rollback before scheduling release to production. Situation: A retail application release is scheduled without a rollback path for failed payment processing.