Question 330
A government agency closes its design phase without required architecture approval and asks engineering to proceed anyway. Before acting, which evidence should the project team examine FIRST to assess the stated need?
Explanation
Correct Answer
Inspect completed phase deliverables, unresolved severity-one defects, signoff requirements, and dependencies for the next phase. This checks the relevant condition before the team intervenes. A phase gate protects investment and quality between stages; an optimistic status presentation cannot substitute for required signoff. The controlled response is: Conduct a phase gate review against pre-agreed entrance and exit criteria and document the decision to proceed, repeat or pause. Situation: A government agency closes its design phase without required architecture approval and asks engineering to proceed anyway.
Incorrect Answers
Review acceptance criteria, regulatory quality requirements, test environments, test coverage, and defect escalation thresholds. That evidence would investigate Quality assurance plan and test entry criteria, not the main uncertainty in this situation. To decide the current case, examine: Inspect completed phase deliverables, unresolved severity-one defects, signoff requirements, and dependencies for the next phase. Situation: A government agency closes its design phase without required architecture approval and asks engineering to proceed anyway.
Inspect labor effort estimates, hardware procurement, licensing renewals, contingency assumptions, and funding authority. That evidence would investigate Budget baseline and funding allocation, not the main uncertainty in this situation. To decide the current case, examine: Inspect completed phase deliverables, unresolved severity-one defects, signoff requirements, and dependencies for the next phase. Situation: A government agency closes its design phase without required architecture approval and asks engineering to proceed anyway.
Inspect vendor statement of work, SLA, deliverable evidence, open defects, invoice milestones, and corrective notices. That evidence would investigate Vendor performance and deliverable approval, not the main uncertainty in this situation. To decide the current case, examine: Inspect completed phase deliverables, unresolved severity-one defects, signoff requirements, and dependencies for the next phase. Situation: A government agency closes its design phase without required architecture approval and asks engineering to proceed anyway.