Question 260
A sponsor wants to see whether discovery, build, testing and release approvals are late, not every code commit. Which project-management response BEST addresses the stated need?
Explanation
Correct Answer
Use a milestone chart or concise status dashboard to convey significant completion dates and approved gate decisions to executives. This targets the specific project decision. Milestone charts summarize important checkpoints rather than individual task effort; they complement but do not replace detailed schedules. Before committing, assess: Inspect approved milestones, actual completion records, confidence in forecasts, and decision-maker needs. Situation: A sponsor wants to see whether discovery, build, testing and release approvals are late, not every code commit.
Incorrect Answers
Use a ticketing system with status, ownership, priority, resolution history, and escalation tracking for operational and project defects. That response is associated with Ticketing and case management workflow and does not directly settle this case. Its relevant principle is: Ticket systems manage discrete actionable requests and incidents; an informal mailbox alone lacks reliable assignment and status controls. The stated case instead calls for: Use a milestone chart or concise status dashboard to convey significant completion dates and approved gate decisions to executives. Situation: A sponsor wants to see whether discovery, build, testing and release approvals are late, not every code commit.
Use a requirements traceability matrix to link each accepted requirement to design, tests, defects and final acceptance evidence. That response is associated with Requirements Traceability Matrix and does not directly settle this case. Its relevant principle is: Traceability proves which requirements were implemented and tested; a count of passing tests without requirement mapping may hide omissions. The stated case instead calls for: Use a milestone chart or concise status dashboard to convey significant completion dates and approved gate decisions to executives. Situation: A sponsor wants to see whether discovery, build, testing and release approvals are late, not every code commit.
Use a control chart with a time-ordered process measure and control limits to distinguish routine variation from unusual process behavior. That response is associated with Control chart variation monitoring and does not directly settle this case. Its relevant principle is: Control charts assess process stability against statistical control limits; specification thresholds and control limits are not automatically identical. The stated case instead calls for: Use a milestone chart or concise status dashboard to convey significant completion dates and approved gate decisions to executives. Situation: A sponsor wants to see whether discovery, build, testing and release approvals are late, not every code commit.