cert
cert-1
cert-2

Pass The Open Group OGEA-103 Exam in First Attempt Guaranteed!

Get 100% Latest Exam Questions, Accurate & Verified Answers to Pass the Actual Exam!
30 Days Free Updates, Instant Download!

cert-5
cert-6
OGEA-103 Exam - Verified By Experts
OGEA-103 Premium Bundle
$14.99

OGEA-103 Premium Bundle

$74.99
$89.98
  • Premium File 183 Questions & Answers. Last update: Nov 08, 2026
  • Study Guide 488 Pages
 
$89.98
$74.99
accept 32 downloads in last 7 days
block-screenshots
Purchase The Open Group OGEA-103 Exam Training Products Individually
The Open Group OGEA-103 Premium File
Premium File 183 Q&A
$76.99$69.99
The Open Group OGEA-103 PDF Study Guide
Study Guide 488 Pages
$21.99 $19.99
The Open Group OGEA-103 Practice Test 25

Question 240

Which flawed shortcut is most directly contradicted by the following situation? An insurer builds overlapping claims applications without deciding which owns a given business service.

  1. An Architecture Contract with implementation contractors replaces authorization for initial architecture development.
  2. A value stream is the same thing as a sequence of technical API calls.
  3. Principles should be chosen only after Phase G has approved every implementation.
  4. A server support group is automatically the owner of every business-facing application service.

Explanation

Correct Answer

D:

This is precisely the false assumption to challenge for Phase C app ownership. The governing principle is: Application responsibilities should be explicit enough to avoid duplication and unmanaged dependencies. This matters here because which flawed shortcut is most directly contradicted by the following situation.

Incorrect Answers

A:

This is also a risky claim, but it directly concerns Phase A work authorization rather than the error in the current case: An insurer builds overlapping claims applications without deciding which owns a given business service.

B:

The shortcut would be dangerous for Phase B value streams; it is not the particular misconception driving the described Phase C app ownership situation (An insurer builds overlapping claims applications without deciding which owns a given business service).

C:

This false belief is about Preliminary architecture principles. The central misconception is that a server support group is automatically the owner of every business-facing application service.

Question 241

Architecture case: A manufacturing target application design still includes an obsolete workflow with no replacement or retirement plan. What should the architect do NEXT to resolve this concern?

  1. Perform application baseline-to-target gap analysis and record necessary changes.
  2. Reconcile work-package dependencies and value delivery when determining migration sequence.
  3. Translate availability and recovery requirements into technology resilience patterns and documented constraints.
  4. Communicate the proposed Architecture Vision and business value with major outcomes and high-level capabilities.

Explanation

Correct Answer

A:

This directly addresses Phase C app gaps. Application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages. A useful acceptance check is: Every unsupported or redundant application service has a target disposition.

Incorrect Answers

B:

Although relevant to Phase F benefit dependencies, this is not the most direct response to Phase C app gaps. For this decision, what matters is whether every unsupported or redundant application service has a target disposition.

C:

This action targets another architecture concern: Phase D resilience. The priority here is Phase C app gaps in this situation; it leaves the specific acceptance result unaddressed: every unsupported or redundant application service has a target disposition.

D:

This proposal belongs primarily to Phase A value proposition. It does not show that every unsupported or redundant application service has a target disposition.

Question 242

An architect is asked to explain the following situation: A manufacturing target application design still includes an obsolete workflow with no replacement or retirement plan. Which underlying principle is most relevant?

  1. Phase G Implementation Governance governs delivery against the agreed architecture and approved deviations.
  2. Application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.
  3. The Preliminary Phase prepares architecture work by establishing capability, governance, principles, and tailoring.
  4. Application responsibilities should be explicit enough to avoid duplication and unmanaged dependencies.

Explanation

Correct Answer

B:

This principle addresses Phase C app gaps. The preferred action is: Perform application baseline-to-target gap analysis and record necessary changes. Verify: Every unsupported or redundant application service has a target disposition.

Incorrect Answers

A:

This is a legitimate concept for Phase G architecture contract; it does not most directly account for A manufacturing target application design still includes an obsolete workflow with no replacement or retirement plan. The important distinction is that application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.

C:

That principle helps reason about Preliminary capability, but the described concern is specifically governed by Phase C app gaps. It does not explain application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.

D:

This is a legitimate concept for Phase C app ownership; it does not most directly account for A manufacturing target application design still includes an obsolete workflow with no replacement or retirement plan. The important distinction is that application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.

Question 243

Architecture acceptance review: A manufacturing target application design still includes an obsolete workflow with no replacement or retirement plan. Which evidence would BEST demonstrate that this concern was resolved?

  1. Affected activities have named actors, role ownership, and defined handoffs.
  2. Target technology choices trace to application requirements and approved standards.
  3. Every unsupported or redundant application service has a target disposition.
  4. The work-package dependency view shows prerequisites and integration constraints.

Explanation

Correct Answer

C:

This checks the Phase C app gaps outcome. The related decision is: Perform application baseline-to-target gap analysis and record necessary changes.

Incorrect Answers

A:

This result checks another area, Phase B stakeholder roles. For This case, it does not establish that every unsupported or redundant application service has a target disposition.

B:

This would provide assurance for Phase D platform standards, not the stated issue. It does not show every unsupported or redundant application service has a target disposition.

D:

This result checks another area, Phase E dependency consolidation. For This case, it does not establish that every unsupported or redundant application service has a target disposition.

Question 244

Which flawed shortcut is most directly contradicted by the following situation? A manufacturing target application design still includes an obsolete workflow with no replacement or retirement plan.

  1. Principles should be chosen only after Phase G has approved every implementation.
  2. All work packages are independent by definition once they receive a budget code.
  3. An application list alone proves every required integration is implemented.
  4. Application change gaps are irrelevant until after implementation is complete.

Explanation

Correct Answer

D:

This is precisely the false assumption to challenge for Phase C app gaps. The governing principle is: Application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.

Incorrect Answers

A:

This is also a risky claim, but it directly concerns Preliminary architecture principles rather than the error in the current case: A manufacturing target application design still includes an obsolete workflow with no replacement or retirement plan.

B:

The shortcut would be dangerous for Phase E dependency consolidation; it is not the particular misconception driving the described Phase C app gaps situation.

C:

This false belief is about Phase C application collaboration. The central misconception is that application change gaps are irrelevant until after implementation is complete.

Question 245

During an architecture engagement: A logistics program discovers its future capabilities have no supporting application services. Which response best addresses the immediate decision?

  1. Perform application baseline-to-target gap analysis and record necessary changes.
  2. Assess the architecture change request and determine its impact and suitable response in Phase H.
  3. Model the relevant business actors, roles, and process responsibilities in the Business Architecture.
  4. Consolidate gaps and dependencies into coherent work packages before sequencing delivery.

Explanation

Correct Answer

A:

This directly addresses Phase C app gaps. Application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages. A useful acceptance check is: Every unsupported or redundant application service has a target disposition. This matters here because a logistics program discovers its future capabilities have no supporting application services. Which response best….

Incorrect Answers

B:

This proposal belongs primarily to Phase H change trigger. It does not show that every unsupported or redundant application service has a target disposition.

C:

Although relevant to Phase B stakeholder roles, this is not the most direct response to Phase C app gaps. For this decision, what matters is whether every unsupported or redundant application service has a target disposition.

D:

This action targets another architecture concern: Phase E dependency consolidation. The priority here is Phase C app gaps in this situation; it leaves the specific acceptance result unaddressed: every unsupported or redundant application service has a target disposition.

Question 246

An architect is asked to explain the following situation: A logistics program discovers its future capabilities have no supporting application services. Which underlying principle is most relevant?

  1. Data Architecture should represent how information is created, shared, maintained, retained, and disposed of.
  2. Application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.
  3. Cross-domain gap dependencies must inform opportunities, work packages, and subsequent roadmap decisions.
  4. Phase G Implementation Governance governs delivery against the agreed architecture and approved deviations.

Explanation

Correct Answer

B:

This principle addresses Phase C app gaps. The preferred action is: Perform application baseline-to-target gap analysis and record necessary changes. Verify: Every unsupported or redundant application service has a target disposition. This matters here because an architect is asked to explain the following situation: A logistics program discovers its future capabilities have….

Incorrect Answers

A:

That principle helps reason about Phase C data lifecycle, but the described concern is specifically governed by Phase C app gaps. It does not explain application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.

C:

The statement addresses Phase E dependency consolidation. In the present case, a principle for Phase C app gaps is required: application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.

D:

That principle helps reason about Phase G architecture contract, but the described concern is specifically governed by Phase C app gaps. It does not explain application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages.

Question 247

Architecture acceptance review: A logistics program discovers its future capabilities have no supporting application services. Which evidence would BEST demonstrate that this concern was resolved?

  1. Candidate work packages address identified gaps with feasible solution paths.
  2. Shared data entities have approved definitions, owners, and quality obligations.
  3. Every unsupported or redundant application service has a target disposition.
  4. Named application owners and interfaces cover each critical business service.

Explanation

Correct Answer

C:

This checks the Phase C app gaps outcome. The related decision is: Perform application baseline-to-target gap analysis and record necessary changes. This matters here because architecture acceptance review: A logistics program discovers its future capabilities have no supporting application….

Incorrect Answers

A:

The observation could be valid elsewhere for Phase E solution options, but this case needs more direct Phase C app gaps evidence: every unsupported or redundant application service has a target disposition.

B:

This result checks another area, Phase C data ownership. For This case, it does not establish that every unsupported or redundant application service has a target disposition.

D:

The observation could be valid elsewhere for Phase C app ownership, but this case needs more direct Phase C app gaps evidence: every unsupported or redundant application service has a target disposition.

Question 248

Architecture peer review: A logistics program discovers its future capabilities have no supporting application services. Which assumption, if accepted, most directly leaves this problem unresolved?

  1. Security architecture is only a concern of Phase H, after deployment.
  2. An Architecture Contract is simply another name for the initial Architecture Vision.
  3. Every application always owns an independent copy of the authoritative enterprise data.
  4. Application change gaps are irrelevant until after implementation is complete.

Explanation

Correct Answer

D:

This is precisely the false assumption to challenge for Phase C app gaps. The governing principle is: Application Architecture identifies capability-enabling systems and gaps that inform subsequent work packages. This matters here because architecture peer review: A logistics program discovers its future capabilities have no supporting application….

Incorrect Answers

A:

This false belief is about Phase D network trust. The central misconception is that application change gaps are irrelevant until after implementation is complete.

B:

This is also a risky claim, but it directly concerns Phase G architecture contract rather than the error in the current case: A logistics program discovers its future capabilities have no supporting application services.

C:

The shortcut would be dangerous for Phase C data flow; it is not the particular misconception driving the described Phase C app gaps situation.

Question 249

During an architecture engagement: A multinational proposes incompatible hosting technologies for the same shared nonfunctional requirement. Which response best addresses the immediate decision?

  1. Develop a Target Technology Architecture with platform services and standard constraints for the intended workloads.
  2. Define technology security controls and trusted network paths consistent with cross-cutting architecture requirements.
  3. Model the relevant business actors, roles, and process responsibilities in the Business Architecture.
  4. Communicate the proposed Architecture Vision and business value with major outcomes and high-level capabilities.

Explanation

Correct Answer

A:

This directly addresses Phase D platform standards. Phase D defines technology services and infrastructure needed to support the target application and data architectures. A useful acceptance check is: Target technology choices trace to application requirements and approved standards.

Incorrect Answers

B:

This proposal belongs primarily to Phase D network trust. It does not show that target technology choices trace to application requirements and approved standards.

C:

Although relevant to Phase B stakeholder roles, this is not the most direct response to Phase D platform standards. For this decision, what matters is whether target technology choices trace to application requirements and approved standards.

D:

This action targets another architecture concern: Phase A value proposition. The priority here is Phase D platform standards in this situation; it leaves the specific acceptance result unaddressed: target technology choices trace to application requirements and approved standards.

Question 250

During design review: A multinational proposes incompatible hosting technologies for the same shared nonfunctional requirement. What is the strongest architectural reasoning for the decision?

  1. Data movement and sharing must support business processes and application interactions.
  2. Phase D defines technology services and infrastructure needed to support the target application and data architectures.
  3. Technology design must demonstrate how infrastructure capabilities satisfy nonfunctional architecture requirements.
  4. Architecture Change Management monitors change drivers and maintains architecture relevance over time.

Explanation

Correct Answer

B:

This principle addresses Phase D platform standards. The preferred action is: Develop a Target Technology Architecture with platform services and standard constraints for the intended workloads. Verify: Target technology choices trace to application requirements and approved standards.

Incorrect Answers

A:

That principle helps reason about Phase C data flow, but the described concern is specifically governed by Phase D platform standards. It does not explain phase D defines technology services and infrastructure needed to support the target application and data architectures.

C:

The statement addresses Phase D resilience. In the present case, a principle for Phase D platform standards is required: phase D defines technology services and infrastructure needed to support the target application and data architectures.

D:

That principle helps reason about Phase H change trigger, but the described concern is specifically governed by Phase D platform standards. It does not explain phase D defines technology services and infrastructure needed to support the target application and data architectures.