The Open Group OGEA-101 Practice Test 24
Question 230
An architecture office is reviewing a proposed change: A retailer reuses an existing architecture for a new subsidiary. Which work product or activity BEST fits the requirement? Choose ONE best answer.
- Use architecture to connect the operating model and systems transition
- Specify intermediate service and integration arrangements
- Adapt the existing ADM cycle to the subsidiary's context
- Develop a concise future-state vision and supporting assumptions
Explanation
Correct Answer
C:The best application step is: Adapt the existing ADM cycle to the subsidiary's context.
Incorrect Answers
A:Use architecture to connect the operating model and systems transition is relevant to the separate architecture topic Purpose of Enterprise Architecture (Concepts), but it does not BEST address the case. The more appropriate application step here is: Adapt the existing ADM cycle to the subsidiary's context.
B:That option concerns Phase E Transition Architectures. The ADM organizes architecture activity into linked phases that can be repeated or tailored.
D:Develop a concise future-state vision and supporting assumptions is relevant to the separate architecture topic Phase A Architecture Vision (Introduction to the ADM), but it does not BEST address the case. The more appropriate application step here is: Adapt the existing ADM cycle to the subsidiary's context.
Question 231
An architecture office is reviewing a proposed change: A retailer reuses an existing architecture for a new subsidiary. Which observation BEST confirms appropriate application? Choose ONE best answer.
- The audit can trace intended behavior to delivered components
- The roadmap and governance obligations reflect the change
- Capacity planning supports the intended demand pattern
- The new cycle references reusable outputs and adjusted scope
Explanation
Correct Answer
D:The best verification evidence is: The new cycle references reusable outputs and adjusted scope.
Incorrect Answers
A:That option concerns Content traceability among outputs. The ADM organizes architecture activity into linked phases that can be repeated or tailored.
B:The roadmap and governance obligations reflect the change is relevant to the separate architecture topic ADM Requirements Management (Introduction to the ADM), but it does not BEST address the case. The more appropriate verification evidence here is: The new cycle references reusable outputs and adjusted scope.
C:Capacity planning supports the intended demand pattern is relevant to the separate architecture topic Phase D platform dependencies (Introduction to the ADM), but it does not BEST address the case. The more appropriate verification evidence here is: The new cycle references reusable outputs and adjusted scope.
Question 232
An enterprise architecture team encounters this situation: A company has no architecture roles or agreed method. Which TOGAF-aligned concept or approach BEST addresses the need? Choose ONE answer.
- Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework
- Recognize an Architecture Board as a body that oversees architecture direction standards and compliance
- Represent technology trust boundaries and control requirements supporting the architecture
- Specify relevant platform technology standards and constraints in the target Technology Architecture
Explanation
Correct Answer
A:The best architectural approach is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
Incorrect Answers
B:Recognize an Architecture Board as a body that oversees architecture direction standards and compliance is relevant to the separate architecture topic Architecture Board responsibilities (Introduction to Architecture Governance), but it does not BEST address the case. The more appropriate architectural approach here is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
C:Represent technology trust boundaries and control requirements supporting the architecture is relevant to the separate architecture topic Phase D security infrastructure (Introduction to the ADM), but it does not BEST address the case. The more appropriate architectural approach here is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
D:Specify relevant platform technology standards and constraints in the target Technology Architecture is relevant to the separate architecture topic Phase D technology standards (Introduction to the ADM), but it does not BEST address the case. The more appropriate architectural approach here is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
Question 233
An enterprise architecture team encounters this situation: A company has no architecture roles or agreed method. Which action would BEST apply that concept to the situation? Choose ONE answer.
- Map service responsibilities and cross-application handoffs
- Describe required platform security and interoperability standards
- Partition work by business domain with shared enterprise rules
- Establish operating principles responsibility and a tailored method before individual ADM projects
Explanation
Correct Answer
D:The best application step is: Establish operating principles responsibility and a tailored method before individual ADM projects.
Incorrect Answers
A:Map service responsibilities and cross-application handoffs is relevant to the separate architecture topic Phase C Application Architecture (Introduction to the ADM), but it does not BEST address the case. The more appropriate application step here is: Establish operating principles responsibility and a tailored method before individual ADM projects.
B:Describe required platform security and interoperability standards is relevant to the separate architecture topic Phase D technology standards (Introduction to the ADM), but it does not BEST address the case. The more appropriate application step here is: Establish operating principles responsibility and a tailored method before individual ADM projects.
C:Partition work by business domain with shared enterprise rules is relevant to the separate architecture topic Architecture partitioning (Introduction to Applying the ADM), but it does not BEST address the case. The more appropriate application step here is: Establish operating principles responsibility and a tailored method before individual ADM projects. The distinguishing idea is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision. In this situation verify: Future architecture requests follow an understood process.
Question 234
An enterprise architecture team encounters this situation: A company has no architecture roles or agreed method. Which explanation BEST supports the architecture decision? Choose ONE answer.
- Architecture demand may originate from business change requirements and sponsors before Phase A planning
- A metamodel provides a structured vocabulary for architecture entities and links among them
- The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision
- Migration planning must account for prerequisites and organizational capability to deliver change
Explanation
Correct Answer
C:The best underlying explanation is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
Incorrect Answers
A:Architecture demand may originate from business change requirements and sponsors before Phase A planning is relevant to the separate architecture topic Request for Architecture Work (Introduction to the ADM), but it does not BEST address the case. The more appropriate underlying explanation here is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
B:A metamodel provides a structured vocabulary for architecture entities and links among them is relevant to the separate architecture topic Enterprise Metamodel (Architecture Content), but it does not BEST address the case. The more appropriate underlying explanation here is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision. The distinguishing idea is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision. In this situation verify: Future architecture requests follow an understood process.
D:Migration planning must account for prerequisites and organizational capability to deliver change is relevant to the separate architecture topic Phase F dependency analysis (Introduction to the ADM), but it does not BEST address the case. The more appropriate underlying explanation here is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
Question 235
An enterprise architecture team encounters this situation: A company has no architecture roles or agreed method. Which evidence BEST shows that the concern was addressed? Choose ONE answer.
- Future architecture requests follow an understood process
- The relevant phases incorporate the new obligation
- The board can prioritize architecture risks
- The target technology supports specified availability
Explanation
Correct Answer
A:The best verification evidence is: Future architecture requests follow an understood process.
Incorrect Answers
B:That option concerns ADM Requirements Management. The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
C:The board can prioritize architecture risks is relevant to the separate architecture topic Architecture governance reporting (Introduction to Architecture Governance), but it does not BEST address the case. The more appropriate verification evidence here is: Future architecture requests follow an understood process.
D:The target technology supports specified availability is relevant to the separate architecture topic Phase D platform services (Introduction to the ADM), but it does not BEST address the case. The more appropriate verification evidence here is: Future architecture requests follow an understood process.
Question 236
During an architecture planning workshop, this issue arises: A public agency wants common architecture standards across programs. What is the MOST appropriate architecture response? Select ONE best answer.
- Consider dependencies resource limits and business value when prioritizing migration projects
- Describe the Architecture Development Method as an iterative process for developing and governing architecture
- Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework
- Use matrices to represent relationships among architecture entities
Explanation
Correct Answer
C:The best architectural approach is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
Incorrect Answers
A:Consider dependencies resource limits and business value when prioritizing migration projects is relevant to the separate architecture topic Phase F dependency analysis (Introduction to the ADM), but it does not BEST address the case. The more appropriate architectural approach here is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
B:That option concerns ADM as an iterative method. The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
D:That option would use matrices to represent relationships among architecture entities, but it addresses a different concern. The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
Question 237
During an architecture planning workshop, this issue arises: A public agency wants common architecture standards across programs. Which concrete architecture step would be MOST suitable? Select ONE best answer.
- Review the architecture implications of the new requirement
- Define governance structures and a suitable framework in Preliminary work
- Identify common risk monitoring capabilities and business ownership
- Create clear governance routes and exception responsibilities
Explanation
Correct Answer
B:The best application step is: Define governance structures and a suitable framework in Preliminary work.
Incorrect Answers
A:Review the architecture implications of the new requirement is relevant to the separate architecture topic Phase H Architecture Change Management (Introduction to the ADM), but it does not BEST address the case. The more appropriate application step here is: Define governance structures and a suitable framework in Preliminary work.
C:That option concerns Phase B business capability modeling. The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
D:Create clear governance routes and exception responsibilities is relevant to the separate architecture topic Architecture Governance framework (Introduction to Architecture Governance), but it does not BEST address the case. The more appropriate application step here is: Define governance structures and a suitable framework in Preliminary work.
Question 238
During an architecture planning workshop, this issue arises: A public agency wants common architecture standards across programs. Which underlying TOGAF idea explains the response? Select ONE best answer.
- An Architecture Landscape can organize different scopes and levels of architecture descriptions
- Migration planning must account for prerequisites and organizational capability to deliver change
- The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision
- Architecture scope includes enterprise breadth depth time horizon and relevant architecture domains
Explanation
Correct Answer
C:The best underlying explanation is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
Incorrect Answers
A:An Architecture Landscape can organize different scopes and levels of architecture descriptions is relevant to the separate architecture topic Architecture levels and landscapes (Introduction to Applying the ADM), but it does not BEST address the case. The more appropriate underlying explanation here is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
B:Migration planning must account for prerequisites and organizational capability to deliver change is relevant to the separate architecture topic Phase F dependency analysis (Introduction to the ADM), but it does not BEST address the case. The more appropriate underlying explanation here is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
D:Architecture scope includes enterprise breadth depth time horizon and relevant architecture domains is relevant to the separate architecture topic Phase A architecture scope (Introduction to the ADM), but it does not BEST address the case. The more appropriate underlying explanation here is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
Question 239
During an architecture planning workshop, this issue arises: A public agency wants common architecture standards across programs. Which result would MOST clearly validate the approach? Select ONE best answer.
- Implementation changes can be checked against agreement
- Auditors can follow the privacy concern through the ADM
- The process model supports evaluation of proposed changes
- Programs use approved architecture process and roles
Explanation
Correct Answer
D:The best verification evidence is: Programs use approved architecture process and roles.
Incorrect Answers
A:Implementation changes can be checked against agreement is relevant to the separate architecture topic Architecture Contracts (Introduction to Architecture Governance), but it does not BEST address the case. The more appropriate verification evidence here is: Programs use approved architecture process and roles. The distinguishing idea is: The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision. In this situation verify: Programs use approved architecture process and roles.
B:That option concerns Requirements traceability across phases. The Preliminary Phase establishes how an organization will conduct architecture rather than defining one project vision.
C:The process model supports evaluation of proposed changes is relevant to the separate architecture topic Phase B business processes (Introduction to the ADM), but it does not BEST address the case. The more appropriate verification evidence here is: Programs use approved architecture process and roles.
Question 240
An architecture office is reviewing a proposed change: A holding company integrates architecture offices after acquisition. What should the architecture practitioner prioritize? Choose ONE best answer.
- Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework
- Use application and data architecture to address interoperability requirements between systems
- Produce and maintain an Implementation and Migration Plan tied to the Architecture Roadmap
- Apply iterative ADM activity when new findings require refinement of previous architecture work
Explanation
Correct Answer
A:The best architectural approach is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
Incorrect Answers
B:Use application and data architecture to address interoperability requirements between systems is relevant to the separate architecture topic Phase C interoperability (Introduction to the ADM), but it does not BEST address the case. The more appropriate architectural approach here is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
C:Produce and maintain an Implementation and Migration Plan tied to the Architecture Roadmap is relevant to the separate architecture topic Phase F implementation roadmap (Introduction to the ADM), but it does not BEST address the case. The more appropriate architectural approach here is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.
D:Apply iterative ADM activity when new findings require refinement of previous architecture work is relevant to the separate architecture topic Iterating through ADM phases (Introduction to Applying the ADM), but it does not BEST address the case. The more appropriate architectural approach here is: Use the Preliminary Phase to prepare the organizational architecture capability and tailor the architecture framework.