PRINCE2 PRINCE2 7 Practitioner Practice Test 85
Question 840
An operator suggests skipping safeguards after this event: a museum digitization stage assigns deliverables but no completion reporting or risk constraints to team managers. Which action should be ruled out? Select ONE answer.
- Execute the agreed work package and its quality activities under team management control
- Present the exception and alternatives for an authorized project board decision
- Prepare a detailed next management stage plan grounded in actual results and current forecasts
- Treat an informal message as full authorization for undefined supplier work
Explanation
Correct Answer
D:The unsafe shortcut is to treat an informal message as full authorization for undefined supplier work. Controlling a stage relies on explicit delegation of deliverable responsibilities. The defensible response is instead to authorize a work package with products, acceptance, reporting and agreed constraints, using the diagnostic step to compare requested work with the approved stage plan and product descriptions before changing settings. Afterward, the team should confirm this result: The team manager accepts a clear scope and reports against defined products and tolerances. It must maintain the safeguard to review work package interfaces when dependencies or product criteria change. By contrast, the response tied to this evidence is: Treat an informal message as full authorization for undefined supplier work.
Incorrect Answers
A:Execute the agreed work package and its quality activities under team management control. The team produces quality-verified deliverables that can be formally handed over. The team manager accepts a clear scope and reports against defined products and tolerances. The shortcut most directly implicated here is: Treat an informal message as full authorization for undefined supplier work.
B:Present the exception and alternatives for an authorized project board decision. A documented board decision approves revised tolerances, changes direction or stops the work. The team manager accepts a clear scope and reports against defined products and tolerances. The shortcut most directly implicated here is: Treat an informal message as full authorization for undefined supplier work.
C:Prepare a detailed next management stage plan grounded in actual results and current forecasts. Stage boundaries create informed authorization points instead of unconditional funding. The team manager accepts a clear scope and reports against defined products and tolerances. The shortcut most directly implicated here is: Treat an informal message as full authorization for undefined supplier work.
Question 841
A PRINCE2 project manager receives this situation: a public safety project stage has no reliable checkpoint evidence from vendors until the final week. Which targeted corrective action should be chosen? Select ONE answer.
- Collect team checkpoint information and update stage forecasts against approved tolerances
- Produce an exception report and escalate the forecast to the project board promptly
- Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
Explanation
Correct Answer
A:First, compare team reports, accepted products and remaining dependencies with the stage plan. Collect team checkpoint information and update stage forecasts against approved tolerances. Timely stage control connects team output evidence to management decisions. Success means the project manager knows stage health early enough to take in-tolerance corrective action. Repeating review progress and forecasts at planned control intervals helps prevent recurrence.
Incorrect Answers
B:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The project manager knows stage health early enough to take in-tolerance corrective action.
C:Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. The board can authorize staged delivery against a defensible project baseline. The project manager knows stage health early enough to take in-tolerance corrective action.
D:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The project manager knows stage health early enough to take in-tolerance corrective action.
Question 842
A support engineer investigates this project governance report: a public safety project stage has no reliable checkpoint evidence from vendors until the final week. Which comparison should be made first? Select ONE answer.
- Compare the PID, business case, project plan and proposed tolerances with the project brief
- Compare team reports, accepted products and remaining dependencies with the stage plan
- Compare planned and actual project outcomes to identify causes and reusable practices
- Inspect outstanding criteria, quality evidence and authorized acceptance decisions
Explanation
Correct Answer
B:The strongest first investigation is to compare team reports, accepted products and remaining dependencies with the stage plan. Timely stage control connects team output evidence to management decisions. If that evidence confirms the issue, the team should collect team checkpoint information and update stage forecasts against approved tolerances. A subsequent acceptance check should confirm this result: The project manager knows stage health early enough to take in-tolerance corrective action. This check produces evidence before any broad configuration change, avoiding the risky proposal to wait for a missed deadline before asking whether a work package is late.
Incorrect Answers
A:Compare the PID, business case, project plan and proposed tolerances with the project brief. The project board authorizes the project and first management stage on coherent evidence. The project manager knows stage health early enough to take in-tolerance corrective action. The relevant investigation is: Compare team reports, accepted products and remaining dependencies with the stage plan.
C:Compare planned and actual project outcomes to identify causes and reusable practices. A final lessons report has actionable recommendations and accountable dissemination. The project manager knows stage health early enough to take in-tolerance corrective action. The relevant investigation is: Compare team reports, accepted products and remaining dependencies with the stage plan.
D:Inspect outstanding criteria, quality evidence and authorized acceptance decisions. Evidence of the products delivered, not simply a completed activity list. The project manager knows stage health early enough to take in-tolerance corrective action. The relevant investigation is: Compare team reports, accepted products and remaining dependencies with the stage plan.
Question 843
An auditor asks how to validate resolution of this situation: a public safety project stage has no reliable checkpoint evidence from vendors until the final week. Which direct evidence is strongest? Select ONE answer.
- Recovery actions improve the forecast without changing unauthorized baselines
- The board can assess desirability, viability and achievability before authorizing the project
- The project manager knows stage health early enough to take in-tolerance corrective action
- The initiation decision is supported by a credible mandate and defined responsibilities
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to review progress and forecasts at planned control intervals. The decisive acceptance evidence is this result: The project manager knows stage health early enough to take in-tolerance corrective action. Timely stage control connects team output evidence to management decisions. The operating team should diagnose it by checking whether it can compare team reports, accepted products and remaining dependencies with the stage plan, then collect team checkpoint information and update stage forecasts against approved tolerances where justified.
Incorrect Answers
A:Recovery actions improve the forecast without changing unauthorized baselines. The project manager knows stage health early enough to take in-tolerance corrective action.
B:The board can assess desirability, viability and achievability before authorizing the project. The project manager knows stage health early enough to take in-tolerance corrective action.
D:The initiation decision is supported by a credible mandate and defined responsibilities. The project manager knows stage health early enough to take in-tolerance corrective action.
Question 844
The project executive wants lasting assurance after this event: a public safety project stage has no reliable checkpoint evidence from vendors until the final week. Which preventive practice should be adopted? Select ONE answer.
- Conduct planned post-project reviews outside the closed delivery project
- Review justification at future stage boundaries and material external changes
- Reconsider delivery assumptions if early supplier or technical evidence changes
- Review progress and forecasts at planned control intervals
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to collect team checkpoint information and update stage forecasts against approved tolerances and diagnostic evidence to compare team reports, accepted products and remaining dependencies with the stage plan. Periodic testing should confirm this result: The project manager knows stage health early enough to take in-tolerance corrective action. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to review progress and forecasts at planned control intervals. Timely stage control connects team output evidence to management decisions.
Incorrect Answers
A:Conduct planned post-project reviews outside the closed delivery project. Some benefits mature after project closure and must have real ownership. The project manager knows stage health early enough to take in-tolerance corrective action. To avoid recurrence, review progress and forecasts at planned control intervals.
B:Review justification at future stage boundaries and material external changes. The board decides whether continued investment remains appropriate with transparent tradeoffs. The project manager knows stage health early enough to take in-tolerance corrective action. To avoid recurrence, review progress and forecasts at planned control intervals.
C:Reconsider delivery assumptions if early supplier or technical evidence changes. An early approach decision should be informed rather than prematurely irreversible. The project manager knows stage health early enough to take in-tolerance corrective action. To avoid recurrence, review progress and forecasts at planned control intervals.
Question 845
An operator suggests skipping safeguards after this event: a public safety project stage has no reliable checkpoint evidence from vendors until the final week. Which action should be ruled out? Select ONE answer.
- Wait for a missed deadline before asking whether a work package is late
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Provide timely checkpoint progress, issues and forecast updates to the project manager
- Produce an exception report and escalate the forecast to the project board promptly
Explanation
Correct Answer
A:The unsafe shortcut is to wait for a missed deadline before asking whether a work package is late. Timely stage control connects team output evidence to management decisions. The defensible response is instead to collect team checkpoint information and update stage forecasts against approved tolerances, using the diagnostic step to compare team reports, accepted products and remaining dependencies with the stage plan before changing settings. Afterward, the team should confirm this result: The project manager knows stage health early enough to take in-tolerance corrective action. It must maintain the safeguard to review progress and forecasts at planned control intervals.
Incorrect Answers
B:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The project manager knows stage health early enough to take in-tolerance corrective action. The shortcut most directly implicated here is: Wait for a missed deadline before asking whether a work package is late.
C:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. The project manager knows stage health early enough to take in-tolerance corrective action. The shortcut most directly implicated here is: Wait for a missed deadline before asking whether a work package is late.
D:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The project manager knows stage health early enough to take in-tolerance corrective action. The shortcut most directly implicated here is: Wait for a missed deadline before asking whether a work package is late.
Question 846
A project board needs to manage this condition: a regional university website rollout reports hours spent but cannot identify completed accepted products. Which administrative action best resolves the specific control gap? Select ONE answer.
- Record and assess actual issues and authorize responses within delegated authority or escalate
- Collect team checkpoint information and update stage forecasts against approved tolerances
- Produce an exception report and escalate the forecast to the project board promptly
- Produce a proportionate project brief and outline business case to support initiation authorization
Explanation
Correct Answer
B:First, compare team reports, accepted products and remaining dependencies with the stage plan. Collect team checkpoint information and update stage forecasts against approved tolerances. Timely stage control connects team output evidence to management decisions. Success means the project manager knows stage health early enough to take in-tolerance corrective action. Repeating review progress and forecasts at planned control intervals helps prevent recurrence. By contrast, the response tied to this evidence is: Collect team checkpoint information and update stage forecasts against approved tolerances.
Incorrect Answers
A:Record and assess actual issues and authorize responses within delegated authority or escalate. Approved issue actions and escalations remain traceable to the current stage baseline. The project manager knows stage health early enough to take in-tolerance corrective action.
C:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The project manager knows stage health early enough to take in-tolerance corrective action. By contrast, the response tied to this evidence is: Collect team checkpoint information and update stage forecasts against approved tolerances.
D:Produce a proportionate project brief and outline business case to support initiation authorization. The board can approve or reject initiation on a coherent brief with clear assumptions. The project manager knows stage health early enough to take in-tolerance corrective action.
Question 847
An operations team is unsure why this occurred: a regional university website rollout reports hours spent but cannot identify completed accepted products. Which targeted diagnostic step would produce the most relevant evidence? Select ONE answer.
- Compare required controls with project risks, stakeholders, contracts and operating context
- Compare preliminary user objectives, constraints, risks and known delivery options
- Compare team reports, accepted products and remaining dependencies with the stage plan
- Check evidence for the proposed costs and benefit owners against available options
Explanation
Correct Answer
C:The strongest first investigation is to compare team reports, accepted products and remaining dependencies with the stage plan. Timely stage control connects team output evidence to management decisions. If that evidence confirms the issue, the team should collect team checkpoint information and update stage forecasts against approved tolerances. A subsequent acceptance check should confirm this result: The project manager knows stage health early enough to take in-tolerance corrective action. This check produces evidence before any broad configuration change, avoiding the risky proposal to wait for a missed deadline before asking whether a work package is late. By contrast, the response tied to this evidence is: Compare team reports, accepted products and remaining dependencies with the stage plan.
Incorrect Answers
A:Compare required controls with project risks, stakeholders, contracts and operating context. Coordinated project controls must be established before distributed delivery begins. The project manager knows stage health early enough to take in-tolerance corrective action. The relevant investigation is: Compare team reports, accepted products and remaining dependencies with the stage plan.
B:Compare preliminary user objectives, constraints, risks and known delivery options. The board can approve or reject initiation on a coherent brief with clear assumptions. The project manager knows stage health early enough to take in-tolerance corrective action. The relevant investigation is: Compare team reports, accepted products and remaining dependencies with the stage plan.
D:Check evidence for the proposed costs and benefit owners against available options. The board can assess desirability, viability and achievability before authorizing the project. The project manager knows stage health early enough to take in-tolerance corrective action. The relevant investigation is: Compare team reports, accepted products and remaining dependencies with the stage plan.
Question 848
The senior user wants proof that this problem is resolved: a regional university website rollout reports hours spent but cannot identify completed accepted products. Which end-to-end verification is most useful? Select ONE answer.
- The board receives a coherent PID that establishes how the project will be managed and controlled
- The board formally authorizes closure with operational ownership and residual obligations identified
- The receiving authority acknowledges accepted products and remaining obligations
- The project manager knows stage health early enough to take in-tolerance corrective action
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to review progress and forecasts at planned control intervals. The decisive acceptance evidence is this result: The project manager knows stage health early enough to take in-tolerance corrective action. Timely stage control connects team output evidence to management decisions. The operating team should diagnose it by checking whether it can compare team reports, accepted products and remaining dependencies with the stage plan, then collect team checkpoint information and update stage forecasts against approved tolerances where justified. By contrast, the response tied to this evidence is: The project manager knows stage health early enough to take in-tolerance corrective action.
Incorrect Answers
A:The board receives a coherent PID that establishes how the project will be managed and controlled. The project manager knows stage health early enough to take in-tolerance corrective action.
B:The board formally authorizes closure with operational ownership and residual obligations identified. Project closure is a governance decision informed by benefits and operational readiness. The project manager knows stage health early enough to take in-tolerance corrective action.
C:The receiving authority acknowledges accepted products and remaining obligations. The project manager knows stage health early enough to take in-tolerance corrective action.
Question 849
An incident has been closed after the team addressed this condition: a regional university website rollout reports hours spent but cannot identify completed accepted products. Which follow-up control is most effective? Select ONE answer.
- Review progress and forecasts at planned control intervals
- Carry startup lessons into initiation and review them at later stages
- Use a consistent handover checklist for future work packages
- Assign and verify actions arising from the end-stage lessons report
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to collect team checkpoint information and update stage forecasts against approved tolerances and diagnostic evidence to compare team reports, accepted products and remaining dependencies with the stage plan. Periodic testing should confirm this result: The project manager knows stage health early enough to take in-tolerance corrective action. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to review progress and forecasts at planned control intervals. Timely stage control connects team output evidence to management decisions. By contrast, the response tied to this evidence is: Review progress and forecasts at planned control intervals.
Incorrect Answers
B:Carry startup lessons into initiation and review them at later stages. The start-up documentation demonstrates applied learning and workable responsibilities. The project manager knows stage health early enough to take in-tolerance corrective action. To avoid recurrence, review progress and forecasts at planned control intervals.
C:Use a consistent handover checklist for future work packages. The receiving authority acknowledges accepted products and remaining obligations. The project manager knows stage health early enough to take in-tolerance corrective action. To avoid recurrence, review progress and forecasts at planned control intervals.
D:Assign and verify actions arising from the end-stage lessons report. The board can see what worked, what failed and how the next stage will improve. The project manager knows stage health early enough to take in-tolerance corrective action. To avoid recurrence, review progress and forecasts at planned control intervals.
Question 850
For this project-management problem, the team is comparing possible shortcuts: a regional university website rollout reports hours spent but cannot identify completed accepted products. Which proposed workaround should be REJECTED as unsafe? Select ONE answer.
- Handover operational responsibilities and future benefit reviews to named accountable owners
- Wait for a missed deadline before asking whether a work package is late
- Produce an exception report and escalate the forecast to the project board promptly
- Establish the project initiation documentation with management approaches, plans and tolerances
Explanation
Correct Answer
B:The unsafe shortcut is to wait for a missed deadline before asking whether a work package is late. Timely stage control connects team output evidence to management decisions. The defensible response is instead to collect team checkpoint information and update stage forecasts against approved tolerances, using the diagnostic step to compare team reports, accepted products and remaining dependencies with the stage plan before changing settings. Afterward, the team should confirm this result: The project manager knows stage health early enough to take in-tolerance corrective action. It must maintain the safeguard to review progress and forecasts at planned control intervals. By contrast, the response tied to this evidence is: Wait for a missed deadline before asking whether a work package is late.
Incorrect Answers
A:Handover operational responsibilities and future benefit reviews to named accountable owners. Some benefits mature after project closure and must have real ownership. The project manager knows stage health early enough to take in-tolerance corrective action. The shortcut most directly implicated here is: Wait for a missed deadline before asking whether a work package is late.
C:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The project manager knows stage health early enough to take in-tolerance corrective action. The shortcut most directly implicated here is: Wait for a missed deadline before asking whether a work package is late. The defensible response is instead to collect team checkpoint information and update stage forecasts against approved tolerances, using the diagnostic step to compare team reports, accepted products and remaining dependencies with the stage plan before changing settings.
D:Establish the project initiation documentation with management approaches, plans and tolerances. The board receives a coherent PID that establishes how the project will be managed and controlled. The project manager knows stage health early enough to take in-tolerance corrective action. The shortcut most directly implicated here is: Wait for a missed deadline before asking whether a work package is late.