PRINCE2 PRINCE2 7 Practitioner Practice Test 72
Question 710
A project manager is under pressure to address the following issue quickly: a city records replacement receives conflicting demands and the team wants to launch initiation without a named sponsor. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Have the project board assess the project brief and authorize a bounded initiation stage
- Spend the complete delivery budget based solely on an informal project idea
- Record and assess actual issues and authorize responses within delegated authority or escalate
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
Explanation
Correct Answer
B:The unsafe shortcut is to spend the complete delivery budget based solely on an informal project idea. Starting up establishes whether the idea is worth the effort of full initiation. The defensible response is instead to confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation, using the diagnostic step to inspect the mandate, sponsor authority and initial expected products and constraints before changing settings. Afterward, the team should confirm this result: The initiation decision is supported by a credible mandate and defined responsibilities. It must maintain the safeguard to validate the mandate and named owners when organizational priorities change. By contrast, the response tied to this evidence is: Spend the complete delivery budget based solely on an informal project idea.
Incorrect Answers
A:Have the project board assess the project brief and authorize a bounded initiation stage. Initiation expenditure is explicitly authorized without pre-approving the entire project. The initiation decision is supported by a credible mandate and defined responsibilities. The shortcut most directly implicated here is: Spend the complete delivery budget based solely on an informal project idea.
C:Record and assess actual issues and authorize responses within delegated authority or escalate. Approved issue actions and escalations remain traceable to the current stage baseline. The initiation decision is supported by a credible mandate and defined responsibilities. The shortcut most directly implicated here is: Spend the complete delivery budget based solely on an informal project idea. It must maintain the safeguard to validate the mandate and named owners when organizational priorities change.
D:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The initiation decision is supported by a credible mandate and defined responsibilities. The shortcut most directly implicated here is: Spend the complete delivery budget based solely on an informal project idea.
Question 711
During a PRINCE2 management-stage review, the team encounters this situation: a regional hospital system has a broad project mandate but cannot describe the first achievable deliverables. What is the most appropriate controlled response? Select ONE answer.
- Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation
- Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions
- Produce a proportionate project brief and outline business case to support initiation authorization
- Define proportionate agreed approaches for risk, issues, quality, communications, change and project information
Explanation
Correct Answer
C:First, compare preliminary user objectives, constraints, risks and known delivery options. Produce a proportionate project brief and outline business case to support initiation authorization. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. Success means the board can approve or reject initiation on a coherent brief with clear assumptions. Repeating refine scope and justification as discovery improves the evidence base helps prevent recurrence.
Incorrect Answers
A:Confirm the project mandate, appoint appropriate leadership and capture outline justification before committing initiation. The initiation decision is supported by a credible mandate and defined responsibilities. The board can approve or reject initiation on a coherent brief with clear assumptions.
B:Create a realistic project plan and initial management stage plan from agreed products, resources and risk assumptions. The board can authorize staged delivery against a defensible project baseline. The board can approve or reject initiation on a coherent brief with clear assumptions.
D:Define proportionate agreed approaches for risk, issues, quality, communications, change and project information. Coordinated project controls must be established before distributed delivery begins. The board can approve or reject initiation on a coherent brief with clear assumptions.
Question 712
The project management team is troubleshooting this situation: a regional hospital system has a broad project mandate but cannot describe the first achievable deliverables. Which check isolates the likely operating dependency? Select ONE answer.
- Compare decision rights and role coverage with business, user and supplier interests
- Review outline justification, initial risk and readiness of named roles
- Compare the PID, business case, project plan and proposed tolerances with the project brief
- Compare preliminary user objectives, constraints, risks and known delivery options
Explanation
Correct Answer
D:The strongest first investigation is to compare preliminary user objectives, constraints, risks and known delivery options. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. If that evidence confirms the issue, the team should produce a proportionate project brief and outline business case to support initiation authorization. A subsequent acceptance check should confirm this result: The board can approve or reject initiation on a coherent brief with clear assumptions. This check produces evidence before any broad configuration change, avoiding the risky proposal to skip the project brief and treat a single vendor quotation as the project mandate.
Incorrect Answers
A:Compare decision rights and role coverage with business, user and supplier interests. A working board and delivery organization are documented with accountable decisions and checks. The board can approve or reject initiation on a coherent brief with clear assumptions. The relevant investigation is: Compare preliminary user objectives, constraints, risks and known delivery options.
B:Review outline justification, initial risk and readiness of named roles. Initiation expenditure is explicitly authorized without pre-approving the entire project. The board can approve or reject initiation on a coherent brief with clear assumptions. The relevant investigation is: Compare preliminary user objectives, constraints, risks and known delivery options.
C:Compare the PID, business case, project plan and proposed tolerances with the project brief. The project board authorizes the project and first management stage on coherent evidence. The board can approve or reject initiation on a coherent brief with clear assumptions. The relevant investigation is: Compare preliminary user objectives, constraints, risks and known delivery options.
Question 713
An administrator claims the following problem is resolved: a regional hospital system has a broad project mandate but cannot describe the first achievable deliverables. Which measured outcome confirms that claim? Select ONE answer.
- The board can approve or reject initiation on a coherent brief with clear assumptions
- Initiation expenditure is explicitly authorized without pre-approving the entire project
- Board-level direction is requested before continuing work beyond delegated limits
- Approved issue actions and escalations remain traceable to the current stage baseline
Explanation
Correct Answer
A:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to refine scope and justification as discovery improves the evidence base. The decisive acceptance evidence is this result: The board can approve or reject initiation on a coherent brief with clear assumptions. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The operating team should diagnose it by checking whether it can compare preliminary user objectives, constraints, risks and known delivery options, then produce a proportionate project brief and outline business case to support initiation authorization where justified.
Incorrect Answers
B:Initiation expenditure is explicitly authorized without pre-approving the entire project. The board can approve or reject initiation on a coherent brief with clear assumptions.
C:Board-level direction is requested before continuing work beyond delegated limits. Exception management is based on forecast tolerance breaches and decision rights. The board can approve or reject initiation on a coherent brief with clear assumptions.
D:Approved issue actions and escalations remain traceable to the current stage baseline. The board can approve or reject initiation on a coherent brief with clear assumptions.
Question 714
After resolving the following issue, the operations team wants to prevent a recurrence: a regional hospital system has a broad project mandate but cannot describe the first achievable deliverables. Which ongoing control is best? Select ONE answer.
- Review issue status and cumulative change effects at each stage control point
- Refine scope and justification as discovery improves the evidence base
- Retain acceptance artifacts and residual obligations in the closure record
- Maintain regular evidence-based checkpoint reporting for all active packages
Explanation
Correct Answer
B:It complements, rather than replaces, the immediate administrative action to produce a proportionate project brief and outline business case to support initiation authorization and diagnostic evidence to compare preliminary user objectives, constraints, risks and known delivery options. Periodic testing should confirm this result: The board can approve or reject initiation on a coherent brief with clear assumptions. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to refine scope and justification as discovery improves the evidence base. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization.
Incorrect Answers
A:Review issue status and cumulative change effects at each stage control point. Approved issue actions and escalations remain traceable to the current stage baseline. The board can approve or reject initiation on a coherent brief with clear assumptions. To avoid recurrence, refine scope and justification as discovery improves the evidence base.
C:Retain acceptance artifacts and residual obligations in the closure record. Evidence of the products delivered, not simply a completed activity list. The board can approve or reject initiation on a coherent brief with clear assumptions. To avoid recurrence, refine scope and justification as discovery improves the evidence base.
D:Maintain regular evidence-based checkpoint reporting for all active packages. Stage forecasts reflect actual work package progress and risks before failure. The board can approve or reject initiation on a coherent brief with clear assumptions. To avoid recurrence, refine scope and justification as discovery improves the evidence base.
Question 715
A project manager is under pressure to address the following issue quickly: a regional hospital system has a broad project mandate but cannot describe the first achievable deliverables. Which proposal creates the clearest avoidable risk? Select ONE answer.
- Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions
- Provide timely checkpoint progress, issues and forecast updates to the project manager
- Skip the project brief and treat a single vendor quotation as the project mandate
- Submit the completed initiation documentation and initial stage plan for formal board authorization
Explanation
Correct Answer
C:The unsafe shortcut is to skip the project brief and treat a single vendor quotation as the project mandate. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The defensible response is instead to produce a proportionate project brief and outline business case to support initiation authorization, using the diagnostic step to compare preliminary user objectives, constraints, risks and known delivery options before changing settings. Afterward, the team should confirm this result: The board can approve or reject initiation on a coherent brief with clear assumptions. It must maintain the safeguard to refine scope and justification as discovery improves the evidence base.
Incorrect Answers
A:Develop a detailed business case supported by costs, benefits, risks and realistic delivery assumptions. The board can assess desirability, viability and achievability before authorizing the project. The board can approve or reject initiation on a coherent brief with clear assumptions. The shortcut most directly implicated here is: Skip the project brief and treat a single vendor quotation as the project mandate.
B:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. The board can approve or reject initiation on a coherent brief with clear assumptions. The shortcut most directly implicated here is: Skip the project brief and treat a single vendor quotation as the project mandate.
D:Submit the completed initiation documentation and initial stage plan for formal board authorization. The project board authorizes the project and first management stage on coherent evidence. The board can approve or reject initiation on a coherent brief with clear assumptions. The shortcut most directly implicated here is: Skip the project brief and treat a single vendor quotation as the project mandate.
Question 716
A project delivery team reports that a research data project has no agreed initial scope or constraints yet requests authorization for full development. Which action directly addresses the issue? Select ONE answer.
- Negotiate and accept the work package with realistic scope, interfaces and quality criteria
- Provide timely checkpoint progress, issues and forecast updates to the project manager
- Prepare a detailed next management stage plan grounded in actual results and current forecasts
- Produce a proportionate project brief and outline business case to support initiation authorization
Explanation
Correct Answer
D:First, compare preliminary user objectives, constraints, risks and known delivery options. Produce a proportionate project brief and outline business case to support initiation authorization. The reported operational condition is that a research data project has no agreed initial scope or constraints yet requests authorization for full development. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. Success means the board can approve or reject initiation on a coherent brief with clear assumptions. Repeating refine scope and justification as discovery improves the evidence base helps prevent recurrence.
Incorrect Answers
A:Negotiate and accept the work package with realistic scope, interfaces and quality criteria. Team and project manager share an agreed deliverable commitment before work starts. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization.
B:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization.
C:Prepare a detailed next management stage plan grounded in actual results and current forecasts. Stage boundaries create informed authorization points instead of unconditional funding. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization.
Question 717
An administrator wants to identify the failure before making a change: a research data project has no agreed initial scope or constraints yet requests authorization for full development. Which inspection is the most informative? Select ONE answer.
- Compare preliminary user objectives, constraints, risks and known delivery options
- Inspect the mandate, sponsor authority and initial expected products and constraints
- Compare the PID, business case, project plan and proposed tolerances with the project brief
- Compare delivery alternatives against expected products, capabilities, constraints and risks
Explanation
Correct Answer
A:The strongest first investigation is to compare preliminary user objectives, constraints, risks and known delivery options. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. If that evidence confirms the issue, the team should produce a proportionate project brief and outline business case to support initiation authorization. A subsequent acceptance check should confirm this result: The board can approve or reject initiation on a coherent brief with clear assumptions. This check produces evidence before any broad configuration change, avoiding the risky proposal to skip the project brief and treat a single vendor quotation as the project mandate. By contrast, the response tied to this evidence is: Compare preliminary user objectives, constraints, risks and known delivery options.
Incorrect Answers
B:Inspect the mandate, sponsor authority and initial expected products and constraints. The initiation decision is supported by a credible mandate and defined responsibilities. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The relevant investigation is: Compare preliminary user objectives, constraints, risks and known delivery options.
C:Compare the PID, business case, project plan and proposed tolerances with the project brief. The project board authorizes the project and first management stage on coherent evidence. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The relevant investigation is: Compare preliminary user objectives, constraints, risks and known delivery options.
D:Compare delivery alternatives against expected products, capabilities, constraints and risks. An early approach decision should be informed rather than prematurely irreversible. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The relevant investigation is: Compare preliminary user objectives, constraints, risks and known delivery options.
Question 718
After a controlled change, the team needs to resolve this report: a research data project has no agreed initial scope or constraints yet requests authorization for full development. Which observable result would best establish success? Select ONE answer.
- A final lessons report has actionable recommendations and accountable dissemination
- The board can approve or reject initiation on a coherent brief with clear assumptions
- The start-up documentation demonstrates applied learning and workable responsibilities
- The board approves closure with clear transfer of every outstanding responsibility
Explanation
Correct Answer
B:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to refine scope and justification as discovery improves the evidence base. The decisive acceptance evidence is this result: The board can approve or reject initiation on a coherent brief with clear assumptions. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The operating team should diagnose it by checking whether it can compare preliminary user objectives, constraints, risks and known delivery options, then produce a proportionate project brief and outline business case to support initiation authorization where justified. By contrast, the response tied to this evidence is: The board can approve or reject initiation on a coherent brief with clear assumptions.
Incorrect Answers
A:A final lessons report has actionable recommendations and accountable dissemination. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. Success in this case requires: The board can approve or reject initiation on a coherent brief with clear assumptions.
C:The start-up documentation demonstrates applied learning and workable responsibilities. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. Success in this case requires: The board can approve or reject initiation on a coherent brief with clear assumptions.
D:The board approves closure with clear transfer of every outstanding responsibility. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. Success in this case requires: The board can approve or reject initiation on a coherent brief with clear assumptions.
Question 719
A project assurance reviewer sees a pattern in this report: a research data project has no agreed initial scope or constraints yet requests authorization for full development. Which recurring safeguard should remain in force? Select ONE answer.
- Replan successive stages using lessons and updated risk forecasts
- Maintain regular evidence-based checkpoint reporting for all active packages
- Refine scope and justification as discovery improves the evidence base
- Validate the mandate and named owners when organizational priorities change
Explanation
Correct Answer
C:It complements, rather than replaces, the immediate administrative action to produce a proportionate project brief and outline business case to support initiation authorization and diagnostic evidence to compare preliminary user objectives, constraints, risks and known delivery options. Periodic testing should confirm this result: The board can approve or reject initiation on a coherent brief with clear assumptions. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to refine scope and justification as discovery improves the evidence base. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. By contrast, the response tied to this evidence is: Refine scope and justification as discovery improves the evidence base.
Incorrect Answers
A:Replan successive stages using lessons and updated risk forecasts. Stage boundaries create informed authorization points instead of unconditional funding. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. To avoid recurrence, refine scope and justification as discovery improves the evidence base.
B:Maintain regular evidence-based checkpoint reporting for all active packages. Stage forecasts reflect actual work package progress and risks before failure. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. To avoid recurrence, refine scope and justification as discovery improves the evidence base.
D:Validate the mandate and named owners when organizational priorities change. The initiation decision is supported by a credible mandate and defined responsibilities. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. To avoid recurrence, refine scope and justification as discovery improves the evidence base.
Question 720
A team wants to simplify its response to this situation: a research data project has no agreed initial scope or constraints yet requests authorization for full development. Which shortcut is the LEAST defensible? Select ONE answer.
- Provide timely checkpoint progress, issues and forecast updates to the project manager
- Produce an exception report and escalate the forecast to the project board promptly
- Confirm formal user acceptance against the project product description before recommending closure
- Skip the project brief and treat a single vendor quotation as the project mandate
Explanation
Correct Answer
D:The unsafe shortcut is to skip the project brief and treat a single vendor quotation as the project mandate. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The defensible response is instead to produce a proportionate project brief and outline business case to support initiation authorization, using the diagnostic step to compare preliminary user objectives, constraints, risks and known delivery options before changing settings. Afterward, the team should confirm this result: The board can approve or reject initiation on a coherent brief with clear assumptions. It must maintain the safeguard to refine scope and justification as discovery improves the evidence base. By contrast, the response tied to this evidence is: Skip the project brief and treat a single vendor quotation as the project mandate.
Incorrect Answers
A:Provide timely checkpoint progress, issues and forecast updates to the project manager. Stage forecasts reflect actual work package progress and risks before failure. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The shortcut most directly implicated here is: Skip the project brief and treat a single vendor quotation as the project mandate.
B:Produce an exception report and escalate the forecast to the project board promptly. Exception management is based on forecast tolerance breaches and decision rights. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The shortcut most directly implicated here is: Skip the project brief and treat a single vendor quotation as the project mandate.
C:Confirm formal user acceptance against the project product description before recommending closure. Evidence of the products delivered, not simply a completed activity list. The start-up process creates sufficient direction for informed initiation, not detailed delivery authorization. The shortcut most directly implicated here is: Skip the project brief and treat a single vendor quotation as the project mandate.