PRINCE2 PRINCE2 7 Practitioner Practice Test 59
Question 580
The service owner is reviewing actions after this report: a ferry operator proposes a new interface after procurement with no assessment of delivery dependencies. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Assess upside opportunities alongside threats and plan proportionate exploitation or enhancement
- Verify that risk responses are actionable, proportionate and integrated with plans
- Collect required acceptance and operational readiness evidence before product handover
- Approve the requested change based solely on its attractive user-interface description
Explanation
Correct Answer
D:The unsafe shortcut is to approve the requested change based solely on its attractive user-interface description. Change control protects overall project viability rather than only the altered feature. The defensible response is instead to assess issue impacts on scope, business case, benefits, risks, quality, schedule and resources before approval, using the diagnostic step to compare the issue proposal with authorized baselines and affected product descriptions before changing settings. Afterward, the team should confirm this result: Approvers receive traceable options and a credible impact statement. It must maintain the safeguard to require impact evidence and user/supplier input for significant issues. By contrast, the response tied to this evidence is: Approve the requested change based solely on its attractive user-interface description.
Incorrect Answers
A:Assess upside opportunities alongside threats and plan proportionate exploitation or enhancement. The selected opportunity produces measurable value without violating risk tolerance. Approvers receive traceable options and a credible impact statement. The shortcut most directly implicated here is: Approve the requested change based solely on its attractive user-interface description.
B:Verify that risk responses are actionable, proportionate and integrated with plans. Tested response arrangements address the defined risk event in realistic conditions. Approvers receive traceable options and a credible impact statement. The shortcut most directly implicated here is: Approve the requested change based solely on its attractive user-interface description.
C:Collect required acceptance and operational readiness evidence before product handover. Receiving owners confirm the product is acceptable and usable in live operations. Approvers receive traceable options and a credible impact statement. The shortcut most directly implicated here is: Approve the requested change based solely on its attractive user-interface description.
Question 581
A project sponsor describes this requirement: a health portal project manager approves an issue that would exceed stage cost tolerance. Which step best meets it without creating unnecessary access? Select ONE answer.
- Route issue decisions to the person or board holding the relevant delegated authority
- Give senior supplier accountability for supplying necessary skills, technical integrity and resources
- Set reporting frequency and content proportionate to information needs and risk
- Translate relevant lessons into owned improvements and monitor completion as part of stage controls
Explanation
Correct Answer
A:First, check impact forecasts against change budget, tolerances and authorized decision rights. Route issue decisions to the person or board holding the relevant delegated authority. Authority depends on impact and delegation, not the loudest requester. Success requires: Issue decisions are formally recorded at the right governance level. Repeating maintain a current delegation matrix for changes and exceptions helps prevent recurrence.
Incorrect Answers
B:Give senior supplier accountability for supplying necessary skills, technical integrity and resources. Technical resource gaps are escalated through appropriate supplier governance. Issue decisions are formally recorded at the right governance level.
C:Set reporting frequency and content proportionate to information needs and risk. The board receives timely progress forecasts and exceptions while teams receive usable controls. Issue decisions are formally recorded at the right governance level.
D:Translate relevant lessons into owned improvements and monitor completion as part of stage controls. Later stage reports show implemented learning and reduced recurrence. Issue decisions are formally recorded at the right governance level.
Question 582
A project manager needs to diagnose this problem: a health portal project manager approves an issue that would exceed stage cost tolerance. Which investigation is the best initial check? Select ONE answer.
- Inspect the issue record for implementation evidence, retest and stakeholder acceptance
- Check impact forecasts against change budget, tolerances and authorized decision rights
- Compare project forecasts with energy, disposal and social-impact assumptions
- Compare consolidated exposure and latest forecasts with stage and project risk tolerances
Explanation
Correct Answer
B:The strongest first investigation is to check impact forecasts against change budget, tolerances and authorized decision rights. Authority depends on impact and delegation, not the loudest requester. If that evidence confirms the issue, the team should route issue decisions to the person or board holding the relevant delegated authority. A subsequent acceptance check should confirm this result: Issue decisions are formally recorded at the right governance level. This check produces evidence before any broad configuration change, avoiding the risky proposal to let any technically knowledgeable team member approve changes beyond project tolerance.
Incorrect Answers
A:Inspect the issue record for implementation evidence, retest and stakeholder acceptance. Decision approval and implemented resolution are different stages of issue management. Issue decisions are formally recorded at the right governance level. The relevant investigation is: Check impact forecasts against change budget, tolerances and authorized decision rights.
C:Compare project forecasts with energy, disposal and social-impact assumptions. The approved justification includes monitored sustainability indicators and credible tradeoffs. Issue decisions are formally recorded at the right governance level. The relevant investigation is: Check impact forecasts against change budget, tolerances and authorized decision rights.
D:Compare consolidated exposure and latest forecasts with stage and project risk tolerances. Risk governance requires clear boundaries between routine response and exception. Issue decisions are formally recorded at the right governance level. The relevant investigation is: Check impact forecasts against change budget, tolerances and authorized decision rights.
Question 583
The project team has corrected a reported weakness: a health portal project manager approves an issue that would exceed stage cost tolerance. Which acceptance result should the owner require? Select ONE answer.
- User needs and benefits are represented in acceptance decisions and board direction
- Commercial decisions support project objectives and have traceable approval evidence
- Issue decisions are formally recorded at the right governance level
- Each major decision and delivery obligation maps to a competent accountable role
Explanation
Correct Answer
C:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to maintain a current delegation matrix for changes and exceptions. The decisive acceptance evidence is this result: Issue decisions are formally recorded at the right governance level. Authority depends on impact and delegation, not the loudest requester. The operating team should diagnose it by checking whether it can check impact forecasts against change budget, tolerances and authorized decision rights, then route issue decisions to the person or board holding the relevant delegated authority where justified.
Incorrect Answers
A:User needs and benefits are represented in acceptance decisions and board direction. Issue decisions are formally recorded at the right governance level.
B:Commercial decisions support project objectives and have traceable approval evidence. Contracts and project governance must align so the board can control risk and value. Issue decisions are formally recorded at the right governance level.
D:Each major decision and delivery obligation maps to a competent accountable role. Issue decisions are formally recorded at the right governance level.
Question 584
The team has remediated this situation: a health portal project manager approves an issue that would exceed stage cost tolerance. What maintenance control most directly reduces repeat failures? Select ONE answer.
- Review supplier capacity and competence before each stage commitment
- Refresh forecasts and assumptions at defined progress checkpoints
- Reconcile team plans and work packages whenever delivery methods or dependencies change
- Maintain a current delegation matrix for changes and exceptions
Explanation
Correct Answer
D:It complements, rather than replaces, the immediate administrative action to route issue decisions to the person or board holding the relevant delegated authority and diagnostic evidence to check impact forecasts against change budget, tolerances and authorized decision rights. Periodic testing should confirm this result: Issue decisions are formally recorded at the right governance level. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to maintain a current delegation matrix for changes and exceptions. Authority depends on impact and delegation, not the loudest requester.
Incorrect Answers
A:Review supplier capacity and competence before each stage commitment. Technical resource gaps are escalated through appropriate supplier governance. Issue decisions are formally recorded at the right governance level. To avoid recurrence, maintain a current delegation matrix for changes and exceptions.
B:Refresh forecasts and assumptions at defined progress checkpoints. The relevant authority receives an exception forecast before delegation limits are exceeded. Issue decisions are formally recorded at the right governance level. To avoid recurrence, maintain a current delegation matrix for changes and exceptions.
C:Reconcile team plans and work packages whenever delivery methods or dependencies change. Teams may plan work flexibly but cannot unilaterally change authorized product acceptance. Issue decisions are formally recorded at the right governance level. To avoid recurrence, maintain a current delegation matrix for changes and exceptions.
Question 585
The service owner is reviewing actions after this report: a health portal project manager approves an issue that would exceed stage cost tolerance. Which proposed bypass would undermine the relevant security control? Select ONE answer.
- Let any technically knowledgeable team member approve changes beyond project tolerance
- Assess likelihood, impact and proximity consistently against agreed risk criteria
- Specify measurable product quality criteria, methods and responsibilities before acceptance
- Prepare structured stage or exception reports showing performance, causes, lessons and forward choices
Explanation
Correct Answer
A:The unsafe shortcut is to let any technically knowledgeable team member approve changes beyond project tolerance. Authority depends on impact and delegation, not the loudest requester. The defensible response is instead to route issue decisions to the person or board holding the relevant delegated authority, using the diagnostic step to check impact forecasts against change budget, tolerances and authorized decision rights before changing settings. Afterward, the team should confirm this result: Issue decisions are formally recorded at the right governance level. It must maintain the safeguard to maintain a current delegation matrix for changes and exceptions.
Incorrect Answers
B:Assess likelihood, impact and proximity consistently against agreed risk criteria. Risk ratings distinguish priority exposures and support defensible response decisions. Issue decisions are formally recorded at the right governance level. The shortcut most directly implicated here is: Let any technically knowledgeable team member approve changes beyond project tolerance.
C:Specify measurable product quality criteria, methods and responsibilities before acceptance. Quality expectations must become testable acceptance evidence. Issue decisions are formally recorded at the right governance level. The shortcut most directly implicated here is: Let any technically knowledgeable team member approve changes beyond project tolerance.
D:Prepare structured stage or exception reports showing performance, causes, lessons and forward choices. The project board can decide continuation or recovery using a credible report. Issue decisions are formally recorded at the right governance level. The shortcut most directly implicated here is: Let any technically knowledgeable team member approve changes beyond project tolerance.
Question 586
A PRINCE2 project manager receives this situation: a rail asset team sends an in-tolerance change to the funding minister rather than its delegated change authority. Which targeted corrective action should be chosen? Select ONE answer.
- Record estimate assumptions and uncertainty and build realistic contingency and risk responses
- Route issue decisions to the person or board holding the relevant delegated authority
- Close issues only when authorized decisions are implemented and their outcomes verified
- Prioritize issues according to severity, product impact, urgency and approved tolerances
Explanation
Correct Answer
B:First, check impact forecasts against change budget, tolerances and authorized decision rights. Route issue decisions to the person or board holding the relevant delegated authority. Authority depends on impact and delegation, not the loudest requester. Success requires: Issue decisions are formally recorded at the right governance level. Repeating maintain a current delegation matrix for changes and exceptions helps prevent recurrence. By contrast, the response tied to this evidence is: Route issue decisions to the person or board holding the relevant delegated authority.
Incorrect Answers
A:Record estimate assumptions and uncertainty and build realistic contingency and risk responses. The plan shows defensible estimates and tolerances consistent with identified uncertainty. Issue decisions are formally recorded at the right governance level.
C:Close issues only when authorized decisions are implemented and their outcomes verified. Decision approval and implemented resolution are different stages of issue management. Issue decisions are formally recorded at the right governance level.
D:Prioritize issues according to severity, product impact, urgency and approved tolerances. High-consequence issues are addressed or escalated before lower-impact work. Issue decisions are formally recorded at the right governance level.
Question 587
A support engineer investigates this project governance report: a rail asset team sends an in-tolerance change to the funding minister rather than its delegated change authority. Which comparison should be made first? Select ONE answer.
- Compare the issue proposal with authorized baselines and affected product descriptions
- Compare delivered products and support materials with approved acceptance and transition criteria
- Check impact forecasts against change budget, tolerances and authorized decision rights
- Review assumptions, lessons and expert input for omitted causes, events and effects
Explanation
Correct Answer
C:The strongest first investigation is to check impact forecasts against change budget, tolerances and authorized decision rights. Authority depends on impact and delegation, not the loudest requester. If that evidence confirms the issue, the team should route issue decisions to the person or board holding the relevant delegated authority. A subsequent acceptance check should confirm this result: Issue decisions are formally recorded at the right governance level. This check produces evidence before any broad configuration change, avoiding the risky proposal to let any technically knowledgeable team member approve changes beyond project tolerance. By contrast, the response tied to this evidence is: Check impact forecasts against change budget, tolerances and authorized decision rights.
Incorrect Answers
A:Compare the issue proposal with authorized baselines and affected product descriptions. Change control protects overall project viability rather than only the altered feature. Issue decisions are formally recorded at the right governance level. The relevant investigation is: Check impact forecasts against change budget, tolerances and authorized decision rights.
B:Compare delivered products and support materials with approved acceptance and transition criteria. Receiving owners confirm the product is acceptable and usable in live operations. Issue decisions are formally recorded at the right governance level. The relevant investigation is: Check impact forecasts against change budget, tolerances and authorized decision rights.
D:Review assumptions, lessons and expert input for omitted causes, events and effects. The risk register covers material exposures with described causes and impacts. Issue decisions are formally recorded at the right governance level. The relevant investigation is: Check impact forecasts against change budget, tolerances and authorized decision rights.
Question 588
An auditor asks how to validate resolution of this situation: a rail asset team sends an in-tolerance change to the funding minister rather than its delegated change authority. Which direct evidence is strongest? Select ONE answer.
- The plan covers required products in a logical sequence with explicit quality expectations
- Material risks receive timely authority decisions and minor exposures stay appropriately delegated
- Material responses are implemented and monitored by identifiable responsible people
- Issue decisions are formally recorded at the right governance level
Explanation
Correct Answer
D:A status banner or closed ticket is not equivalent to this end-to-end outcome. The enduring safeguard is to maintain a current delegation matrix for changes and exceptions. The decisive acceptance evidence is this result: Issue decisions are formally recorded at the right governance level. Authority depends on impact and delegation, not the loudest requester. The operating team should diagnose it by checking whether it can check impact forecasts against change budget, tolerances and authorized decision rights, then route issue decisions to the person or board holding the relevant delegated authority where justified. By contrast, the response tied to this evidence is: Issue decisions are formally recorded at the right governance level.
Incorrect Answers
A:The plan covers required products in a logical sequence with explicit quality expectations. Issue decisions are formally recorded at the right governance level.
B:Material risks receive timely authority decisions and minor exposures stay appropriately delegated. Risk governance requires clear boundaries between routine response and exception. Issue decisions are formally recorded at the right governance level.
C:Material responses are implemented and monitored by identifiable responsible people. Issue decisions are formally recorded at the right governance level.
Question 589
The project executive wants lasting assurance after this event: a rail asset team sends an in-tolerance change to the funding minister rather than its delegated change authority. Which preventive practice should be adopted? Select ONE answer.
- Maintain a current delegation matrix for changes and exceptions
- Review aggregated change spending and residual budget during stage controls
- Confirm operational ownership as part of closeout and business case updates
- Re-estimate each succeeding stage with fresh delivery information
Explanation
Correct Answer
A:It complements, rather than replaces, the immediate administrative action to route issue decisions to the person or board holding the relevant delegated authority and diagnostic evidence to check impact forecasts against change budget, tolerances and authorized decision rights. Periodic testing should confirm this result: Issue decisions are formally recorded at the right governance level. Any exception should be corrected before it becomes normal operation. The recurring safeguard is to maintain a current delegation matrix for changes and exceptions. Authority depends on impact and delegation, not the loudest requester. By contrast, the response tied to this evidence is: Maintain a current delegation matrix for changes and exceptions.
Incorrect Answers
B:Review aggregated change spending and residual budget during stage controls. Change expenditure stays within authority and project forecasts reflect cumulative commitments. Issue decisions are formally recorded at the right governance level. To avoid recurrence, maintain a current delegation matrix for changes and exceptions.
C:Confirm operational ownership as part of closeout and business case updates. Handover records identify accountable owners and scheduled benefit reviews after closure. Issue decisions are formally recorded at the right governance level. To avoid recurrence, maintain a current delegation matrix for changes and exceptions.
D:Re-estimate each succeeding stage with fresh delivery information. The next stage has a realistic plan approved by the appropriate authority. Issue decisions are formally recorded at the right governance level. To avoid recurrence, maintain a current delegation matrix for changes and exceptions.
Question 590
An operator suggests skipping safeguards after this event: a rail asset team sends an in-tolerance change to the funding minister rather than its delegated change authority. Which action should be ruled out? Select ONE answer.
- Refresh life-cycle costs, assumptions and the investment justification before requesting commitment
- Let any technically knowledgeable team member approve changes beyond project tolerance
- Tailor planning levels and product controls for the delivery methods while keeping board commitments visible
- Define benefits, owners, measurement timing and dependencies in the updated business case and benefits management approach
Explanation
Correct Answer
B:The unsafe shortcut is to let any technically knowledgeable team member approve changes beyond project tolerance. Authority depends on impact and delegation, not the loudest requester. The defensible response is instead to route issue decisions to the person or board holding the relevant delegated authority, using the diagnostic step to check impact forecasts against change budget, tolerances and authorized decision rights before changing settings. Afterward, the team should confirm this result: Issue decisions are formally recorded at the right governance level. It must maintain the safeguard to maintain a current delegation matrix for changes and exceptions. By contrast, the response tied to this evidence is: Let any technically knowledgeable team member approve changes beyond project tolerance.
Incorrect Answers
A:Refresh life-cycle costs, assumptions and the investment justification before requesting commitment. The board considers a transparent forecast with affordable funding and defensible benefits. Issue decisions are formally recorded at the right governance level. The shortcut most directly implicated here is: Let any technically knowledgeable team member approve changes beyond project tolerance.
C:Tailor planning levels and product controls for the delivery methods while keeping board commitments visible. Stage commitments use reliable forecasts without constraining justified team-level iterations. Issue decisions are formally recorded at the right governance level. The shortcut most directly implicated here is: Let any technically knowledgeable team member approve changes beyond project tolerance.
D:Define benefits, owners, measurement timing and dependencies in the updated business case and benefits management approach. Approved benefit measures can be traced to users, data sources and review dates. Issue decisions are formally recorded at the right governance level. The shortcut most directly implicated here is: Let any technically knowledgeable team member approve changes beyond project tolerance.